Dixon, California Building Permit Guide

To get a building permit in Dixon, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Dixon’s Building Division at City Hall, 600 East A Street, issues permits inside the city, and since December 1, 2025 nearly every application, payment and inspection request goes through the Dixon Civic Access portal.

Authority: Dixon Building DivisionFiling: Dixon Civic AccessPhone: 707-678-7005
Authority
City Building Division600 East A Street
Inspections
Monday–Thursday8 a.m. to 3:30 p.m., none on Fridays
Plan check
65% of permit feeResolution 26-090
Card payments
$5,000 limitLarger totals by check or cash

For property inside the City of Dixon, building permits come from the Building Division of Community Development at City Hall, 600 East A Street (707-678-7005, option 2; buildingdivision@cityofdixonca.gov), whose counter is open 8:30 a.m. to 4:30 p.m. Applications, plan review, payments and inspection requests run through Dixon Civic Access, and review starts only once a complete application is paid. Permit fees follow the valuation table in Resolution 26-090, effective July 1, 2026, with plan check at 65% of the permit fee.

What requires a building permit in Dixon?

Dixon permits new buildings, additions, alterations, demolition and trade work through one Building Division. Its fee schedule shows the range of residential work it permits on its own: window replacements, re-roofs, pools and spas, stucco and siding, insulation, sheds, patio covers, trellises, porches and decks, fireplace inserts, kitchen and bath remodels, water heaters, furnaces and air conditioners, sewer and gas line repairs, service changes, solar, EV chargers and battery storage.

Permit needed (accessory structures)

  • Any structure attached to the house, whatever its size, including attached patio covers
  • Any detached structure larger than 120 square feet
  • Any accessory structure that gets gas, mechanical or electrical work, which brings the whole structure under permit, setbacks and zoning

Not required

  • Single-story structures of 120 square feet or less with no plumbing, mechanical or electrical work
  • Detached decks up to 200 square feet, no more than 30 inches above grade at any point, that do not serve the required exit door
  • Other items listed in section R105.2 of the residential code

Exempt structures still have to meet Planning’s setback, size, height and lot coverage limits, so check with the Planning Division before building. Fire construction permits, for example for fire sprinklers, kitchen hood systems, alarms and LP-gas systems, are a separate Fire Department permit under section 105.6 of the fire code.

What Dixon decides and what the state holds

Under Ordinance No. 25-007, Dixon adopted the 2025 California codes by reference with local amendments, added chapter 16.20 bringing the new Wildland-Urban Interface Code into the municipal code, and amended chapter 16.13, the Dixon Emergency Hazard and Placard System. The ordinance says the amendments that apply to homes are substantially the same as those adopted in 2022 by Ordinance No. 31-2022. The city’s amendments are published in Title 16 of the Dixon Municipal Code. Contractor licenses are issued by the state; owners doing their own work file the city’s owner-builder form.

Dixon building department: who handles permitting

The Building Division of the Community Development Department reviews plans, issues building permits and inspects work inside the city limits. The Chief Building Official is Larry Paisley and the Community Development Director is Raffi Boloyan. Planning, Engineering and the Dixon Fire Department review their own parts of a project, and all four use Civic Access. Land outside the city is unincorporated Solano County, where the county’s Building & Safety Services issues permits.

Short on time to read all of this?

Get a free quote →
Dixon permit contacts
OfficeContact
Building Division707-678-7005, option 2, or 707-678-7000 ext. 1789; buildingdivision@cityofdixonca.gov
Inspection request line (24 hours)707-678-7005, option 1
Planning Division (also books planning inspections)707-678-7000 ext. 1786; planningdivision@cityofdixonca.gov
Engineering Department707-678-7030; engineering@cityofdixonca.gov
Dixon Fire Department707-678-7060; fireadmin@dixonfireca.gov
City Hall and payments600 East A Street, Dixon, CA 95620; main line 707-678-7000
Building counter hours8:30 a.m. to 4:30 p.m.

Dixon permit types

Civic Access lists every application type the city takes, from building and fire permits to encroachment permits, development applications and business licenses. Applicants register an account, pick the application from the Available Applications tab or from the map, upload files and pay invoices in the portal. Paper or emailed submittals need special arrangements made in advance.

Residential permits

  • Instant permits: residential HVAC changeouts, re-roofs, service panel replacements, sewer and water line repair or replacement, and like-for-like water heater changeouts each have a published requirements sheet, and qualifying rooftop solar is issued through SolarAPP+.
  • Accessory structures and patio covers: plans must be digital, to scale and legible at 11 by 17 inches. A listed patio cover with an ICC or IAPMO report number needs no separate engineering, but a site plan still goes to Planning.
  • ADUs: the city’s June 2025 flyer allows attached or converted ADUs up to half the main home’s living area or 1,200 square feet, whichever is less, and detached ADUs up to 1,200 square feet and 16 feet tall, with 4-foot side and rear setbacks. A pre-approved ADU plan program has its own checklists for designers and homeowners.
  • Required forms: the owner-builder form, a declaration and authorization for agents, the smoke alarm, carbon monoxide and water-saving fixture certificate, a construction debris worksheet and the air district asbestos questionnaire.

Commercial permits

Non-residential projects follow the city’s online submittal checklist, with a separate checklist for commercial solar. Projects that need special inspection sign Dixon’s special inspection agreement, and fire plan review is charged on the Fire Department’s own schedule. The city also publishes its policy on third-party plan review under state law (AB 253).

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Planning: design review for a new or altered single-family home or duplex costs $425 per building; multifamily and commercial design review and conditional use permits carry separate Planning fees.
  • Encroachment: any work or dumpster in the public right-of-way, including sidewalk repair, needs an Engineering encroachment permit in Civic Access. Cutting into a newly paved street also needs a moratorium waiver under Ordinance 20-014.
  • Construction water: using a city hydrant needs a temporary construction meter: an $1,800 deposit, a $100 application fee, $100 a month and $5 per unit of water.
  • School fees: the Dixon Unified School District collects its fees directly, using the school impact fee form from the city.

Dixon permit costs and fees

The City Council approved a 3.0% CPI increase to the Master Fee Schedule on April 21, 2026 (Resolution No. 26-090), effective for applications submitted on or after July 1, 2026. Fees are set by the date of a complete submittal and are due before approval. Building permit fees follow a valuation table; plan check is 65% of the building permit fee for residential, commercial, multifamily and industrial work (25% for a subsequent identical residential plan).

Selected Dixon building fees, effective July 1, 2026
ItemFee
Valuation $1 to $2,000$321 flat
Valuation $25,001 to $50,000$891.22 for the first $25,000 plus $21.39 per $1,000
Valuation $50,001 to $100,000$1,425.95 for the first $50,000 plus $23.02 per $1,000
Valuation $100,001 to $500,000$2,577.02 for the first $100,000 plus $10.34 per $1,000
Plan check65% of the building permit fee
General Plan update surcharge$6.79 per $1,000 of valuation
Technology fee8% of the building, planning, engineering or fire permit fee
Re-roof, residential / commercial$346 / $1,049
Water heater / HVAC complete changeout$193 / $289
Residential service change$193
Shed under 250 sq ft (no trades) or residential patio cover$396
Kitchen or bath direct replacement, no trades / with trades$148 / $494
Residential solar, 15 kW or less$450, plus $15 per kW above 15
Missed inspection or reinspection$62
Permit extension or change of contractor$202

Rather talk it over?

Call 1-855-478-4290 →

Worked example. A project valued at $60,000 has a building permit fee of $1,425.95 plus 10 × $23.02, or $1,656.15. Plan check at 65% adds $1,076.50 and the General Plan surcharge adds $407.40 (60 × $6.79), for $3,140.05 before the 8% technology fee and the state SMIP and building standards fees.

New construction also pays Dixon’s development impact (AB 1600) fees, updated by Resolution No. 26-039 on February 17, 2026 and in effect since April 18, 2026, plus Solano County’s public facilities fee, which the city collects for the county. For a single-family home the fire facilities fee is $2,180.21, the police facilities fee $868.59 and the administrative and public works facilities fee $1,706.31, among other components. ADUs of 749 square feet or less and junior ADUs are exempt from these capital facilities fees; larger ADUs pay in proportion to the size of the main home. Card payments are capped at $5,000, so larger totals are paid by check or cash.

Other flat residential fees in the schedule include $199 for the first five replacement windows plus $15 for each additional window, $1,286 for a pool and $692 for a spa, $644 for a porch or deck, $247 to repair stucco or siding and $594 for new stucco or siding, $248 for insulation and $199 for a fireplace insert. A structural kitchen or bath remodel is charged at 75% of the building permit fee.

Trade permits and who may pull them

The Building Division issues mechanical, plumbing and electrical permits as well as building permits. Common residential jobs have flat fees: a complete HVAC changeout is $289 and a partial one $145, a water heater $193, sewer repair $289, gas line repair $193 and a residential service change $193; stand-alone residential trade work valued at $2,500 or less is $242, and larger work is priced from the MEP valuation table. A single-family EV charger is $194 and a battery storage system $726.

  • Who can apply: licensed contractors, owner-builders using the city’s owner-builder form, or an agent with the city’s declaration and authorization form.
  • Instant permits: HVAC, water heater, service panel, sewer, water line and re-roof replacements that meet the city’s requirement sheets can be issued without plan review.
  • Business licenses are applied for in the same Civic Access portal.
  • Fire systems: sprinkler, alarm, hood and similar systems need a Fire Department construction permit (707-678-7060).

Rather not deal with the building department?

Get a free quote →

How to apply for a Dixon building permit

1. Register in Civic Access

Create an account using the city’s 2026 registration guide; keep using an email you already use with the city.

2. Check zoning and design review

Ask Planning about setbacks and whether design review applies before drawing plans.

3. Choose the application

Pick it from Available Applications or from the map, and fill in the project details.

4. Upload a complete set

Attach digital plans and the required city forms; review waits for a complete, paid submittal.

5. Answer review comments

Use Files & Reviews and the Resubmit Files action to upload corrected plans.

6. Pay invoices and get the permit

Pay in the portal, by check mailed to City Hall, or in person; credit cards are capped at $5,000.

Review, corrections and what causes delay

The most common hold-up is an incomplete or unpaid application, because the city does not start review until both are done. Comments appear in the portal, and the city posts step-by-step guides for finding them, resubmitting files and paying invoices. If the Add Files button is missing, the department handling the case has to enable uploads. Fees are locked to the date of a complete submittal, so an application filed before an annual fee update keeps the older rates. A permit extension, reissuance or change of contractor costs $202.

Inspections in Dixon

Building inspections run Monday through Thursday, 8 a.m. to 3:30 p.m., with none on Fridays or city holidays; this schedule began on December 1, 2025. Request them in Civic Access after the permit is issued (Request Inspection, choose the inspection and date, then submit) by 3 p.m. the day before. If the portal is not an option, leave a message on the 24-hour line, 707-678-7005 option 1, by 3 p.m. with the permit number, address, inspection type, contact name and phone number. Inspections can be requested only 24 hours ahead.

  • A missed inspection or reinspection costs $62.
  • Inspections outside normal hours are billed on time and materials at $131 an hour, two hours minimum.
  • Planning inspections are booked directly with the Planning Division.
  • A temporary occupancy permit costs $451.

California building code in Dixon

Dixon enforces the 2025 California codes as adopted with local amendments by Ordinance No. 25-007, introduced November 18, 2025, finally adopted December 2, 2025 and in force since January 1, 2026; complete applications received before January 1, 2026 stay under the 2022 codes. FEMA’s Community Status Book lists Dixon (community 060369) as participating in the National Flood Insurance Program; the city points to FEMA flood map panel 06095C0200F, revised August 2, 2012.

Want this handled start to finish?

Get a free quote →

California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments

Dixon building permit FAQs

Can I still apply on paper in Dixon?

Only by special arrangement made in advance; since December 1, 2025, permits are submitted through Dixon Civic Access.

How much does a building permit cost in Dixon?

It follows the valuation table: a $60,000 project pays $1,656.15, plus 65% plan check and the General Plan and technology surcharges.

Are inspections done on Fridays?

No. Inspections run Monday through Thursday, 8 a.m. to 3:30 p.m.; request them by 3 p.m. the day before.

Do I need a permit for a shed?

Not for a single-story shed of 120 square feet or less with no plumbing, mechanical or electrical work; anything larger or attached needs one.

Can I pay my permit fees by credit card?

Yes, online or at City Hall, up to $5,000 per transaction; larger totals must be paid by check or cash.

Do ADUs pay impact fees?

ADUs of 749 square feet or less and junior ADUs are exempt from Dixon’s capital facilities fees; larger ADUs pay a proportional share.

How much is a re-roof permit?

$346 for a home and $1,049 for commercial, multifamily or industrial roofs; qualifying residential re-roofs can be issued as instant permits.

Who handles school fees?

The Dixon Unified School District collects them directly; the city provides the school impact fee form.

Dixon permit search and official resources

Registered Civic Access users see their own cases, inspections and results, invoices, required actions and resubmittals on their dashboard. For the wider public, the Building Division posts monthly building permit reports on the city website.

Inspections are where schedules slip.

Get a free quote →

Simplify Dixon permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Dixon sooner?

Let Alliance prepare, file, and track your Dixon permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Dixon permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.