Lompoc, California Building Permit Guide

To get a building permit in Lompoc, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

The City of Lompoc’s Building and Safety Division takes every permit application digitally through its Customer Self-Service portal, sees the public by appointment Monday to Thursday, and charges $184 for a building permit on work valued up to $2,000.

Authority: City of Lompoc Building and Safety DivisionFiling: Customer Self-Service portal (digital only)Phone: 805-875-8220
Authority
City Building & SafetyCommunity Development Department
Hours
Mon–Thu 9 a.m.–4:30 p.m.By appointment only
Inspections
805-875-8231Or book in the permit portal
Fees
Master Fee ScheduleEffective Feb. 5, 2024, amended Mar. 8, 2024

Lompoc issues its own building permits through the Building and Safety Division of the Community Development Department. Applications and corrected plans go in digitally through the city’s Customer Self-Service portal, and staff work Monday to Thursday, 9 a.m. to 4:30 p.m., by appointment (805-875-8220, building@ci.lompoc.ca.us). Fees come from the Master Fee Schedule adopted as Resolution No. 6620(23), effective February 5, 2024 and amended March 8, 2024: on a $50,000 job the building permit fee is $1,894 and plan check $1,628.

What requires a building permit in Lompoc?

The division describes its service as one-stop permitting for building, fire and development needs, and its Permits page sets out when building, mechanical, plumbing and electrical permits are required. The fee schedule shows the work it permits and the limits it applies:

Permit required

  • New buildings, additions and alterations, priced by job valuation
  • Mechanical, electrical and plumbing work, priced in six categories
  • Grading, drainage and parking lot improvements, including every new parking lot
  • Excavation of any amount inside the archaeologically sensitive area set by Ordinance No. 1521(06)

No grading permit

  • Excavations of 50 cubic yards or less that are under 2 feet deep or leave no slope over 5 feet high and steeper than 2:1, without blocking a drainage course
  • Fills of 50 cubic yards or less of earth only, flatter than 5:1 and not blocking a drainage course
  • Digging for basements, footings or retaining walls under a valid building permit
  • Work in the public right-of-way, wells, utilities and engineer-directed soil testing

The Fire Department’s part of the schedule doubles all fees for work done without a valid permit.

What Lompoc decides and what the state holds

The city sets its own fees, grading rules, architectural and design review and its archaeological excavation rule, and the division keeps a Building and Fire Codes page. Building standards come from the state code, and the division applies the 2025 California codes to all projects from January 1, 2026; projects already under way may continue under the older codes only while forward progress stays continuous.

Lompoc building department: who handles permitting

The City of Lompoc does, for all land inside the city limits. The Building and Safety Division reviews plans before permits are issued, issues building, mechanical, plumbing and electrical permits and inspects the work. Fire plan review and the fire permit fee on building plans sit with the city’s Fire Department in the same fee schedule. Unincorporated land around Lompoc is permitted by Santa Barbara County Planning and Development; see our Santa Barbara County guide. An annexation request to bring land into the city is billed at actual cost against a $5,000 deposit in the city’s fee schedule.

Short on time to read all of this?

Get a free quote →
Lompoc permit contacts
DetailInformation
OfficeBuilding and Safety Division, Community Development Department (the city’s address: City Hall, 100 Civic Center Plaza, Lompoc, CA 93436)
HoursMonday to Thursday, 9 a.m. to 4:30 p.m., by appointment only
Email (the division’s preferred contact)building@ci.lompoc.ca.us
Building counter805-875-8220
Inspection request line805-875-8231
City Hall805-736-1261, weekdays 9 a.m. to 5 p.m.
PortalCustomer Self-Service portal

The division says email is the best way to reach it, since counter staff may be helping another customer when the phone rings.

Lompoc permit types

Building permits are priced from a valuation table, with a matching plan check table; trade work is priced by category, and grading has its own inspection table.

Residential permits

  • New homes, additions and remodels: valuation-based building permit and plan check fees, plus the trade permits for the house.
  • Fire fee on house plans: the Fire Department charges 5% of the building fees for a single-family house (R-3), covering up to three site inspections.
  • Construction details and forms: the division posts online forms and construction details to help projects meet current California codes the first time.

Commercial permits

Commercial, industrial and R-1 or R-2 residential projects pay the same valuation-based building permit and plan check fees, a Fire Department permit fee of 10% of the building fees and, where the Fire Department reviews the plans, 20% of the building fees for plan review and one re-check. Subdivisions and single-lot developments are billed at actual cost against a $1,000 deposit, and the city can bring in contract services at actual cost plus 10%. The Planning Division also keeps a page on construction storm water pollution prevention plans.

What comes before the building permit

  • Architectural review: $1,865 for a minor review and $3,340 for a major one.
  • Design review of a site plan or building plan: actual cost, starting at $1,320 plus a $2,000 deposit.
  • Changes to an approval: amending an existing permit or approval is $1,690, and an appeal of a staff decision to the Planning Commission $257.80.
  • Environmental review: a categorical exemption is $170 ($275 for cannabis projects); larger documents are billed at actual cost.
  • Fee estimate: the city prepares an estimate of development fees for $257.80 per pre-application submittal, free for requests tied to an open application.
  • Density bonus: $825.

Not sure this scope needs a permit?

Get a free quote →

Lompoc building permit fees

The City Council adopted the current Master Fee Schedule on December 5, 2023 (Resolution No. 6620(23)); it took effect February 5, 2024 and was amended March 8, 2024. The city’s fee page notes that its list may be partial and may not show recent changes, and asks that fee questions go to the Finance Department. Building permits are $92 to issue, or $551 to issue with plan check, plus these tables:

Lompoc building permit and plan check fees (Master Fee Schedule, effective Feb. 5, 2024)
Job valuationBuilding permit feePlan check fee
Up to $2,000$184$200
$2,001 to $20,000$184 + $40 per $1,000 over $2,000$200 + $36 per $1,000 over $2,000
$20,001 to $50,000$904 + $33 per $1,000 over $20,000$848 + $26 per $1,000 over $20,000
$50,001 to $75,000$1,894 + $32 per $1,000 over $50,000$1,628 + $25 per $1,000 over $50,000
$75,001 to $100,000$2,694 + $23 per $1,000 over $75,000$2,253 + $13 per $1,000 over $75,000
$100,001 to $500,000$3,269 + $11 per $1,000 over $100,000$2,578 + $8 per $1,000 over $100,000
$500,001 to $1,000,000$7,669 + $9 per $1,000 over $500,000$5,778 + $6 per $1,000 over $500,000
$1,000,001 to $3,000,000$12,169 + $7 per $1,000 over $1,000,000$8,778 + $3 per $1,000 over $1,000,000
Over $3,000,000$26,035 + $4.50 per $1,000 over $3,000,000$14,778 + $2 per $1,000 over $3,000,000

Worked example: a $50,000 job sits at the top of the $20,001 to $50,000 band. Building permit: $904 + 30 × $33 = $1,894. Plan check: $848 + 30 × $26 = $1,628. Both figures equal the base of the next band, so these bands join without a gap. Issuance and the percentage add-ons below come on top.

Rather talk it over?

Call 1-855-478-4290 →
Other Lompoc building-related fees
ItemFee
General Plan maintenance fee5% of all building, electrical, plumbing and mechanical permit fees
Community Development technology fee5% of all building, electrical, plumbing and mechanical permit fees
Fire Department permit fee on approved plans5% of building fees (house, R-3); 10% (commercial, industrial, R-1 and R-2)
Fire Department plan review20% of building fees, including one re-check
Fire permit preparation / fire access and protection inspection$55 / $103
Fire Department technology and imaging fee2.5% of the total permit fee
Fire Marshal consultation$220 per hour, one-hour minimum
Appeal of a building decision$1,985
Plan re-check, re-inspection, inspection of unpermitted workHourly rate
After-hours inspectionHourly rate, 4-hour minimum

Grading permits for grading, drainage and parking lot work are prepared at actual cost against a $1,000 deposit, and their non-refundable inspection fee follows a separate table based on the volume of cut plus import:

Lompoc grading permit inspection fees
VolumeFee
Under 50 cubic yards$124
50 to 100 cubic yards$317
101 to 500 cubic yards$317 + $58.59 per 100 cubic yards over 101
501 to 5,000 cubic yards$551 + $6.18 per 100 cubic yards over 501
5,001 to 50,000 cubic yards$830 + $6.18 per 100 cubic yards over 5,001
50,001 to 500,000 cubic yards$1,108 + $6.18 per 1,000 cubic yards over 50,001

Development impact fees are separate. The 2026–2027 impact fee schedule took effect July 1, 2026, alongside Ordinance 1726(25) and the 2025 development impact fee nexus report; ask the division for the amounts that apply to a project.

Trade permits and who may pull them in Lompoc

Mechanical, electrical and plumbing permits come from the same division and carry a $92 processing fee plus a category fee:

Lompoc mechanical, electrical and plumbing permit categories
CategoryFee
Category A$77
Category B$107
Category C$172
Category D$239
Category E$303
Category F$505

Rather not deal with the building department?

Get a free quote →

The schedule names the categories without saying which jobs fall in each, so ask the division which category a job falls in. Contractors working in Lompoc pay the city’s business license charges for contractors: $150 for a general engineering or building contractor and $75 for a subcontractor or specialty contractor, plus a $25 planning review fee per application, a $10 renewal fee and the $4 state CASp fee. The trade license itself is a state license from the Contractors State License Board, and owner-builders may pull permits for their own property.

How to apply for a Lompoc building permit

1. Settle planning review

Find out whether the project needs architectural review, design review or an environmental determination; a fee estimate can be requested before applying.

2. Prepare digital plans

Use the division’s online forms and construction details and design to the 2025 California codes.

3. Register in the Customer Self-Service portal

All permit applications and corrected plans are submitted digitally, and paper plan sets are no longer taken.

4. Plan review

Staff review the plans before any permit is issued; the schedule lists issuance with plan check at $551 and prices plan check from its own valuation table.

5. Answer corrections

Upload corrected plans to the portal; re-checks are billed at the hourly rate.

6. Pay the permit fees

Building permit, trade categories, the two 5% surcharges and any Fire Department fees.

7. Schedule inspections

Call 805-875-8231 or book in the portal, with the stamped plans on site.

Review, corrections and what causes delay

The division gives detailed plan reviews before issuing permits and says that following its forms and construction details from the start speeds up the process. Status can be checked around the clock in the portal, which the division calls the fastest way to follow a permit. Because each re-check is billed by the hour, a complete first submittal keeps both time and cost down. Projects started under older codes before 2026 must keep making continuous progress to stay valid.

Lompoc building inspections

The division inspects daily. Inspections are booked through the request line at 805-875-8231 or online in the permit portal. The stamped, approved plans must be on the job site: if they are not, the inspector leaves without inspecting and the inspection has to be booked again.

Re-inspections and inspections of unpermitted work are charged at the hourly rate, and after-hours inspections at the hourly rate with a four-hour minimum. Fire inspections on approved plans are part of the Fire Department’s permit fee, which covers up to three site inspections. A temporary certificate of occupancy is handled by the Building Division at actual cost, with a one-hour minimum.

Want this handled start to finish?

Get a free quote →

California building code in Lompoc

Lompoc requires all projects to be designed to the 2025 California Building Codes from January 1, 2026, and the division keeps a separate Building and Fire Codes page. FEMA’s Community Status Book lists the City of Lompoc (community 060334) as participating in the National Flood Insurance Program, with a current flood map dated December 4, 2012.

California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments

Lompoc permit search and official resources

Permit status, plan submittals and inspection bookings all run through the Customer Self-Service portal, which is open around the clock; the division also answers status questions by email or phone.

Inspections are where schedules slip.

Get a free quote →

Lompoc building permit FAQs

Can I bring paper plans to Lompoc City Hall?

No. All permit applications and corrected plans are submitted digitally through the Customer Self-Service portal.

Do I need an appointment?

Yes. The division sees the public Monday to Thursday, 9 a.m. to 4:30 p.m., by appointment only, and prefers email at building@ci.lompoc.ca.us.

How much is a building permit in Lompoc?

$184 for work valued up to $2,000, rising by band. A $50,000 job pays $1,894 for the permit and $1,628 for plan check, plus issuance and surcharges.

How do I book an inspection?

Call 805-875-8231 or book in the permit portal, and have the stamped approved plans on site.

Which code applies to my project?

Projects designed from January 1, 2026 must follow the 2025 California codes; earlier projects can stay on older codes only with continuous progress.

Do I need a grading permit to dig?

An excavation of 50 cubic yards or less is exempt if it is under 2 feet deep or leaves no slope over 5 feet high and steeper than 2:1, but any excavation in the archaeologically sensitive area and every new parking lot needs one.

What does a contractor pay the city?

A general or building contractor pays $150 and a subcontractor $75 in city business license charges, plus the $25 planning review and $4 state fees.

Are impact fees charged?

Yes, from the 2026–2027 impact fee schedule effective July 1, 2026; ask the division for the figures for a project.

Simplify Lompoc permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Lompoc sooner?

Let Alliance prepare, file, and track your Lompoc permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Lompoc permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.