Pico Rivera, California Building Permit Guide

To get a building permit in Pico Rivera, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Pico Rivera’s Building Division at City Hall, 6615 Passons Boulevard, issues building, electrical, plumbing and mechanical permits inside the city, and most residential work clears a Planning zoning review before plan check.

Authority: Pico Rivera Building DivisionPhone: (562) 801-4360Hours: Mon–Thu 7:30–5
Authority
City Building Division6615 Passons Blvd, Pico Rivera
Apply
Online permit portalExpress permits for simple home jobs
Planning fee
$350.20 habitable addition$175.10 for patios, pools, porches
Plan check
4–6 weeksPer submittal, residential handout

The City of Pico Rivera issues its own building permits through the Building Division at City Hall, 6615 Passons Boulevard ((562) 801-4360), open Monday to Thursday from 7:30 a.m. to 5 p.m. Additions, ADUs, patios and similar residential work need a Planning zoning review first ($350.20 for a habitable addition under the January 2026 handout), building plan check takes about 4 to 6 weeks per submittal, and the division quotes plan check fees when plans are submitted.

What requires a building permit in Pico Rivera?

The Building Division enforces the construction and occupancy rules for every commercial, industrial and residential structure in the city. Its online permit portal sorts work into the permits it issues, and the list shows how broad the requirement is:

Residential

  • Additions, alterations, re-roofing and HVAC work
  • New dwellings, ADUs and junior ADUs
  • Accessory structures: sheds, patios, pools and porches
  • Block walls, fences and pilasters (city permit form)
  • Water heater, wall heater, gas line and panel work
  • Rooftop solar

Non-residential

  • New construction and tenant improvements
  • Alterations, re-roofing and HVAC
  • Fire sprinklers and cell sites
  • Landscape and irrigation
  • Signs
  • Commercial solar

Small storage sheds get lighter treatment: a structure of 120 square feet or less needs Planning approval only, unless it has electricity or plumbing. A shed with windows or doors must sit 10 feet from the side and rear lot lines, and no accessory structure may contain a bathroom.

What Pico Rivera decides and what the state holds

The city controls its zoning standards, design standards for homes (Chapter 18.11.040), its fees and its fence and wall heights. Fire code enforcement follows the Los Angeles County Fire Code (Title 32 of the County Code), which the division lists among the rules plans must meet. The state sets the building code and licenses contractors.

Pico Rivera building department: who handles permitting

The City of Pico Rivera’s Building Division reviews plans and issues building, electrical, mechanical and plumbing permits for property inside the city. The division runs a concurrent plan check program so that reviews can move together, and counter staff help in person during City Hall hours. The city’s agency referral form shows the division under the Public Works Department.

Pico Rivera permit contacts
DetailInformation
Building DivisionCity Hall, 6615 Passons Boulevard, Pico Rivera, CA 90660; (562) 801-4360; Buildingdivision@pico-rivera.org
HoursMonday to Thursday, 7:30 a.m. to 5 p.m.; City Hall is closed on Fridays
Planning(562) 801-4476 (permits and ADUs); (562) 801-4332 (zoning consistency review)
Public Works Engineering(562) 801-4368 for public improvements, driveways and grading
Business licenseRevenue Division, (562) 801-4321
PortalPico Rivera Online Permit: apply, search permits, request inspections and pay

Short on time to read all of this?

Get a free quote →

Pico Rivera permit types

The online permit portal groups applications into express, residential solar, residential, non-residential and Public Works permits. The solar application and inspection requests require a login on the city’s permit site.

Residential permits

  • Express permits. Issued online for a same-location water heater change-out (tank or tankless), gas line repair, wall heater change-out or electrical panel upgrade, only in the single-family, residential estate, multiple-family variable density, planned residential unit development and Specific Plan 301 zones. The contractor needs an active state license and a Pico Rivera business license.
  • Counter permits. Water heater change-outs, electrical upgrades and similar jobs can also be issued at the Building Division counter without plans.
  • Additions. Bedrooms, bathrooms, room expansions, covered patios and some storage sheds need Planning approval and a building permit; full construction plans with Title 24 energy and structural calculations follow the Planning-approved set.
  • ADUs and junior ADUs. Under the January 2026 handout, a new ADU needs 4-foot side and rear setbacks, a detached ADU may be up to 1,000 square feet and is limited to 16 feet and one story, a junior ADU is limited to 500 square feet with owner occupancy and a recorded deed restriction, and a new address requires an address assignment letter. Parking is one space per ADU or per bedroom, whichever is less, and may be tandem on the driveway; it is waived within half a mile walking distance of public transit and in the other cases the handout lists.
  • Rooftop solar. Small single-family rooftop systems approved through SolarAPP+ (a $25 SolarAPP+ fee per project) are usually issued the same day.

Commercial permits

Non-residential permits cover new construction, tenant improvements, alterations, re-roofing, HVAC, fire sprinklers, cell sites, landscape and irrigation, signs and commercial solar. Every business in the city also needs a certificate of occupancy along with its business license: it costs $250, typically takes 30 days, and involves inspections by the fire department, health department, Building Division and Planning. Applicants carry the fire prevention paperwork to the Los Angeles County Fire East Region Fire Prevention office in Irwindale ((626) 430-3050) and return the approval to the Building Division.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Zoning consistency review. Submit the site plan, floor plan and elevations to Planning; the handout gives 2 to 3 weeks.
  • Agency clearances. The agency referral sheet can require a school district developer fee certificate (El Rancho Unified School District, Montebello School District or Whittier City School District), a NASA Services waste management deposit, a Sanitation District sewer connection fee receipt and Pico Water District approval, all filed 48 hours before issuance.
  • Soils report. Required for new buildings, additions to commercial or industrial buildings, second-story and two-story additions and home additions of 1,000 square feet or more, prepared by a licensed geotechnical or civil engineer. A preliminary report is generally enough for a new home on a flat lot; structures on hillside lots (including pools, retaining walls and accessory structures) and larger buildings need a full geotechnical report.
  • Public Works. Driveway approaches, public improvements, water, sewer and storm drain work and grading need a Public Works plan check; excavation, roll-off bins in the street and small wireless facilities need a Public Works permit.

Pico Rivera permit fees

The Building Division calculates fees when an application is submitted, and it does not post a current building fee schedule on its pages. The city’s AB 602 page links its “current list of fees” to a building and safety schedule headed “Proposed, April 2022” for fiscal year 2022–23, with an 8.5% CPI increase. Its proposed figures are shown below; treat them as a guide and get the current amount from the division.

Building fees in the April 2022 schedule (proposed column)
ItemFee
Permit issuance$46
Valuation $2,001 to $25,000$105 plus $16 per $1,000 over $2,001
Valuation $25,001 to $50,000$525 plus $12 per $1,000 over $25,001
Valuation $50,001 to $100,000$867 plus $8.50 per $1,000 over $50,001
Valuation $100,001 to $500,000$1,351 plus $7 per $1,000 over $100,001
Building plan check100% of the building permit fee
Expedited plan checkPermit fee plus 50% of the plan check fee
Combination electrical, plumbing or mechanical permit10% of the building permit fee each
Technology surcharge3% of applicable fees
Plan check extension / permit extension$154 / $97
Demolition permit and inspection$247
Single-family solar, 0 to 10 kW$177

Rather talk it over?

Call 1-855-478-4290 →

Other current figures come from the city’s own pages. Planning’s zoning review for a residential addition is $350.20 for habitable space and $175.10 for non-habitable additions such as pools, patios and porches, and both are doubled when the work is a code enforcement case. The residential handout notes that the permit fee is usually a little more than the plan check fee, that additions over 500 square feet pay school fees, and that projects valued over $100,000 post a waste management deposit. A business certificate of occupancy is $250, and SolarAPP+ charges $25 per solar project.

The AB 602 page says the city has adopted no impact fee study since 2018; it points developers to the park land dedication and in-lieu fees in Sections 17.36.150 to 17.36.270 and to the Public Image Enhancement Program.

Trade permits and who may pull them in Pico Rivera

The Building Division issues the electrical, plumbing and mechanical permits itself. Simple replacements are express permits, and trade work on a larger project can be folded into a combination permit priced at 10% of the building permit fee per trade under the 2022 schedule.

  • Business license. Anyone doing business in the city must have a Pico Rivera business license, and express permit applicants must have the number ready along with the state contractor’s license. Packets are available from the Revenue Division by phone, email, online or at City Hall.
  • Contractors. SolarAPP+ permits require the solar contractor’s name and license number on the city application.
  • Homeowners. The city’s pages do not set out an owner-builder procedure; ask the counter what documents an owner needs before applying.
  • Fire systems. Fire sprinkler permits are filed as non-residential permits, and commercial occupancies need Los Angeles County Fire approval for the certificate of occupancy.

Construction is limited to 7 a.m. to 7 p.m. under the Planning conditions printed on the residential handout.

Rather not deal with the building department?

Get a free quote →

How to apply for a Pico Rivera building permit

1. Check the zone

Use the city’s zoning map and residential handout to confirm setbacks, height and lot coverage.

2. Get Planning approval

Submit the site plan, floor plan and elevations online for zoning review and pay the Planning fee.

3. Submit for plan check

Send full construction plans with structural calculations and Title 24 documents, the approved Planning set and the building permit application.

4. Clear referrals

Return school district, sanitation, water and waste approvals at least 48 hours before issuance.

5. Pay and get the job card

Pay through the portal or at the counter; the applicant is responsible for scheduling inspections.

Review, corrections and what causes delay

The residential handout gives 4 to 6 weeks for each building submittal and resubmittal, after a Planning review of 2 to 3 weeks. Under Government Code 65913.3 the city’s review clock is tolled while an outside agency approval is outstanding, so late school, sanitation or water clearances hold up issuance. Plan checks and permits nearing expiration can be extended with the city’s plan check extension and permit extension request forms.

Inspections in Pico Rivera

Inspections are requested online: log in to the city’s permit site, find the permit number and choose the action to request an inspection. The city’s instructions, written for solar permits, ask for at least 24 hours’ notice and do not guarantee a specific date or time; it notifies you once the inspection is scheduled. The job card issued with the permit stays on site, and the applicant is responsible for scheduling each inspection.

Setbacks are checked with a staked survey. A property line survey by a licensed land surveyor or engineer must be submitted to the inspector before the foundation inspection is approved for new homes, condominiums, apartments and commercial, industrial or institutional buildings, for garages, sheds and guest homes set less than 5 feet from a property line, for additions closer than 5 feet to a line, and for any building built to a setback approved by variance. Block walls and retaining walls do not routinely need one.

A residential project ends with a final inspection. For businesses, the certificate of occupancy process brings in fire, health, building and planning inspections, and the business cannot open until both the certificate and the business license are approved.

California building code in Pico Rivera

The division’s page asks designers to follow Title 15 of the Pico Rivera Municipal Code, the California codes and the Los Angeles County Fire Code; its list still names the 2022 editions, while the state note below gives the edition in force. FEMA’s Community Status Book lists Pico Rivera (community 060148) as participating in the National Flood Insurance Program, with no special flood hazard area shown on its current map.

Want this handled start to finish?

Get a free quote →

California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments

Pico Rivera building permit FAQ

Who issues building permits in Pico Rivera?

The city’s Building Division at 6615 Passons Boulevard, (562) 801-4360. It also issues the electrical, plumbing and mechanical permits.

Do I need Planning approval for a room addition?

Yes. Bedrooms, bathrooms, room expansions, covered patios and some sheds need a Planning zoning review first, which costs $350.20 for habitable space.

Can I get a water heater permit online?

Yes, as an express permit for a same-location replacement in residential zones, or at the counter without plans.

Do I need a permit for a shed?

A shed of 120 square feet or less with no electricity or plumbing needs Planning approval only; larger sheds and those with utilities go through the residential permit process.

How tall can my fence or block wall be?

The city’s permit form limits solid walls in the front setback to 3 feet 6 inches and open fences to 4 feet 6 inches, with up to 7 feet behind the front setback.

How long does plan check take?

About 4 to 6 weeks per building submittal, after 2 to 3 weeks of Planning review, according to the residential handout.

How much does a building permit cost?

The division calculates it at submittal. The fee list linked from the city’s AB 602 page is a proposed April 2022 schedule with plan check at 100% of the permit fee, so ask for a current quote.

How do I schedule an inspection?

Log in to the online permit site, find your permit and request the inspection at least 24 hours ahead.

Pico Rivera permit search and official resources

Permits can be looked up through the Search Permit / Request Inspection tool on the city’s online permit page, which also handles payments. For older records, ask the Building Division counter during City Hall hours.

Inspections are where schedules slip.

Get a free quote →

Simplify Pico Rivera permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Pico Rivera sooner?

Let Alliance prepare, file, and track your Pico Rivera permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Pico Rivera permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.