Artesia, California Building Permit Guide

To get a building permit in Artesia, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Artesia’s Building and Safety Division, with services provided under contract by BPR Consultants, issues building and trade permits for the city through its OpenGov portal, with inspections on Tuesdays, Wednesdays and Thursdays.

Authority: City of Artesia Building and SafetyFees: Schedule effective July 1, 2025Phone: 562-865-6262
Authority
City Building & SafetyContract firm: BPR Consultants
Apply
OpenGov portalOpen 24 hours a day
Inspections
Tue, Wed, Thu onlyBook 24 hours ahead
Impact fee
$28,346 per new houseADUs under 750 sq ft exempt

In the City of Artesia, building, electrical, plumbing and mechanical permits are issued by the Building and Safety Division of the Community Development Department, City Hall, 18747 Clarkdale Avenue (562-865-6262); the city contracts with BPR Consultants to provide its building and safety services. Applications, plans and payments go through the city’s OpenGov portal. Fees follow the schedule effective July 1, 2025: plan check and permit fees by valuation, a $39.99 issuance fee on every permit, and a 2% plan maintenance fee.

What requires a building permit in Artesia?

Artesia requires a building, electrical or plumbing permit to erect, construct, enlarge, alter, repair, move, improve, remove, connect, convert, demolish or equip any building, structure or part of one, and the city also requires Planning Department approval before any construction starts. The city’s own examples:

Building permits

  • Garages, workshops, sheds and storage buildings
  • Room additions
  • Swimming pools
  • Patio covers and awnings
  • Fences and block walls
  • Retaining walls (the city’s list reads “over 3 inches”)
  • Re-roofing

Electrical, plumbing, mechanical and gas

  • Electrical wiring, fans and solar
  • Water heaters, sinks and garbage disposals
  • Dryers and air conditioners
  • Swimming pool piping and lawn sprinklers
  • Water softeners and gas piping

The city says these permits make sure buildings meet minimum standards that protect occupants and neighbors in everyday use and in emergencies or natural disasters. Work done without a required permit carries an investigation fee equal to the permit fee, at least $975.76, or $487.88 for an owner-builder on a one- or two-family home.

What Artesia decides and what the state holds

The city sets its building, planning and impact fees, runs its zoning and planning approvals, requires every contractor and subcontractor to hold a city business license, and enforces a construction and demolition recycling program with a 65% diversion target. Its building code, zoning and other local rules are in the Artesia Municipal Code. The state code and contractor licensing come from the state.

Artesia building department: who handles permitting

The Community Development Department, led by Community Development Director Paul Bollier, covers building and safety, planning, development engineering, code enforcement, housing and right-of-way permits. Building and safety services are provided under contract by BPR Consultants, and engineering plan check is also contracted. Applications for Artesia addresses go to the city’s own OpenGov portal and counter at City Hall. Los Angeles County Public Works, whose Building and Safety Division serves unincorporated areas and eight contract cities, does not list Artesia among the contract cities on its plan check and permit fees page.

Short on time to read all of this?

Get a free quote →
Artesia permit contacts
DetailInformation
OfficeCity Hall, 18747 Clarkdale Avenue, Artesia
Phone / fax562-865-6262 / 562-865-6240
Building questionsbuilding@cityofartesia.us (requirements, submittals, plan check status)
Inspectionsinspection@cityofartesia.us; 562-865-6262, ext. 0
Building counterWednesday and Thursday, 8 a.m. to noon (plan checker hours the same)
Planning counterWalk-in Monday to Thursday 7:30 a.m. to noon and every other Friday 8 a.m. to noon; appointments noon to 5 p.m.
PortalArtesia OpenGov permit portal
Virtual helpTeams meetings with a plan checker, Monday to Thursday, 9 a.m. to 4:30 p.m.

Artesia permit types

The OpenGov portal handles building, electrical, plumbing and mechanical permits and Public Works encroachment permits. The Building and Safety page also links separate PDF forms for building, electrical, mechanical, plumbing, sewer and grading permits, a fence and wall packet, a landscaping and irrigation permit, a plot plan application and a low impact development checklist.

Residential permits

  • New homes and additions need three sets of plans: a plot plan at 1/8 inch or 1 inch to 10 feet showing buildings, setbacks, eaves and paving; elevations; a floor plan with room uses, windows and doors; structural plans and calculations where required; and electrical and plumbing plans. A combined permit for a one- or two-family home with an attached garage is 1.6 times the building permit fee. Typical framing detail sheets are available from Building and Safety, and the division answers by email whether a project needs structural plans. The city also reminds homeowners to check that the right permits are in place when others do the work.
  • Rooftop solar on the main house can use the express SolarAPP+ path if a licensed contractor installs a roof-mounted, non-ballasted system; the SolarAPP+ approval number goes into the city application. SolarAPP+ charges its own processing fee, which covers up to three revisions, and permit numbers on this path start with RSL; anything ineligible follows the city’s solar submittal checklist instead.
  • Pools carry a separate pool barrier inspection fee of $266.82.
  • Accessory dwelling units under 750 square feet are exempt from development impact fees; larger ADUs pay a share of the $11,842 ADU fee in proportion to the main home.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

Commercial work follows the same portal process, and the valuation table has separate columns for non-residential occupancies, with and without energy and disabled access checks. Electrical energy plan check for a tenant improvement with no building plan check is $39.55 per 1,000 square feet, with a $159.07 minimum. Change of use or occupancy inspections are priced by floor area, from $1,561.61 up to 5,000 square feet to $4,735.49 above 100,000. New commercial space pays development impact fees of $6,645 per 1,000 square feet, office $6,293 and industrial $3,551.

What comes before the building permit

  • Planning approval: the city requires Planning approval before construction; book a meeting with a planner through the Connect With a Planner page.
  • School fees: construction of 500 square feet or more pays school fees before the building permit is issued.
  • Recycling plan: new construction, demolition, non-residential alterations and residential additions that add area need a Job Site Recycling and Waste Reduction Plan and a deposit, refunded on proof of 65% diversion.
  • Engineering: grading, lot mergers and street work are processed by contracted engineers on an hourly basis with a deposit, and work in the street needs an encroachment permit through OpenGov.

Artesia building permit fees

The current building fee schedule took effect on July 1, 2025. Building plan check and permit fees come from a valuation table that varies with the occupancy and with whether energy and disabled access checks are needed; the table is for reference, and staff compute the actual fee from the valuation. A $39.99 issuance fee is added to every permit, and a plan maintenance fee of 2% of the building permit fee ($28.66 minimum, $1,220.58 maximum) is added to valuation-based permits.

Sample rows from the Artesia building fee table (residential occupancy, effective July 1, 2025)
ValuationPlan checkPermit fee
$10,000, energy check only$588.70$693.88
$10,000, no energy or access check$535.18$630.92
$100,000, energy check only$3,498.11$4,128.42
$100,000, energy and disabled access$3,657.11$4,315.49

Rather talk it over?

Call 1-855-478-4290 →
Other Artesia building fees
ItemFee
Permit issuance fee (each permit)$39.99
Certificate of occupancy / temporary certificate$293.04 / $440.11
Demolition inspection (including sewer termination)$473.66
Preliminary plan review (two-hour minimum)$634.51; no fee for 15 minutes or less
Additional review or third plan check, per hour$317.25
Inspection with no set fee, per hour$284.37
Minimum plan check for a standard plan$436.34
Assignment of house numbers$156.41
Investigation fee, work without a permitEqual to permit fee, $975.76 minimum

Worked example: a $10,000 residential alteration that needs only an energy check pays $588.70 plan check and $693.88 permit fee from the table, the $39.99 issuance fee, and the $28.66 minimum plan maintenance fee (2% of the permit fee would be $13.88), for $1,351.23.

Development impact fees. New homes pay $28,346 per single-family unit and $20,613 per multi-family unit, covering public facilities, traffic, storm drains, parks and the community center. The city posts annual impact fee reports and the 2019 nexus study on its Development Impact Fees page. Planning and engineering fees are set by Resolution 20-2803, adjusted each July by the consumer price index.

Trade permits and who may pull them in Artesia

Electrical, plumbing and mechanical permits are separate permits from the same division, each with the $39.99 issuance fee. Electrical plan check is 70% of the electrical permit fee with a $317.25 minimum, mechanical plan check is 50% of the mechanical permit fee, and plumbing plan check is 40% of the plumbing permit fee. A house sewer connection is $135.74 and a private sewage disposal system $278.82.

Permits are issued to licensed contractors, but a homeowner or the homeowner’s relatives can obtain a permit for construction or alteration of a one- or two-family home when the homeowner does the work, and electrical and plumbing work on a residential building may be done by the homeowner. Every contractor and subcontractor needs a City of Artesia business license before any building permit is issued, and each work vehicle needs a business license sticker renewed every year; licenses are processed through HDL, which takes contractor applications online or by phone at 562-222-8742.

Rather not deal with the building department?

Get a free quote →

All applicants file the city’s declaration form: the owner-builder or licensed contractor declaration, workers’ compensation, hazardous materials disclosure, asbestos notification and the construction lending agency. A representative filing for the owner, such as a contractor, architect, engineer, designer or permit expediter, needs an owner authorization signed and dated by the owner of record that names the representative and the project address. It covers permit processing only, stays valid until the permit is issued or expires or the owner revokes it in writing, and does not shift the owner-builder’s legal duties; the city may ask for proof of ownership.

How to apply for an Artesia building permit

1. Get Planning approval

Meet a planner, in person or virtually, and secure zoning approval for the project.

2. Prepare plans and forms

Assemble the plan sets, the declaration form, the smoke and carbon monoxide certification for homes, and any recycling plan.

3. Create an OpenGov account

Log in at the city’s portal, choose the Building and Safety department and the right permit type.

4. Upload and submit

Complete the application and upload every required document at submission to avoid delays.

5. Answer corrections and pay

Read plan check comments in the portal, resubmit, pay school fees where due and the permit fees online.

6. Print the permit and book inspections

Print the permit documents and request inspections in OpenGov at least a day ahead.

Review, corrections and what causes delay

The city asks applicants to review the submission requirements for the permit type, make sure plans are complete and meet city standards, and upload all documents at once. A third or later plan check due to changes, errors or omissions is charged at $317.25 an hour. The city publishes no review times; for plan check status, email the building address, or book a free Teams meeting with a plan checker for questions about your review.

Artesia building inspections

Inspections are available on Tuesdays, Wednesdays and Thursdays only. Request them in OpenGov or by calling 562-865-6262 at least 24 hours in advance with the project address, contact name and phone, permit number and inspection type; cancellations go to the same number or the building email. The inspector must have the approved plans and the inspection card on site, and work should be complete before the visit to avoid delays or re-inspection fees.

The city lists the usual inspections as foundation, concrete slab or underfloor, framing, insulation, lath or drywall, and final, with others depending on the project. Changes made after plans are approved must be cleared with the Building Division, often over the counter, before the inspector arrives. The division also makes investigation inspections of illegal construction, fire or collision damage to structures, and building complaints that reach the city. A certificate of occupancy is $293.04, and a temporary one $440.11.

Want this handled start to finish?

Get a free quote →

California building code in Artesia

Artesia’s Building and Safety Division applies the state code through the Artesia Municipal Code, which holds any local amendments; the plan checker can confirm which apply to a project. FEMA’s Community Status Book lists the City of Artesia (community 060097) as participating in the National Flood Insurance Program, with no Special Flood Hazard Area mapped in the city on its current maps.

California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments

Artesia permit search and official resources

Applicants track their permits, review status and correction comments in the OpenGov portal. For other permit records, use the city’s public records request page linked from Community Development, or email the Building and Safety Division.

Inspections are where schedules slip.

Get a free quote →

Artesia building permit FAQs

Who runs building permits in Artesia?

The city’s Building and Safety Division, with services provided under contract by BPR Consultants; applications go through the city’s OpenGov portal.

Which days are inspections?

Tuesdays, Wednesdays and Thursdays only, requested at least 24 hours ahead in OpenGov or by phone at 562-865-6262.

Do I need a permit for a fence or block wall?

Yes. The city lists fences and block walls among projects that need a building permit, and it publishes a fence and wall packet.

Can a homeowner pull a permit?

Yes, for a one- or two-family home when the homeowner does the work; otherwise permits go to licensed contractors.

Do contractors need an Artesia business license?

Yes. Every contractor and subcontractor needs one before any building permit is issued, plus a sticker for each work vehicle.

What are the impact fees for a new house?

$28,346 per single-family home; ADUs under 750 square feet are exempt.

Are school fees charged?

Yes, for construction of 500 square feet or more, paid before the building permit is issued.

Can I install rooftop solar with a fast permit?

Yes, through SolarAPP+ if a licensed contractor installs a roof-mounted, non-ballasted system on the main house.

Simplify Artesia permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Artesia sooner?

Let Alliance prepare, file, and track your Artesia permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Artesia permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.