Colusa County, California Building Permit Guide

To get a building permit in Colusa County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Colusa County’s Development Services Department issues building permits for unincorporated land, including Arbuckle and Maxwell, and takes every application through its online permit portal; the cities of Colusa and Williams permit their own.

Authority: Colusa County Development Services, BuildingFiling: Online permit portal onlyPhone: (530) 458-0481
Office
1213 Market StreetColusa; Building (530) 458-0481
Applications
Online portal onlyHelp line (530) 458-0480
Inspections
By phone, 3–5 days aheadCancel before 8 a.m.
Septic permit
$364 new systemEnvironmental Health

For land outside the cities of Colusa and Williams, building permits come from the Planning and Building unit of Colusa County’s Development Services (Community Development) Department at 1213 Market Street, Colusa (Building (530) 458-0481). All permit applications must be filed through the county’s online permit portal, and each one is reviewed by Planning, Building, Environmental Health, the local fire district and Public Works. The county has applied the 2025 California Building Standards Code since January 1, 2026; inspections are booked by phone three to five days ahead.

What requires a building permit in Colusa County?

The county’s permit pages describe a building permit for new structures, additions, remodels and accessory buildings on any parcel in the unincorporated county, each reviewed against the plot plan, the zoning code and the building code. The required drawings show what the county expects to see: electrical and plumbing plans, truss and energy calculations, a plot plan, and fire sprinkler and solar plans where a project has them. Electric vehicle charging stations and solar energy systems have their own streamlined processes.

County reviews on every permit

  • Planning: setbacks and whether the use is allowed in the zone
  • Building: plans and code compliance
  • Environmental Health: wells and sewage disposal (septic) systems
  • Fire district: State Fire-Safe regulations
  • Public Works: county road encroachments, flood hazards and significant grading

Separate county permits

  • Septic system construction, repair, destruction and alternative systems
  • Lot evaluation and soil profile for a septic design
  • Encroachments onto county-maintained roads
  • Land use permits, such as administrative permits for home occupations and second dwelling units, use permits and variances

What Colusa County decides and what the state holds

The Board of Supervisors keeps the county’s own building rules in Chapter 5, Building Code, of the Colusa County Code, and adds to it by ordinance: Ordinance No. 828, adopted on December 20, 2022, added Article V, an expedited permitting process for electric vehicle charging stations. The ordinance confirms that the Planning and Building unit is responsible for issuing building permits in the unincorporated county. The county also writes its own zoning code, general plan and Local Agency Management Program for septic systems, which allows some local flexibility in the state’s septic standards to suit local soil and climate.

Colusa County building department: who handles permitting

Colusa County’s Development Services Department, directed by Xzandrea Fowler, combines Planning, Building, Environmental Health, Code Compliance and Water Resources in one agency. Its Building unit processes permits, inspects sites and enforces building codes in the unincorporated county. The county’s two incorporated cities each run their own building departments.

Short on time to read all of this?

Get a free quote →
Who issues building permits in Colusa County
PlaceBuilding permits issued byContact
Unincorporated county, including Arbuckle, Maxwell and rural areasColusa County Development Services, Planning and Building unit1213 Market Street, Colusa; (530) 458-0481
City of Colusa (pop. 6,519)City of Colusa Building Department(530) 458-4941, ext. 3106, 3108 or 3100
City of Williams (pop. 5,529)City of Williams Building Department530-235-3276; Monday to Friday, 8 a.m. to 4:30 p.m.

To see whether a parcel is inside a city, look it up on the county’s GIS Interactive Map, kept by Public Works, or ask the Assessor’s office ((530) 458-0450), which answers property questions. The county’s permit page names these offices for an unincorporated application:

County offices on a Colusa County building permit
OfficeReviewsContact
BuildingPlans and code compliance; inspections1213 Market Street; (530) 458-0481
PlanningSetbacks, zoning, land use permits; portal help1213 Market Street; (530) 458-0480
Environmental HealthWells and septic systems1213 Market Street; (530) 458-0888; weekdays 8 a.m. to noon and 1 to 4:30 p.m.
Public WorksRoad encroachments, flood hazards, significant grading1215 Market Street; (530) 458-0466
Fire districtState Fire-Safe regulationsContact details from the Building unit

Colusa County permit types

Building, planning and environmental health applications are all filed in the county’s online permit portal, where applicants can track status, request inspections and message the staff handling the permit. The portal also holds the land use applications: administrative permits for home occupations and second dwelling units, major and minor use permits, variances, parcel and subdivision maps, general plan and zoning amendments and lot line adjustments.

Residential permits

  • New houses and additions need a full plan set: plot plan, floor plan, foundation and floor framing plan, four exterior elevations and enough cross-sections to show stairs, vaulted ceilings and other details. For remodels and additions, the plans must separate existing and new work.
  • Who may draw the plans. The county’s page explains that any person may prepare plans for wood-frame single-family homes of up to two stories, wood-frame multifamily buildings of up to two stories with no more than four units on a lot, wood-frame garages and agricultural and ranch buildings, and interior non-structural alterations. Unconventional designs, unusual features or buildings without enough lateral bracing need a registered civil engineer or licensed architect, and structures 20 feet or more in length or width may need engineering.
  • EV chargers qualify for the expedited process under Ordinance No. 828, using the county’s EV Charging Station Permit Checklist: a site plan drawn to an engineer’s scale on 11 by 17 to 24 by 36 inch paper showing the septic tank and leach field, two plan sets with equipment cut sheets, a stamped and signed design, a single-line electrical diagram and load calculations when required.
  • Solar energy systems. The Building page carries a heading on solar energy system permit fee caps “as of January 01, 2026” without amounts and links the state’s Solar Energy Systems Guidelines; ask the Building unit for the fee.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

Business, commercial and industrial buildings with offices and bathrooms must show accessibility on the original plans under disability access rules. Engineered buildings need signed and stamped structural calculations, with every detail and nailing schedule carried onto the drawings, or a statement from the engineer or architect that the plans include the calculated criteria. Projects near the county airport are screened by Planning staff for referral to the Airport Land Use Commission.

What comes before the building permit

  • Land use approval. Where a project needs a use permit or other entitlement, Planning reviews it first; a Concurrent Processing Request Form lets you submit the construction permit before the land use permit is approved.
  • Planning paperwork. An Authorization and Indemnification Agreement must accompany every planning application, and the county keeps an Approved Consultant List, revised January 13, 2026.
  • Septic and well. Environmental Health reviews the well and sewage disposal system shown on the plot plan.
  • Roads and floods. Public Works reviews encroachments onto county-maintained roads, flood hazards and significant grading.

Colusa County permit costs and fees

Colusa County does not post a building permit fee schedule on its Building pages; call the Building unit ((530) 458-0481) for the fee on a project. The fee figures the county does post are below.

Fees posted by Colusa County
ItemFee
Septic system construction$364
Septic system repair$224
Septic system destruction$140
Commercial or industrial septic system$560
Alternative septic system permit$560
Lot evaluation and soil profile$280
Water well: domestic, agricultural, or exploratory and monitoring wells (per parcel)$364
Well system repair$224
Well abandonment or destruction$168
Building re-inspection when inspection requirements are not met$47 per hour

Rather talk it over?

Call 1-855-478-4290 →

Septic and well fees are paid to Environmental Health in cash or by check, in person or by mail to 1213 Market Street. The division’s fee schedule, dated effective July 1, 2008, lists the same septic and well amounts and also a $56 environmental health building sign-off, $112 an hour for other services, and double the applicable permit fee for operating without a permit. The re-inspection fee must be paid to the Building unit before another inspection is scheduled, and the inspection page notes that other fees may be charged under the county building code.

Planning fees are in a spreadsheet titled “Colusa County Department of Planning & Building Fee Schedule” on the Permits & Applications page. It shows no adoption date, so ask Planning ((530) 458-0480) to confirm a figure before you budget. It lists, for example, a minor use permit at $531 in total (Planning $375, Environmental Health $56, a $100 categorical exemption and a $50 County Clerk fee), a minor variance at $503, and a major use permit at $1,316 plus state Fish and Wildlife filing fees. Minor use permits cover second dwellings, signs and similar uses.

Trade permits and who may pull them in Colusa County

Electrical, plumbing and mechanical work in the unincorporated county is reviewed and inspected by the county Building unit; the plan set for a new building must include electrical and plumbing plans, with the electrical outlets and panel shown on the floor plan. Fire sprinkler plans and solar plans are added where a project includes them.

  • Designers. Every sheet must carry the designer’s signature, and the designer must sign a statement that the truss calculations were reviewed and all loading and design criteria were met.
  • Engineers and architects stamp and sign drawings when a structure is engineered.
  • Contractors and owner-builders file through the same online portal.
  • Septic pumpers apply through the portal and file a monthly report with Environmental Health.

Rather not deal with the Colusa County building department?

Get a free quote →

How to apply for a Colusa County building permit

1. Confirm the parcel is unincorporated

If it is inside Colusa or Williams, apply to that city. Otherwise check zoning and setbacks with county Planning.

2. Sort out septic and water

For a new septic system, file a site evaluation application, dig the soil test holes and call Environmental Health for an inspection before the system is designed.

3. Prepare the plans

Draw the plot plan to scale with the assessor’s parcel number, north arrow, every structure, wells, septic and leach field, streets, easements and the access road; add the floor, foundation, elevation and detail sheets.

4. Apply in the online portal

Create an account and file the application with all drawings and calculations. Call (530) 458-0480 for help with the portal.

5. Respond to each department

Planning, Building, Environmental Health, the fire district and Public Works each review the file; answer their comments in the portal.

6. Pay and receive the permit

Pay the fees the county sets, post the address so it can be seen from the road, and keep the stamped plans on site.

Review, corrections and what causes delay

Five reviewers work from the same plot plan, so it must show the distances between all buildings and to property lines, utilities, the septic system and leach field, streets, easements and the access road. All sheets must be the same size and legible at their original size. For septic work, Environmental Health can usually set the design requirements from two soil test holes, but some sites need deeper holes, percolation tests, wet-weather testing or a soil scientist, engineer or geologist, and large or unusual flows may go to the Regional Water Quality Control Board.

Inspections in Colusa County

Request building inspections by phone at (530) 458-0481, three to five days ahead, or through the online portal. Have the approved, stamped plans and specifications on site, and give the permit number and the location of the building. The address must be posted so it can be read from the nearest county road; a site more than 100 yards off the road needs directional signs along the way. Cancellations must reach the Building office before 8 a.m. on the inspection day. Missing any of these items brings a re-inspection fee of $47 an hour, paid before the next inspection is booked. Any permitted repair, alteration or addition must also bring smoke and carbon monoxide alarms up to code, and the permit cannot be finaled until the owner, contractor or authorized agent signs the county’s alarm certification.

Septic soil test holes are dug on the morning of the inspection: at least two holes, 8 feet deep, 3 feet wide and 5 feet long with a step down to a landing at 5 feet, usually about 75 feet apart (one for the disposal field and one for the replacement area). Call Environmental Health at (530) 458-0395 when they are ready; inspections are usually made within 2 working days. The county’s setback table keeps septic tanks and disposal fields at least 100 feet from private wells and springs and 5 feet from a property line. Well drillers must notify Environmental Health 48 hours before an inspection, and well applications are filed through the online portal.

Want this handled start to finish?

Get a free quote →

California building code in Colusa County

California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments

Colusa County says it has operated under the 2025 California Building Standards Code since January 1, 2026. Its local building provisions are in Chapter 5 of the County Code, published on eCode360.

Colusa County permit search and official resources

Applicants follow their permit status, inspections and messages with staff in the online portal. For older permit records, ask the Building unit. Flood map panels for Colusa, Williams, Arbuckle and other areas are posted on the county’s FEMA Remapping page; that page still describes 2003 maps and 2022 preliminary maps, while FEMA’s community list shows the unincorporated county taking part in the National Flood Insurance Program with a current effective map dated March 27, 2024.

Inspections are where schedules slip.

Get a free quote →

Colusa County building permit FAQs

Where do I apply for a building permit in Colusa County?

Through the county’s online permit portal; the county requires all permit applications to be filed there. Staff at (530) 458-0480 can help with the portal.

Does the county issue permits in Colusa or Williams?

No. The City of Colusa and the City of Williams each have their own building department; the county covers unincorporated areas such as Arbuckle and Maxwell.

How do I schedule a county building inspection?

Call (530) 458-0481 three to five days ahead, with stamped plans on site and the address posted where it can be seen from the county road.

How much is a septic permit?

A new septic system permit is $364, a repair $224 and an alternative system $560; a lot evaluation and soil profile is $280.

Can I draw my own house plans?

For a conventional wood-frame house of up to two stories, the county says any person may prepare the plans; unusual designs need a registered civil engineer or licensed architect.

What code does Colusa County use?

The 2025 California Building Standards Code, effective January 1, 2026, with the county’s own provisions in Chapter 5 of the County Code.

How much is a well permit in Colusa County?

Environmental Health charges $364 for a domestic or agricultural well, $224 for a well repair and $168 to destroy a well.

Simplify Colusa County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Colusa County sooner?

Let Alliance prepare, file, and track your Colusa County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Colusa County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.