Pleasant Hill, California Building Permit Guide

To get a building permit in Pleasant Hill, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Pleasant Hill’s Building Division at City Hall, 100 Gregory Lane, issues building and trade permits through the PHill Online Service Center, where applicants also pay fees and book inspections.

Authority: City of Pleasant Hill Building DivisionFiling: PHill Online Service CenterPhone: (925) 671-5200
Authority
City Building Division100 Gregory Lane, Pleasant Hill
Apply
PHill Online Service CenterAccount required
Plan check
80% of permit fee50% deposit before review
Permit life
180 daysRestarts with each approved inspection

Building permits in Pleasant Hill come from the City’s own Building Division at City Hall, 100 Gregory Lane ((925) 671-5200), led by Chief Building Official Geoff Simmons. Applications, plans, payments and inspection requests all go through the PHill Online Service Center. Under the Master Fee Schedule effective September 1, 2026, plan check is 80% of the building permit fee, and jobs that need plan review are invoiced a deposit of half the permit fee before review starts.

What requires a building permit in Pleasant Hill?

The Building Division’s short rule is that any work that physically changes or adds structures on a property needs a permit, and it invites calls to (925) 671-5200 when in doubt. Its FAQs settle the common borderline cases.

Building permit needed

  • Decks more than 30 inches above adjacent grade, new or replacement
  • Window or door work that removes any part of the frame, exterior siding or interior drywall
  • Front doors, garage doors and interior fire-rated doors
  • Re-roofs, and the electrical upgrades required whenever any part of a kitchen is remodeled
  • Any shed or accessory structure that will have electricity, whatever its size
  • Demolition of a structure, after the Bay Area Air Quality Management District issues a J number

No building permit

  • Decks not more than 30 inches above grade (Planning still reviews every deck)
  • Retrofit windows, and kitchen cabinets, countertops and backsplashes
  • One-story tool or storage sheds and playhouses up to 120 square feet (a Planning zoning permit is still needed)
  • Driveways, pathways and patios at ground level (an encroachment permit if work reaches the street, curb or gutter)

Planning’s fee schedule shows where zoning permits come in even without a building permit: fences and walls need a zoning permit at no charge, and an accessory structure that needs no building permit takes a $92 zoning permit.

What Pleasant Hill decides and what the state holds

The City runs its own building department, so it sets plan check practice, inspection rules, fees and the hours of construction: Monday to Friday 7:30 a.m. to 7 p.m., and weekends 9 a.m. to 6 p.m., under section 9.15.040 of the municipal code (emergency work excepted). The Building Division moved from the 2022 to the 2025 California code set on January 1, 2026. Zoning, ADU rules (Pleasant Hill Municipal Code section 18.15.050), design review and tree permits belong to the Planning Division; fire review belongs to Contra Costa County Fire and sewer connections to Central Contra Costa Sanitary District.

Pleasant Hill building department: who handles permitting

The Building Division in the Community Development Department issues building, electrical, mechanical and plumbing permits for all property inside city limits. Planning reviews the zoning information on residential applications, and the Engineering Division handles encroachment and grading permits through the same online portal.

Short on time to read all of this?

Get a free quote →
Pleasant Hill permit contacts
OfficeDetails
Building Division100 Gregory Lane, Pleasant Hill, CA 94523; (925) 671-5200; Chief Building Official Geoff Simmons
Building counter hoursMonday–Wednesday 8:30 a.m.–5 p.m.; Thursday 8:30 a.m.–6 p.m.; Friday 8:30 a.m.–1 p.m.; visits can be booked online through QLess
Planning Division(925) 671-5209; planning@phillca.gov
Engineering (encroachment and grading)925-671-5264
Business licenses (Finance)(925) 671-5234

Pleasant Hill permit types

All permit types are applied for in the PHill Online Service Center, part of the permitting and business license system the City brought in during 2024. For residential projects, the City’s Interactive Permit Guide builds a custom list of steps from your address and project details; it is a guide only and does not issue permits.

Residential permits

  • Additions, remodels and new homes. The Residential Building Permit & Zoning Application covers both building and zoning review; setbacks must be measured from property lines, not the sidewalk, curb or fence, and the City publishes kitchen, bathroom and window egress handouts.
  • Re-roofs. A residential re-roof is a $158 flat fee. Comp-to-comp tear-offs get a bare-deck and final inspection, shake-to-comp jobs a deck nailing and final, and overlays (two layers maximum) a final only.
  • Solar. Residential systems through SolarAPP+ are $263; other systems up to 15 kilowatts are $391, plus $15 per kilowatt above that.
  • ADUs. The City offers free pre-approved ADU plans in three sizes, 350, 636 and 798 square feet, that qualify as building-permit-only ADUs, though outside agency clearances are still needed.

Commercial permits

The owner of a commercial property cannot pull a building permit; a contractor must be listed on every commercial permit and pulls it. Tenant improvements need Central San and fire district approval, and food-service tenant improvements also go through Engineering. Commercial projects use the Commercial Building Permit & Zoning Application, and Planning’s commercial plan check fee is $427, collected with the building permit fees.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Planning and zoning. Site plan and architectural review where needed, Planning review of every deck whatever its height, and a zoning permit for fences, walls, small sheds and new or relocated businesses.
  • Engineering. Drainage, clean-water (NPDES) and FEMA floodplain review, and an encroachment permit for any work in the public right-of-way, such as curb, gutter, driveway or sewer lateral work.
  • Outside agencies. Central Contra Costa Sanitary District when adding a bathroom or for any tenant improvement; Contra Costa County Fire for tenant improvements; the Flood Control District, water district and County Environmental Health where the project calls for them.
  • School fees. Mt. Diablo Unified School District fees apply when adding 500 square feet or more to a house or building an ADU of 750 square feet or more.
  • Demolition. A Bay Area Air Quality Management District J number before the Building Division will review demolition plans.

Pleasant Hill permit costs and fees

Building fees come from the City’s Master Fee Schedule effective September 1, 2026; the Planning Division’s fee list gives the adopting resolution as No. 44-26, while the master schedule leaves the number blank. Fees may change each year with the San Francisco-Oakland-San Jose consumer price index.

Pleasant Hill building fees (effective September 1, 2026)
ItemFee
Valuation $2,001 to $25,000$144 for the first $2,000 plus $18 per added $1,000
Valuation $25,001 to $50,000$745 for the first $25,000 plus $12 per added $1,000
Valuation $50,001 to $100,000$1,243 for the first $50,000 plus $9 per added $1,000
Valuation $100,001 to $500,000$1,895 for the first $100,000 plus $4 per added $1,000
Submittal deposit / plan check50% of the permit fee / 80% of the building permit fee
Electrical / mechanical / plumbing permits16% / 12% / 14% of the building permit fee (minimums $195 / $158 / $158)
Residential re-roof$158
Title 24 insulation inspection (underfloor, or walls and attic)$152
Re-inspection$206 per hour
General Plan update fee0.0023 × construction valuation
Planning plan check (collected with building fees)$213 residential; $427 commercial
Zoning permit: fences and walls / accessory structure without a building permit$0 / $92
Tree removal permit$166 (hourly over five trees)
Work without a permit (investigation)$293

Rather talk it over?

Call 1-855-478-4290 →

Worked example from the table: a remodel valued at $80,000 falls in the $50,001 to $100,000 band, so the building permit fee is $1,243 plus 30 × $9, or $1,513. Plan check at 80% adds $1,210.40, and the 50% submittal deposit due before review is $756.50. The bands do not join up neatly (the formula for the band below gives $558 at $25,000, while the next band starts at $745), so always use the band your valuation falls in.

Engineering charges for encroachment permits on residential work are a $168 processing fee plus $168 for each hour of inspection: the schedule estimates about 2 hours for curb and gutter repair, 3 hours for a driveway installation and 2½ hours for a sewer lateral repair, while a homeowner repairing their own sidewalk pays nothing. An ADU that needs only Planning approval and no building permit carries a $1,060 zoning fee, and pre-application zoning consultations are billed at $213 an hour after the first hour.

Trade permits and who may pull them

The Building Division issues electrical, mechanical and plumbing permits, priced as a share of the building permit fee when they go with building work. Minimum permits for an upgrade to an existing system are $195 for electrical and $158 each for mechanical and plumbing, and a temporary power service is $195.

A business license is required to work in Pleasant Hill, including for independent contractors and for businesses whose office is outside the city, and the residential application asks for the contractor’s Pleasant Hill business license number with the CSLB license. Homeowners can file as owner-builders on residential work using the declaration on the application; on a residential permit that lists a contractor, the City releases the permit and plans only to the contractor, whose signature is required. Commercial permits must always be pulled by a contractor.

Rather not deal with the building department?

Get a free quote →

How to apply for a building permit in Pleasant Hill

1. Map out the steps

Run the Interactive Permit Guide for a residential project, or book a visit with the Building Division through QLess.

2. Create an account

Register in the PHill Online Service Center; contractors can submit once registration is complete.

3. Upload the application and plans

Use the residential or commercial building permit and zoning application, the electronic plan submittal requirements and a scaled plot plan.

4. Pay the deposit

Jobs needing plan review are invoiced 50% of the permit fee; review starts once payment is confirmed.

5. Make corrections

Correction notices go to the email on the application; upload revised plans to the portal.

6. Pay the balance and get the permit

When review is complete, the City notifies you of the fees due, which can be paid online.

Review, corrections and what causes delay

The City’s FAQ puts typical residential plan review at 2 to 3 days. Electronic submittals follow the same review as paper ones and are not expedited. For some types of work the plot plan must be stamped “approved for construction” by each outside agency involved, such as Central San or the fire district, before the permit is issued, and demolition waits for the air district J number. A permit expires 180 days after issue, but the clock restarts after each approved inspection; a single six-month extension can be requested in writing before expiry, and an expired permit costs 50% of the original fee to reinstate.

Inspections in Pleasant Hill

Inspections are scheduled in the PHill Online Service Center, and the day’s inspection list can be checked there after 8:30 a.m.; the City’s FAQ also says to call (925) 671-5200 a day ahead to be added to the next day’s schedule. Re-inspections are billed at $206 an hour, and insulation inspections under the energy code are $152 each.

Any addition, remodel or new construction must include smoke detectors in each bedroom and hallway and a carbon monoxide detector in the home. Window and door replacements that need a permit get a flashing inspection and a final. Re-roofs have no in-progress inspection: the inspector sees the bare deck or the deck nailing, depending on the roof, and then the final. A certificate of occupancy without a change of occupancy costs $263, and a new address or suite number $368. Work must stay within the City’s construction hours on weekdays and weekends.

Projects that need special inspection under the building code file a Special Inspection and Testing Agreement, and the City publishes a list of recognized special inspection and testing agencies. Encroachment and grading work is inspected by Engineering under its own permits, and Engineering keeps a five-year street moratorium list for cuts in resurfaced streets.

Want this handled start to finish?

Get a free quote →

California building code in Pleasant Hill

Pleasant Hill enforces the building code through its own Building Division and changed to the 2025 California code set on January 1, 2026. The City keeps FEMA flood insurance rate maps at City Hall, the library and on its website for checking flood zones. FEMA’s Community Status Book lists the City of Pleasant Hill (community 060034) as participating in the National Flood Insurance Program, with maps effective March 21, 2017, and in the Community Rating System at class 9, a 5% discount on flood insurance premiums.

California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments

Pleasant Hill permit search and official resources

To see a property’s permit history and inspection records, visit the Building Division at City Hall and review the address file. Permit holders follow their own applications, invoices and inspections in the PHill Online Service Center. A zoning information letter for a single-family property costs $372.

Inspections are where schedules slip.

Get a free quote →

Pleasant Hill building permit FAQs

Who issues building permits in Pleasant Hill?

The City’s Building Division at 100 Gregory Lane, which also issues electrical, mechanical and plumbing permits.

How long is a building permit valid?

180 days from issue, restarting after each approved inspection, with one six-month extension available on written request.

Do I need a permit for a deck?

Only if it is more than 30 inches above grade, but Planning reviews every deck regardless of height.

Does a shed need a permit?

Not a building permit if it is one story and 120 square feet or less with no electricity, but it needs a Planning zoning permit.

How much is plan check?

80% of the building permit fee, with a deposit of 50% of the permit fee paid before review begins.

Can the owner of a commercial building pull the permit?

No. A contractor must be listed on, and pull, every commercial permit.

Do contractors need a Pleasant Hill business license?

Yes. Anyone doing business in the city needs one, including contractors based elsewhere.

How do I find old permits for a house?

Review the address file at the Building Division in City Hall.

Simplify Pleasant Hill permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Pleasant Hill sooner?

Let Alliance prepare, file, and track your Pleasant Hill permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Pleasant Hill permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.