Skip to main content
Municipal GuideCaliforniaAlbany · Alameda County

Albany, California Building Permit Guide

To get a building permit in Albany, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Albany’s Building Division, part of the Community Development Department at 1000 San Pablo Avenue, issues building, electrical, plumbing and mechanical permits inside city limits and takes new applications through the city’s Cloudpermit portal.

Authority: Albany Building Division (Community Development)Phone: 510-528-5760
Authority
City Building Division1000 San Pablo Avenue
Apply
Cloudpermit portalBuilding and planning applications
Inspections
Next day, usuallyAllow up to 3 days; cancel by 9:00 a.m.
Contractors
Albany business licenseNeeded before the permit is issued

In the City of Albany, building permits come from the Building Division of the Community Development Department, 1000 San Pablo Avenue (510-528-5760). New applications go through the city’s Cloudpermit portal, and larger projects are plan-checked by the city’s consultant, Phillips Seabrook Associates. Under the Master Fee Schedule in force from July 1, 2026, every building permit starts with an $89.30 application fee, and a single-family permit valued at $100,000 carries a $1,607.50 permit fee.

What requires a building permit in Albany?

The Building Division’s Work Exempt from Permit handout reprints the exemption list of section R105.2 of the 2025 residential and building codes and adds the city rules that still apply to exempt work; construction, electrical, plumbing, gas and mechanical work that is not on that list needs a permit.

Permit required

  • Additions, new houses and every ADU
  • Remodels, windows, siding and re-roofs
  • Water heaters, furnaces, HVAC, panels, solar, EV chargers and sewer laterals
  • Sheds or other detached one-story buildings over 120 square feet
  • Decks over 200 square feet or 30 inches above grade, and any deck attached to the house or serving a required exit door
  • Retaining walls over 4 feet, or any wall holding a surcharge

Exempt from a building permit

  • One-story detached accessory buildings up to 120 square feet
  • Fences up to 7 feet (zoning still caps most residential fences at 6 feet)
  • Painting, tiling, carpet, cabinets and countertops
  • Clearing stoppages and stopping leaks without replacing pipe or fixtures

Zoning still applies to exempt work: Municipal Code section 20.24.110 caps residential fences, walls and hedges at 6 feet, and at 3 feet in the required front yard and corner-lot vision triangles. Sidewalk and driveway-approach work in the public right-of-way always needs an encroachment permit, which the department issues only to licensed contractors. Grading needs its own permit for excavation within 15 feet of a property line and for larger cuts and fills under the city’s grading ordinance.

What Albany decides and what the state holds

The building standards are the state’s; Albany sets fees, forms, appendices and a few amendments (Ordinance No. 2026-01, May 4, 2026), and runs its own safety programs: the soft-story retrofit ordinance (Ordinance 2023-04, Municipal Code section 12-15) for wood-framed buildings built before 1981 with three or more units and a soft target story, and the exterior elevated elements (3E) inspection program for balconies, decks and stairs on multi-family buildings with three or more units.

Albany building department: who handles permitting

The Building Division checks plans, issues permits, inspects construction and handles building code enforcement for all property inside Albany city limits. It shares the Community Development Department with the Planning Division (design review, use permits, ADU zoning). Projects needing full plan review are checked by the city’s third-party service, Phillips Seabrook Associates; the city still issues the permit.

Short on time to read all of this?

Get a free quote →
Albany permit contacts
DetailInformation
OfficeBuilding Division, Community Development Department, 1000 San Pablo Avenue, Albany, CA 94706
Phone510-528-5760
Emailpermits@albanyca.org (permits and inspections); com-dev@albanyca.org (department)
PortalCloudpermit, us.cloudpermit.com/city-of-albany-ca (building and planning applications)
Fire Prevention Bureau(510) 528-5775: contact before finalizing plans
Business licensesHdL Companies for the city, (510) 292-4619
Flood programAlbany takes part in the National Flood Insurance Program (FEMA community 060003; current map dated December 21, 2018)

Albany permit types

Small residential jobs with little or no structural change are over-the-counter permits, typically issued within 1–2 business days; second-story additions, tenant improvements and new construction go to plan review. Both start with the Building Permit Application, which names the owner, the contractor’s CSLB license and whether the permit goes to the owner-builder, the contractor or an agent.

Residential permits

  • Over-the-counter work: furnaces, water heaters, panel change-outs, siding, windows (photos, spec sheet, site plan), HVAC (site plan with the outdoor unit’s distance to property lines), re-roofs (open-flame work needs the fire code affidavit) and sewer laterals.
  • Kitchens and bathrooms: submittal lists with example drawings are published for each.
  • Solar: licensed contractors can use SolarAPP+ instant review for qualifying rooftop systems, then file the city permit.
  • ADUs: up to 850 square feet (1,000 with two or more bedrooms), junior ADUs up to 500, 3-foot side and rear setbacks. A detached ADU closer than 4 feet to a line needs a surveyor’s form certification before the pour, and new detached ADUs need solar panels.

Commercial permits

Commercial, multi-family and industrial work follows its own valuation table and goes through plan review. Under Albany’s amendment to the fire code (Municipal Code section 11-6), an alteration of a non-residential occupancy triggers automatic sprinklers when the altered area exceeds 50% of the occupancy or the occupancy changes, unless the space is separated by two-hour fire walls. Signs need planning sign approval first.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Design review. The Community Development Director reviews residential alterations or additions under 400 square feet (other than second stories) and accessory structures over 120 and under 200 square feet. The Planning & Zoning Commission hears new construction or additions of 400 square feet or more, accessory structures of 200 square feet or more, every second-story addition, roofline changes and height exceptions. The commission meets on the second and fourth Wednesdays.
  • Watercourse Overlay. Lots near Cerrito or Codornices Creeks may sit in the FEMA-mapped Watercourse Overlay District, governed by the flood damage prevention rules in Municipal Code section 20.52; talk to staff before the design is final.
  • Fire Prevention Bureau. Call (510) 528-5775 before plans are final; the plan check package includes a Fire Safety Requirements Checklist.
  • Encroachment. Street trenching, dumpsters, pods and reserved parking need an encroachment permit.

Albany permit costs and fees

Albany’s fees are set in the Master Fee Schedule, which the City Council approves each year and which takes effect on July 1. The FY 2026-27 schedule took effect July 1, 2026. Permit fees follow valuation, which the schedule’s own table sets (one- and two-family housing $296.40 per square foot; remodels 75% and decks 35% of that).

Selected Albany building fees, FY 2026-27
ItemFee (FY 2026-27)
Application fee (every building permit)$89.30
General plan update fee / technology fee$8.20 / $20.50
Single-family permit fee at $25,000 / $50,000 / $100,000$401.90 / $535.90 / $1,607.50
Plan check, city processing fee (valuation up to $100,000)$267.80, plus the consultant’s actual cost
Residential re-roof (flat rate)$267.80
Residential remodel, repair, windows and doors$267.80 up to $10,000 of work; $803.20 over $100,000
Residential or simple standalone MEP permit (up to 3 items)$267.90
Complex MEP (whole-house rewire or repipe)$535.50
Re-inspection / temporary certificate of occupancy$267.80 / $401.60
Residential fire sprinkler system (Fire Department)$719.50, including one plan review, hydrostatic test and final
Minor encroachment (curb, gutter, sidewalk, driveway, lower lateral)$267.80

Waived and doubled fees. The Council has waived the MEP fee for EV chargers, gas-to-electric appliance swaps, solar thermal and their panel upgrades, and the flat fee for battery storage and voluntary solar systems; the state-mandated building standards fee still applies. Work started without a required permit pays double the building or encroachment portion of the permit cost.

Rather talk it over?

Call 1-855-478-4290 →

Impact and connection fees. The capital facilities impact fee is $0.65 per square foot for residential additions and conversions, and $375, $840 or $1,365 for a new home of 600 square feet or less, 601–1,000 square feet or over 1,000 square feet; a new ADU under 750 square feet is exempt by state law. A new sewer service costs $1,407.40 and each new fixture on an existing service $226.40. Storm drain impact fees are $0.10 per square foot. School impact fees on new floor area over 500 square feet are set by the Albany Unified School District.

Worked example. A single-family project valued at exactly $100,000 that goes through plan review pays the city $1,607.50 (permit) + $89.30 (application) + $8.20 (general plan update) + $20.50 (technology) + $267.80 (plan check processing) = $1,993.30, before the plan check consultant’s actual cost, the state fees and any impact or school fees. The table’s bands do not chain exactly, so read the fee at your own band.

Trade permits and who may pull them in Albany

Electrical, plumbing and mechanical permits are issued by the Building Division. A residential or simple standalone MEP permit covers up to three items from the schedule’s lists, such as a water heater, an HVAC change-out, receptacles and lighting, a service of up to 400 amperes or bathroom fixtures; larger jobs such as a whole-house rewire or repipe are charged as complex MEP.

Who can apply

  • State-licensed contractors, for any permit
  • Agents and permit expeditors, with the owner’s written authorization; the licensed contractor doing the work must be listed
  • Property owners, either naming their hired contractor or acting as owner-builder

Owner-builder conditions

  • You must own the property
  • It must be your primary residence for at least 12 months before the work is completed
  • You must do the work yourself

Albany business license. Any contractor or handyman hired to work in Albany must hold a current Albany business license when the permit is issued. Since October 27, 2025, HdL Companies has processed the city’s business license applications, renewals and reissues (customer support (510) 292-4619). A first license carries a $20.50 issuance fee plus the business tax, and renewals are due each January 31.

Rather not deal with the building department?

Get a free quote →

How to apply for an Albany building permit

1. Check planning first

Additions, second stories, larger accessory buildings and roofline changes need design review in Cloudpermit before the building permit.

2. Create a Cloudpermit account

Register at us.cloudpermit.com/city-of-albany-ca. Projects first submitted by email before the switch stay in the older system.

3. Prepare the package

For plan review: the application, sealed plans where state licensing rules require them, structural calculations, the Stormwater and Fire Safety Requirements Checklists, and a soils report with the engineer’s conformance letter.

4. Submit and pay the plan check fee

Applications are not processed until everything requested is in and the plan check fees are paid.

5. Answer corrections

Comments from the city and its plan check consultant come back through the portal; later plan changes cost $535.50 in added review.

6. Get the business license and pay the permit fees

The contractor’s Albany business license must be active, and impact, sewer and school fees are due before issuance.

7. Keep the permit and approved plans on site

Changes to approved plans must be made in writing; work that does not match the approved plans has to be removed or corrected.

Review, corrections and what causes delay

Review does not start until every requested item and the plan check fee are in. Commission design review adds a hearing date with 10 days’ notice to owners within 300 feet. Skipping the Fire Prevention Bureau call or the Watercourse Overlay check, or a contractor without an Albany license, also stalls permits. A permit expires if work does not start within 365 days or if no inspection takes place for 365 days; the Building Permit Extension Request form is used to ask for more time, and extensions carry no fee.

Inspections in Albany

The permit holder schedules inspections through the Cloudpermit project workspace, by calling 510-528-5760 or by emailing permits@albanyca.org. The office can usually offer next-day inspections but asks for up to 3 days’ lead time, and a cancellation must be phoned in by 9:00 a.m. on the inspection day. Construction is allowed from 8:00 a.m. to 6:00 p.m. Monday through Saturday and from 10:00 a.m. to 6:00 p.m. on Sundays and legal holidays.

  • Foundation, slab and under-floor: forms, steel, anchor bolts and buried piping in place, before concrete or sheathing.
  • Nailing: sheathing nailed, before roofing or siding.
  • Rough plumbing, mechanical and electrical: when framing is complete and before cover, with drains water-tested and gas piping air-tested.
  • Frame and insulation: with all framing, fire blocking and bracing in place; sprinkler lines and fire alarm wiring are inspected by the Fire Department before insulation.
  • Lath or wallboard: before plaster, stucco, tile or taping.
  • Final: Planning & Zoning, Fire, Public Works and Environmental Resources must all sign off before anyone moves in; up to five working days’ notice may be needed.

Special inspectors for concrete, welding, structural masonry and similar work must be approved by the Building Inspector. A return visit after a failed inspection costs $267.80.

California building code in Albany

California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments

Want this handled start to finish?

Get a free quote →

Ordinance No. 2026-01 adopted the 2025 California Building Standards Code into the Albany Municipal Code and named the optional appendices that apply in the city, among them flood-resistant construction, grading, patio covers, sleeping lofts and the residential appendices for tiny houses, radon control and existing buildings. Its findings cite older wood-frame buildings on small lots, Diablo winds from the East Bay Hills and expansive soils.

Frequently asked questions

Does Albany issue its own building permits?

Yes. The Building Division of the Community Development Department issues building, electrical, plumbing and mechanical permits for all property inside the city.

Do I need a permit for a shed or fence in Albany?

A one-story shed up to 120 square feet and a fence up to 7 feet need no building permit, but zoning caps residential fences at 6 feet (3 feet in the front yard), and larger accessory buildings need design review too.

How much is a building permit in Albany?

Every permit starts with an $89.30 application fee plus $8.20 and $20.50 surcharges. A $100,000 single-family job adds a $1,607.50 permit fee and $267.80 plan check processing, plus the consultant’s cost.

Can a homeowner pull a permit in Albany?

Yes. An owner can list a hired contractor or act as owner-builder, but to be an owner-builder you must own the property, make it your primary residence for at least 12 months before the work is finished, and do the work yourself.

Does my contractor need an Albany business license?

Yes. Any contractor or handyman hired to work in Albany must have an active Albany business license before the permit is issued.

How fast can I get an inspection?

The city can usually schedule next-day inspections, but asks for up to 3 days’ notice.

Do ADUs in Albany need planning approval?

No separate planning approval is needed for an ADU; it needs a building permit. New ADUs under 750 square feet are exempt from the capital facilities impact fee.

How long is an Albany building permit good for?

Work must start within 365 days, and the permit lapses if 365 days pass without an inspection. Extensions are requested on the city’s extension form and are free.

Albany permit search and official resources

Permits filed in Cloudpermit can be tracked in the portal, which emails the applicant when the status changes. For older permits and plans, ask the Community Development Department for the property history; printed copies cost $0.25 a page under the fee schedule.

Inspections are where schedules slip.

Get a free quote →

Simplify Albany permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Albany sooner?

Let Alliance prepare, file, and track your Albany permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Albany permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.