Inside the City of Ukiah, the Building Services Division of the Community Development Department reviews plans, issues building, electrical, plumbing and mechanical permits and inspects the work; Matt Keizer is the Chief Building Official. Applications go through the city’s CitizenServe portal or the counter at City Hall (707-467-5786), plan check takes 10 to 15 business days, and small residential jobs can be approved the same day at Rapid Review on Tuesday and Thursday mornings. Building permit fees are based on project valuation, from $105 for work up to $500.
What requires a building permit in Ukiah?
The Building Services FAQ answers the common questions directly. A new roof needs a permit, as do replacement windows even when the opening stays the same size, dry rot repair, decks attached to a house and any deck repair that replaces decking, joists, beams, stairs, guards or the connection to the house. Panel upgrades, water heaters, furnaces and air conditioners also need permits, though they are issued over the counter.
Permit required
- Reroofing (same-day over-the-counter permit)
- Window replacement, including same-size dual-glazed units
- Dry rot repair, usually with a copy of the termite report
- Attached decks and structural deck repairs
- Hardwired spas and hot tubs (spa, electrical and plumbing permits)
- Rooftop solar, after pre-approval
- Fences over 7 feet, after a use permit
- Demolition, with extra review for buildings over 50 years old
No building permit
- Fences 7 feet or lower (zoning height and setback limits still apply)
- Detached decks up to 200 square feet and no more than 30 inches above grade that do not serve an exit door
- Cord-connected spas, apart from any new electrical work they need
- Landscaping and minor grading for landscaping
A kitchen remodel needs a permit once framing, electrical, mechanical or plumbing systems are altered or the cabinets come out; the city then asks for three sets of plans at least 11 by 17 inches, drawn at 1/4 inch to the foot, with existing and proposed floor plans and a lighting plan. Every water heater installation or replacement needs a permit and a final inspection. Even a deck that needs no building permit goes through Planning review for its location on the lot. Drainage disputes between neighbors are a civil matter, not a Building Services issue.
What Ukiah decides and what the state holds
The city sets its own design values: seismic design categories D and E, a 110 mph wind speed with exposure B or C, no snow load below 1,300 feet of elevation, and a 1.5-inch 60-minute rainfall. It also sets its fees, zoning, ADU ordinance and demolition review rules, and its Electric Department sets meter requirements. Contractor licensing and the building standards themselves are state matters.
Short on time to read all of this?
Get a free quote →Ukiah building department: who handles permitting
The Building Services Division handles plan review, permit issuance and field inspections for residential and commercial work inside the city limits, enforcing local and state rules on construction, rehabilitation and accessibility. Planning Services reviews zoning, setbacks and use permits. Land outside the city is permitted by Mendocino County Planning and Building Services in Ukiah.
| Detail | Information |
|---|---|
| Building Division | Community Development, City Hall, 300 Seminary Avenue; 707-467-5786; buildingdivision@cityofukiah.com |
| Chief Building Official | Matt Keizer, 707-467-5718 |
| Permit issuance hours | Monday to Friday, 8:00 to 11:30 a.m. and 1:00 to 4:30 p.m. |
| Inspection line | 707-463-6739; inspections Monday to Friday, 8:00 a.m. to noon and 1:00 to 4:00 p.m. |
| Rapid Review | Tuesday and Thursday, 8:30 to 10:00 a.m., by appointment at 707-467-5786 |
| Planning Services | 707-463-6203 |
| Online portal | CitizenServe |
| Outside the city | Mendocino County Building Division |
Ukiah permit types
Every job starts with the city’s building permit application, which carries the licensed contractor, owner-builder and workers’ compensation declarations. The division also publishes a release of property information form, a notice to property owner, a special inspection agreement, a generator checklist and application, and residential and commercial acceptance checklists.
Residential permits
- Over-the-counter permits need no plan review: reroofs, water heater, furnace and air conditioner replacements, panel upgrades and other minor repairs. The city’s handouts cover reroofing, water heaters, panel upgrades, bathroom and kitchen remodels and decks.
- Rapid Review gives same-day review by Public Works, Electric, Fire, Planning and Building staff for kitchen and bathroom remodels, decks under two stories, patio covers, sheds, landscaping structures, small renovations and EV chargers. An appointment is required.
- New homes and additions need three sets of construction plans, from cover sheet and site plan through foundation, framing, electrical, plumbing and mechanical plans, four elevations and energy calculations bound into the set.
- ADUs follow the city’s ADU and junior ADU articles, updated in 2025. The city offers three free pre-approved plans: a 534-square-foot one-bedroom Cottage, a 748-square-foot two-bedroom Clerestory and an 832-square-foot two-bedroom Bungalow, which still need a site-specific site plan. An ADU needs fire sprinklers only if the main house has them.
Building or remodeling a home here? Alliance handles home building permits, so the crew isn't waiting on the counter.
Not sure this scope needs a permit?
Get a free quote →Commercial permits
Tenant improvements need five sets of plans at least 24 by 36 inches, drawn to scale, with a cover sheet showing occupancy, construction type, occupant load, sanitation and accessibility. The city recommends plans by a California-licensed engineer or architect and an evaluation by a certified access specialist before design. A commercial demolition permit is not issued until the Mendocino County Air Quality Management District has cleared asbestos.
For tenant improvements and new commercial builds, Alliance handles commercial permit filing through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Planning approval: plans must match any use permit or site development permit, with the Planning agreement letter, conditions and mitigation measures bound into the set.
- Demolition review: a building over 50 years old may go to the Demolition Permit Review Committee, which advises the City Council on historic or architectural significance under Section 3016 of the Ukiah City Code; the council decides whether the permit can issue.
- Right-of-way: work in a city street or sidewalk needs a Public Works encroachment permit before it starts.
- County health review: where a project needs Mendocino County Environmental Health approval, the applicant files directly with that department.
- Utilities: a new or upgraded service needs an Electric Department meter box with a ring-type meter socket.
Ukiah building permit fees
The Building Division posts its building fee table and a separate mechanical, electrical and plumbing fee table on its Permit Fees tab; neither sheet carries an adoption date or resolution number, so ask the division whether a newer schedule applies before you budget. Fees follow the total valuation of the work plus the trade items on the permit.
| Valuation | Building permit fee |
|---|---|
| $1 to $500 | $105 |
| $501 to $2,000 | $105 for the first $500 plus $4.75 per additional $100 |
| $2,001 to $25,000 | $107.62 for the first $2,000 plus $21.76 per additional $1,000 |
| $25,001 to $50,000 | $608.78 for the first $25,000 plus $15.69 per additional $1,000 |
| $50,001 to $100,000 | $1,000.38 for the first $50,000 plus $10.88 per additional $1,000 |
| $100,001 to $500,000 | $1,545.04 for the first $100,000 plus $8.55 per additional $1,000 |
| $500,000 to $1,000,000 | $5,025.24 for the first $500,000 plus $7.38 per additional $1,000 |
| Over $1,000,000 | $8,715.99 for the first $1,000,000 plus $5.67 per additional $1,000 |
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee |
|---|---|
| Work started without a permit (red-tagged) | Permit fee plus 3 times the permit fee |
| Reinspection, unlisted inspection or added plan review | $105, or the city’s full hourly cost if greater |
| After-hours inspection | $105 an hour, two-hour minimum |
| Issuance of each electrical, plumbing or mechanical permit | $105 |
| Electrical service up to 200 amps / 200 to 1,000 amps | $54.18 / $110.38 |
| New one- or two-family home, electrical | $0.96 per square foot |
| Plumbing fixture / water heater / building sewer | $17.41 / $21.84 / $43.78 |
| Furnace up to 100,000 Btu/h | $26.29 |
| Residential solar permit | $368.50 |
| Demolition permit (2019 packet) | $50, plus utility or encroachment charges |
Worked example: a project valued at $80,000 falls in the $50,001 to $100,000 band, so the building permit fee is $1,000.38 plus 30 times $10.88, or $1,326.78, before any electrical, plumbing or mechanical items. The lower bands on the table do not join exactly (the $501 to $2,000 band reaches $176.25 at $2,000, while the next band starts from $107.62), so use the band your valuation actually falls in. The residential submittal handout charges $52.17 an hour for plans that need more than one resubmittal, while the fee table lists $105 for added plan review; ask which applies to your job. Outside consultants used for plan check or inspection are billed at actual cost.
Rather not deal with the building department?
Get a free quote →Trade permits and who may pull them in Ukiah
The Building Services Division issues the electrical, plumbing and mechanical permits, each with a $105 issuance fee plus unit fees for outlets, fixtures and equipment. Panel upgrades must meet the division’s service-entrance handout, including two ground rods where driven rods are used, unless the system is shown to meet the 25-ohm limit, and the Electric Department meter requirements. Rooftop solar needs pre-approval before the building permit, and the city offers expedited permits for small residential systems.
The application form asks a licensed contractor for the license class and number, or an owner for the owner-builder declaration explaining the exemption from contractor licensing; residential submittals add the owner-builder disclosure form where it applies. The city’s ADU page tells owners they may act as owner-builders or hire a licensed contractor, and recommends a contractor for complex or multi-trade work.
How to apply for a Ukiah building permit
Call Planning Services for setbacks, fence heights or any use permit, and get discretionary approvals first.
Bring simple replacements to the counter for an over-the-counter permit, book Rapid Review for small remodels, or prepare a full plan set.
Use the residential or commercial submittal document: sheets no larger than 24 by 36 inches, numbered, dated and wet-signed.
Upload the application and plans in CitizenServe, or file at City Hall during permit issuance hours.
Plan check takes 10 to 15 business days; revise and resubmit any corrections.
Pay the fees, collect the permit and call 707-463-6739 for the first inspection on the permit card.
Review, corrections and what causes delay
Plans that are not drawn to scale or lack the required sheets slow review, and the city expects plans to match any approved use permit exactly. Engineering, energy and soils reports go in as two sets, wet-stamped by the responsible California professional where the Building Official, plans examiner, City Engineer or Fire Chief requires it. A plan that needs more than one resubmittal is charged for the extra review. Complete ADU applications are reviewed within 60 days, depending on complexity.
Ukiah building inspections
The inspections required are printed on your copy of the permit, and all work must be inspected before it is covered; footings, for example, are checked after excavation and steel placement and before the pour. Schedule or cancel on the inspection line, 707-463-6739. The FAQ gives two notice periods: one answer asks for at least 48 hours and another says 24 hours, so book two days ahead to be safe. Inspectors work Monday to Friday, 8:00 a.m. to noon and 1:00 to 4:00 p.m.
Want this handled start to finish?
Get a free quote →For a water heater, inspectors look for two seismic straps placed in the top and bottom thirds of the tank, a temperature and pressure relief line piped outdoors to end 6 to 24 inches above grade, protection from vehicles in a garage, and a drain pan where the heater sits in or above living space. Reinspections, inspections outside normal hours and inspections not otherwise listed cost $105 each, with a two-hour minimum after hours. On a demolition, all utilities must be shut off and capped to the satisfaction of city staff before the work proceeds.
California building code in Ukiah
The Building Services page still lists the 2022 California codes as adopted; applications filed since January 1, 2026 fall under the 2025 code, so ask the Building Official about any amendments in the Ukiah City Code. FEMA’s Community Status Book lists the City of Ukiah (community 060186) as participating in the National Flood Insurance Program, with flood maps effective September 19, 2025.
California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Ukiah permit search and official resources
To find out whether a permit exists for a property, contact the Building Division at 707-467-5786 or buildingdivision@cityofukiah.com with the street address, because permits are filed by address.
- Ukiah Building Services Division
- CitizenServe permit portal
- Building permit fee table
- Mechanical, electrical and plumbing fees
- Building permit application
- Residential building permit submittal documents
- Tenant improvement submittal requirements
- Residential decks handout
- Demolition permit packet, buildings over 50 years old
- Accessory dwelling units and pre-approved plans
- FEMA Community Status Book, California
Inspections are where schedules slip.
Get a free quote →Ukiah building permit FAQs
How long does plan check take in Ukiah?
The city says 10 to 15 business days; small residential projects can be approved the same day at Rapid Review.
Do I need a permit to replace windows?
Yes, even for same-size replacements; it is issued over the counter with a simple floor plan on letter-size paper.
Do I need a permit for a fence?
Not for a fence 7 feet or lower. A taller fence needs a use permit, then a building permit with plans by a licensed architect or engineer.
Is a reroof permit quick?
Yes. Residential reroof permits are same-day, over-the-counter permits priced on the value of labor and materials. A new roof can go over only one existing layer; if there are already two layers, both must be stripped.
Are there free ADU plans?
Yes. Three pre-approved plans from 534 to 832 square feet are free; you add a site plan for your lot.
Can I demolish an old house?
A building over 50 years old may need review by the Demolition Permit Review Committee and a City Council decision before the permit issues.
Does Ukiah issue permits outside the city?
No. Unincorporated land around Ukiah is permitted by Mendocino County Planning and Building Services.
Simplify Ukiah permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Ukiah sooner?
Let Alliance prepare, file, and track your Ukiah permits while your crew stays on the job.
More California permitting guides
Mendocino County
Read guide →Lake County
Read guide →Sonoma County
Read guide →Union City Building Permit Guide
Read guide →Upland Building Permit Guide
Read guide →Vacaville Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Ukiah permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.