In the Village of Germantown, Building Inspection Services in the Community Development Department at Village Hall, N112 W17001 Mequon Road (262-346-4460), issues every building, electrical, plumbing and HVAC permit; SAFEbuilt WI staff do the permit processing, plan review and inspections. A new house is charged $0.44 per square foot under the 2026 fee schedule plus fixed fees, the village’s 2026 impact and utility connection fees total $8,588 per home inside the water and sewer service areas, and work started before the permit costs triple.
What requires a building permit in Germantown?
The village’s rule is that every building, out-buildings and garages included, needs a permit before it is built, and that changes to or installations of electrical, plumbing, HVAC systems and driveways need a permit before work begins. Its residential handout lists the common projects.
Residential permits
- New one- and two-family homes and additions
- Garages and storage sheds
- Decks, porches and gazebos
- Swimming pools and fences
- Finished basements and remodeling, kitchens included
- Heating and air conditioning
- Siding and reroofing
- Foundation repairs and egress windows
- Solar, wind and fireplaces or wood stoves
Building or remodeling a home here? Alliance handles residential permit applications, so the crew isn't waiting on the counter.
Other village permits
- Electrical, plumbing and HVAC work
- Driveways, approaches and culverts (Engineering)
- Erosion control for new homes and land disturbance (Engineering)
- Wrecking or razing, and moving a building over a street
- Propane tanks
- Outside water and sewer work
Projects not on the list may still need a permit; the department asks owners to call 262-346-4460 when unsure. A subdivision’s architectural approval and a homeowners association’s approval are separate from the permit.
What the village decides and what the state holds
The village administers its own zoning code, its shoreland, wetland and floodplain zoning and its 2050 Comprehensive Plan, and its Community Development Department supports the Village Board, Plan Commission and Board of Zoning Appeals. The construction standards are the state’s: the Uniform Dwelling Code for one- and two-family homes and the commercial building code, which Germantown enforces itself because DSPS has delegated commercial building, HVAC, plumbing, fire suppression and fire sprinkler plan review and inspection to the village since February 25, 2021.
Germantown building department: who handles permitting
Building Inspection Services oversees new construction and alterations of homes and commercial buildings and the installation of plumbing, electrical and heating and air conditioning systems. The village contracts SAFEbuilt WI for permit processing, plan review and inspections, and the state’s Uniform Dwelling Code list, current as of September 24, 2026, shows the Village of Germantown as a delegated municipality. The Town of Germantown is a separate municipality with its own entry.
Short on time to read all of this?
Get a free quote →| Office | Contact |
|---|---|
| Building Inspection Services (building, electrical, plumbing, HVAC, zoning compliance) | N112 W17001 Mequon Road, Germantown, WI 53022; 262-346-4460; germantowninspections@safebuilt.com; staff Monday to Friday, 8:00 a.m. to 3:30 p.m.; inspectors in the office 8 to 10 a.m. |
| Engineering Department (driveways, culverts, erosion control) | Same address; 262-250-4721; engineering@germantownwi.gov |
| Village Hall | 262-250-4700; Monday to Friday, 8:00 a.m. to 4:30 p.m. |
| Septic systems | Washington County Planning & Parks, Public Agency Center, Suite 2300, 333 East Washington Street, West Bend; 262-335-4445 |
Card payments (Visa, Mastercard or Discover) are accepted at the inspection window in Village Hall, but not over the phone.
Germantown permit types and application documents
The 2026 building permit application covers one- and two-family, multi-family, commercial and agricultural work. It asks for the description of work, the size, height, zoning district, setbacks, estimated cost, the owner, and the contractor’s Dwelling Contractor and Qualifier numbers with expiration dates. By signing, the applicant agrees to get inspection results by email, as SPS 320.10(4) allows.
Residential permits
A new one- or two-family home needs a complete set of plans with elevations and a materials cross section, energy worksheets from the heating contractor or an energy consultant, the makeup and combustion air worksheet where open-combustion appliances are used, a lot survey with the house staked, setbacks, driveway location and elevations to the village datum including the curb stop, the state UDC permit application completed on the DSPS eSLA website, and an erosion control permit application. At submittal the village wants three sets of plans (one on 11-by-17 paper) with roof, siding and trim colors noted, five copies of the survey and two energy worksheets. There is no fee at submittal; the house permit includes the plumbing, HVAC and electrical permits but not the outside water and sewer permit. Additions and accessory buildings need two sets of plans and a survey.
Commercial permits
Commercial building and occupancy permits need sign-off from both Planning and Engineering, and buildings over 50,000 cubic feet need state-approved plans. The submittal is the building permit application, two sets of approved plans and one more for the Fire Department, an erosion control application with two erosion control plans, the sewer and water connection data form, a driveway permit application, a Fire Department inspection application and a $20,000 occupancy bond in cash or a letter of credit. Under its delegation the village can give the DSPS-authorized plan review itself.
For tenant improvements and new commercial builds, Alliance handles commercial building permits through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Planning approvals. Contact the Planning Department about village approval requirements; most subdivisions also require architectural approval.
- Septic. On a private system, a sanitary permit or approval from Washington County comes first, for new homes and for exterior projects.
- Driveway. An Engineering Department permit; in the A-1, A-2 and Rs districts a driveway is 12 to 25 feet wide at the road and at least 5 feet from the side lot line, and on new construction the curb stop must be at least 5 feet from it.
- Erosion control. An Engineering Department permit for every new home.
- Fences. Up to 6 feet in rear and side yards and 4 feet in front (up to 6 with Plan Commission approval), at least 2 feet from the right of way, and not on an easement without the Plan Commission.
Germantown permit fees (2026)
The village’s 2026 Building Inspection Fee Schedule, revised December 15, 2025, sets the fees below, and a $4.23 technology fee is added to every permit. More than one fee usually applies: the schedule says a new home is charged a base construction fee, plan review, property record maintenance, zoning compliance, occupancy, erosion control and the state building permit seal, plus the HVAC, electrical and plumbing fees.
| Item | Fee |
|---|---|
| New dwelling, with or without attached garage / addition | $0.44 per sq ft / $0.44 per sq ft |
| Major remodel, including basement finish | $0.40 per sq ft or $7.41 per $1,000 of value |
| Minor remodel | $0.27 per sq ft or $5.30 per $1,000 of value |
| Deck or porch | $0.27 per sq ft |
| Detached garage or accessory building over 192 sq ft / 192 sq ft or less | $0.32 per sq ft / $68.77 |
| Fence, reroofing or siding | $68.77 each |
| Swimming pool | $11.64 per $1,000 of value |
| Early start (footings and foundation only) | $185.13 |
| Wisconsin uniform building permit seal / occupancy permit | $68.77 / $68.77 |
| Plan review: new dwelling / addition / remodel | $238.02 / $79.35 / $58.19 |
| Property record maintenance: new dwelling / addition / accessory | $211.57 / $84.63 / $15.88 |
| Zoning permit: new dwelling / additions, accessory buildings, fences | $185.13 / $26.46 |
| Erosion control, new one- or two-family home | $185.13 per lot |
| HVAC or plumbing, new construction / electrical, new construction | $0.10 per sq ft each |
| Furnace or air conditioner replacement (includes electrical) | $105.79 |
| Minimum construction, HVAC, plumbing or electrical permit | $68.77 plus the $4.23 technology fee |
| Re-inspection (third or more) / failure to call for inspection | $68.77 / $68.77 |
| Work started without or before a permit | Triple fees |
Rather talk it over?
Call 1-855-478-4290 →For a new home the fixed charges on the schedule add up to $957.39 before any per-square-foot fee: plan review $238.02, property record maintenance $211.57, zoning permit $185.13, erosion control $185.13, the state seal $68.77 and one occupancy permit $68.77. The construction, HVAC, plumbing and electrical fees are then figured on the home’s area, and the technology fee is added to each permit.
Impact and utility connection fees for 2026 are separate: $1,003 water, $1,311 park and recreation, $171 fire, $148 police, $711 library and $5,244 sewer, $8,588 in all for a home. The water and sewer fees apply only inside the village’s water and sewer service areas, and the sewer fee rises 3.25% every January 1. Commercial buildings pay $1,003 water and $5,244 sewer per REC (the schedule’s connection unit), and fire and police impact fees of $0.63549 and $0.2809 per $1,000 of construction cost.
Trade permits and who may pull them
Germantown issues its own electrical, plumbing and HVAC permits, with separate application forms for each, and its inspectors check the work. On a new house those permits are rolled into the building permit cost; on other projects the building permit form warns that separate electrical, plumbing and heating permits may be required. Under the village’s DSPS delegation, commercial HVAC, plumbing, fire suppression and sprinkler plans are reviewed locally too.
- Contractors. A contractor pulling permits for work on one- and two-family homes must hold both the state Dwelling Contractor certification and the Dwelling Contractor Qualifier certification, and the village form records both numbers; an owner-occupant building their own home is exempt under state law.
- Electrical fees. $52.90 for a service up to 200 amps, $10.58 for each further 100 amps, $77.25 for a home vehicle charger and $105.79 for in-ground pool wiring.
- Plumbing fees. $10.58 a fixture for remodels and replacements, $52.90 for the first 100 feet of sewer or water line and $0.49 for each foot beyond.
- Plumbing tests. The forms list includes an affidavit of plumbing testing and a compliance statement.
Rather not deal with the building department?
Get a free quote →How to apply for a Germantown building permit
Ask Planning about approvals and get any subdivision architectural or HOA approval.
Apply to Engineering for the driveway and erosion control permits; on a septic lot, start with Washington County.
For a new home, complete the UDC permit application on eSLA.
Plans, surveys, energy worksheets and the village building permit application.
No fee is due at submittal for a new home.
Pay the fees once they are set; cards are taken at the Village Hall inspection window, not by phone.
Call before 4 p.m. for the next day.
Review, corrections and what causes delay
Applications are reviewed first come, first served, and review time depends on the project and the line of applications ahead of it. A new-home file is held up by missing pieces such as the energy worksheets, the staked survey with datum elevations and curb stop, or the eSLA state application with contractor credentials. Commercial permits wait for Planning and Engineering sign-off and the $20,000 occupancy bond. To talk a plan through with an inspector, come between 8 and 10 a.m. on a weekday.
Inspections and occupancy in Germantown
Inspections must be scheduled before 4 p.m. for the next day, at 262-346-4460. A new home goes through footing (with the surveyor’s recertification of the footings), foundation (before backfill, with waterproofing and drain tile done), an optional service inspection, rough electrical, rough under-floor and rough plumbing, drain tile, rough framing, insulation, exterior plumbing for the sewer and water laterals (the curb stop ending 6 inches above grade), final electrical, final plumbing and the final inspection.
The water meter and house numbers must be in before the final; the occupancy permit is issued at the final inspection, and moving in earlier brings the ordinance’s penalties. Inspectors will not enter a building that has belongings in it without an escort. The re-inspection fee, charged from the third inspection on, is $68.77, as is a missed call for a required inspection. Each inspection gets a written report, kept in the property file as a history for current and future owners.
The village has no certificate of compliance program, so it requires no compliance certificate before a property changes hands.
Want this handled start to finish?
Get a free quote →Wisconsin building code
FEMA’s Community Status Book lists Germantown (community 550472) as participating in the National Flood Insurance Program, with a current effective flood map dated February 20, 2026; the village administers its own floodplain zoning.
Wisconsin's Uniform Dwelling Code covers one- and two-family homes. Its Commercial Building Code covers public buildings, workplaces and buildings of three or more units. Local ordinances must conform to both. Wisconsin rules
Germantown permit search and official resources
Property files are public records, open for inspection at Building Inspection Services during regular office hours; staff can supply copies of property surveys, building, plumbing, electrical and heating permits, and address displays. Call 262-346-4460 before visiting.
- Building Inspection Services
- Community Development Department
- 2026 Building Inspection fee schedule
- 2026 impact and utility connection fees
- New one and two family homes
- New home application requirements
- Inspections required
- Residential permits required
- General information on residential permits
- Commercial or industrial buildings
- Commercial plans, approvals and submittals
- Permit applications and forms
- Building permit application (2026)
- Erosion control permit application
- Driveway and culvert permit
- Building inspection FAQs
- DSPS list of UDC delegated agents
- FEMA Community Status Book, Wisconsin
Inspections are where schedules slip.
Get a free quote →Germantown building permit FAQ
How much is a building permit for a new house in Germantown?
$0.44 a square foot for the construction, plus fixed fees totaling $957.39, trade fees, $4.23 per permit and, inside the service areas, $8,588 in impact and connection fees.
Do I need a permit for a fence?
Yes, $68.77 plus a $26.46 zoning fee, with a survey showing the right of way, easements and lot lines.
Do I need a permit to reroof or reside?
Yes. Reroofing and siding are $68.77 each for a home.
Is a small shed exempt?
No. A shed of 192 square feet or less is a flat $68.77; larger ones are $0.32 a square foot.
What happens if I start without a permit?
The permit fees are tripled.
Can I pay by credit card?
Yes, Visa, Mastercard or Discover at the inspection window in Village Hall, but not by phone.
Is this the Town of Germantown?
No. The Village of Germantown and the Town of Germantown are separate municipalities, each with its own building permit arrangements on the state list.
Does Germantown require an inspection when a house is sold?
No. The village has no certificate of compliance program.
Simplify Germantown permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Wisconsin. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Germantown sooner?
Let Alliance prepare, file, and track your Germantown permits while your crew stays on the job.
More Wisconsin permitting guides
Washington County
Read guide →Hartford
Read guide →Richfield
Read guide →Glendale Building Permit Guide
Read guide →Grafton Building Permit Guide
Read guide →Grand Chute Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Germantown permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.