Raleigh County, West Virginia Building Permit Guide

To get a building permit in Raleigh County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

In unincorporated Raleigh County the Raleigh County Building Code Office in Beckley enforces the State Building Code and takes building permit applications through its iWorQ citizen portal.

Authority: Raleigh County Building Code OfficeCode: State Building Code: 2018 IBC and IRC, 2020 NECPhone: (304) 255-9388
Building Code Office
203 South Eisenhower DriveBeckley; weekdays 8:00 am to 4:00 pm
Permit fee
0.5% of estimated cost$20 minimum
Apply
iWorQ citizen portal15 permit applications
Zoning first
Location Improvement PermitPlanning and Zoning, 116 N. Heber Street

In unincorporated Raleigh County the Raleigh County Building Code Office, the county’s Code Enforcement Department, issues building permits under the State Building Code, with applications filed through its iWorQ citizen portal. The permit fee is 0.5% of the estimated cost of the work, with a $20 minimum, and inspections are included in that fee apart from repeat re-inspections.

The county has enforced a building code since its Building Code Ordinance of April 15, 2003. The current version, effective June 6, 2023, adopts the State Building Code with the 2018 International Building, Residential, Plumbing, Mechanical, Fuel Gas and Existing Building Codes, the 2015 International Energy Conservation Code for homes, ASHRAE 90.1-2013 for commercial energy use and the 2020 National Electrical Code. Every structure also needs zoning and floodplain clearance from the county’s Planning and Zoning office, which issues a Location Improvement Permit under the planning and zoning ordinance amended on September 1, 2026.

The county building permit covers the unincorporated area. The City of Beckley runs its own Code Enforcement Office and the Town of Sophia issues its own building permit; Mabscott, Lester and the Raleigh County part of Whitesville are listed under Who handles permitting.

📜

No inspection does not mean no zoning check. A storage shed of up to 200 square feet with no plumbing or electrical connections, used only for residential storage, is not inspected by the county, but the ordinance still requires a pre-application so zoning and floodplain rules can be checked.

What requires a building permit in Raleigh County?

A building permit is required to construct, alter, renovate or demolish, and the iWorQ portal lists the applications the Building Code Office takes. The applications for new buildings, additions, garages, storage buildings, signs, decks, pools and cell towers need a site plan.

Permit applications on iWorQ

  • New residential or commercial building
  • Addition, garage, storage building and deck
  • Swimming pool, spa or hot tub
  • Roofing, siding and windows
  • Demolition
  • Plumbing/mechanical, electric, solar panel and generator
  • Sign and cell tower

No building permit (Section 1-505)

  • One-story detached accessory building of up to 200 square feet with no electrical, plumbing or mechanical work
  • Deck of up to 200 square feet and no more than 30 inches above grade
  • Fences up to 7 feet high, and retaining walls up to 2 feet above grade that support no surcharge
  • Sidewalks and driveways up to 30 inches above grade, not over a basement or part of an accessible route
  • Painting, papering, tiling, carpeting, cabinets, countertops and similar finish work
  • Prefabricated above-ground pools under 24 inches deep holding up to 5,000 gallons
  • Swings and playground equipment, and window awnings projecting up to 54 inches

Agricultural buildings

Buildings used primarily for agriculture, including agritourism, fall outside the State Building Code. An owner who claims that exemption puts the question to the West Virginia Commissioner of Agriculture, who decides and sends a copy of the decision to the county.

Short on time to read all of this?

Get a free quote →

West Virginia lets each county and city adopt the State Building Code or no building code at all; no other building code may be adopted, and floodplain, sewage and fire rules can apply either way. West Virginia rules

Raleigh County building department: who handles permitting

The Building Code Office receives and processes applications, issues building permits, inspects construction and issues or denies certificates of occupancy. Zoning, floodplain and stormwater questions go to the county offices at 116 N. Heber Street, and inside Beckley the city handles all of this itself.

Raleigh County permit offices
DetailInformation
Building Code Office203 South Eisenhower Drive, Beckley, WV 25801
Phone(304) 255-9388; fax (304) 255-9391
HoursMonday to Friday, 8:00 am to 4:00 pm, closed noon to 1:00 pm
OnlineiWorQ citizen portal: permit applications and a search of existing permits
Planning and Zoning116 N. Heber Street, Beckley, (304) 255-9173; Monday to Friday, 8:30 am to 4:30 pm, closed noon to 1:00 pm
Floodplain Management116 N. Heber Street, Beckley, (304) 255-9146 or (304) 255-9173
Septic systems and wellsBeckley-Raleigh County Health Department, 1602 Harper Road, Beckley, (304) 252-8531; its approval is required for the Location Improvement Permit

In 2025, building permits issued in unincorporated Raleigh County authorized 49 new privately owned housing units, all of them single-family homes, according to the U.S. Census Bureau Building Permits Survey.

Who issues permits in each municipality

Permit offices in Raleigh County’s cities and towns
MunicipalityWho issues permitsPhone
BeckleyCity Code Enforcement Office, 232 Industrial Drive; State Building Code with the 2018 International codes; plan review at no charge on scheduled days; commercial permits need the city Fire Marshal’s approval(304) 256-1738
SophiaTown building permit: file the town’s online Pre-Application with a site plan showing the setbacks; the town’s Zoning Officer must approve the zoning and setbacks before the permit is issued, and contractors file a town contractor licence application; Town Hall, 100 E. Railroad Avenue, Monday to Thursday 7:00 am to 4:00 pm, Friday 7:00 to 11:00 am(304) 683-4456
MabscottThe town’s published pages do not describe a permit process; ask the town office(304) 253-5654
LesterNo town permit information is published; ask town hallNot published
Whitesville (Raleigh County part)The town lies almost entirely in Boone County, and the Census counts no residents in its Raleigh County part; the published sources do not say who permits thereNot published

Not sure this scope needs a permit?

Get a free quote →

Permit types

Residential permits

A new house is filed as a New Residential or Commercial Building Permit with a site plan. One- and two-family dwellings are exempt from the two-set drawing review, but the application still has to show, where they apply, the tax map, parcel and lot, the zoning, use and setback approval, the property boundaries, approved water and sewer service, a floodplain elevation certificate, a street address checked by the county EOC, stormwater approval, and contractor and trade licence verification.

Commercial permits

Every other building that needs construction plans requires two sets of drawings, reviewed and approved before the permit is issued, with one stamped set kept on the job site until completion. A $100 plan review fee is paid on the first submission of commercial or nonresidential documents, and the application includes the fire marshal’s inspection and approval report.

Insurance and abandoned applications

No permit is issued for a new building, or for exterior renovation or alteration, until the contractor files proof of workers’ compensation and general liability insurance of $500,000 per occurrence and $1,000,000 aggregate. The portal treats an application as abandoned 180 days after it was first submitted.

West Virginia licenses contractors at state level through the Contractor Licensing Board, run by the Division of Labor, valid statewide. West Virginia rules

Raleigh County permit costs and fees

Section 1-701 of the Building Code Ordinance sets the fees in effect since July 1, 2023. The estimated cost is the reasonable cost of labor and materials for the whole job until it is ready for use, and a project may not be split into smaller jobs to lower the fee. All fees are paid before the permit is issued.

Rather talk it over?

Call 1-855-478-4290 →
Raleigh County building permit fees (effective July 1, 2023)
ProjectFee
Building permit: construction, alteration, renovation or demolition0.5% of the estimated cost; $20 minimum
Plan review, commercial or nonresidential documents$100 on first submission
InspectionsIncluded in the permit fee
Re-inspection after a failed inspectionFirst one free, then $35 each
Electrical re-inspection (the electrical permit fee covers the first inspection)$40 each
Inspection not ready when scheduledCounted as a failed inspection, $35
Final inspection not scheduled within three business days of completion$35 administrative fee plus $35 re-inspection fee
Work started without a permitDouble the permit fee, plus $35 per inspection
Permit renewal before expiry$20
Permit obtained fraudulently or work by an unlicensed contractor or tradesman$50 administrative fee; $100 for a repeat

When no estimated cost is given, or the figure is in question, the county values the work at $100 per square foot for inhabited space, $80 per square foot for garages, porches, decks and accessory buildings, and $60 per square foot for unfinished basements, sidewalks, driveways and walkways. Example: a house with 2,000 square feet of living space and a 500-square-foot garage priced on those values comes to $240,000 ($200,000 + $40,000), so the permit fee is $1,200.

⚠️

Permits last one year. A building permit can be renewed before it expires for $20. If it lapses for more than 10 days, a new permit is needed, priced on the remaining job cost, and no inspection can be scheduled while a permit is expired.

Trade permits and who may pull them

Separate county applications

  • Electric permit; the power company requires an electrical service inspection before it connects or restores power, service upgrades included
  • Plumbing/mechanical permit
  • Solar panel and generator permits
  • Electrician, plumber and mechanic licence verification on the application

No permit needed (Section 1-505)

  • Minor electrical repairs, such as replacing lamps or connecting portable appliances to permanent receptacles
  • Portable heating, cooking or clothes drying appliances
  • Clearing stoppages and repairing leaks without replacing or rearranging pipes, valves or fixtures
  • Portable heating, ventilating or cooling units, and self-contained refrigeration of 10 pounds or less with motors of one horsepower or less

Rather not deal with the Raleigh County building department?

Get a free quote →

The ordinance makes it county policy that everyone doing work regulated by the State Building Code in Raleigh County holds the state licence or certification for that work, and the Building Code Office can issue cease and desist orders to anyone contracting without one.

Trade work is permitted separately where the jurisdiction enforces the code and done by state-licensed contractors. West Virginia rules

How to apply for a Raleigh County building permit

1. Confirm the parcel is in the county’s area

Inside Beckley or Sophia, apply to the city or town. For Mabscott or Lester, ask the town first.

2. Get the Location Improvement Permit

Planning and Zoning at 116 N. Heber Street needs the tax district, map and parcel, a site plan with property lines, buildings and setbacks, the adjoining roads, and sewer and water certificates or the health department’s septic and well approvals.

3. Line up addressing, stormwater and floodplain

A street address checked by the county EOC, stormwater approval, and an elevation certificate if the site is in the floodplain (Floodplain Management, 304-255-9146 or 304-255-9173).

4. Apply on iWorQ

Choose the permit type, complete the required fields and uploads, and attach the site plan where marked. Commercial jobs add two sets of drawings and the $100 plan review fee.

5. Pay the fee and post the permit

The permit is issued once the fees are paid; contractors file their insurance certificates and licence details first.

6. Book inspections and the final

Call for each stage before covering work, and schedule the final within three business days of finishing to avoid the $35 charges.

When the county can hold back a permit

At the County Commission’s request, a building permit, inspection or certificate of occupancy may be denied for a violation of another county ordinance, a state licensing or code violation, or an unpaid county tax, fee or assessment.

Inspections in Raleigh County

The ordinance lists the required stages for new construction. The footing, foundation or slab is inspected after excavation and before concrete is poured, with footers at least 24 inches deep and 8 inches thick and rebar at least 3 inches from the bottom and sides. Rough-in inspections of electrical, mechanical, plumbing, framing and insulation come before anything is covered. A final inspection checks the work against the State Building and Fire Codes and the approved drawings, and licensing, addressing, zoning, floodplain and stormwater requirements must all be met before the certificate of occupancy is issued. No structure may be occupied lawfully until it has one. Work started without a permit gets a stop work order, an inspection of the work already done at $35, and possibly a report from a West Virginia design professional.

Want this handled start to finish?

Get a free quote →

Raleigh County permit search and official resources

Inspections are where schedules slip.

Get a free quote →

Frequently asked questions

How much is a building permit in Raleigh County?

0.5% of the estimated cost of the work, with a $20 minimum, so a $300,000 house pays $1,500. Commercial and nonresidential projects add a $100 plan review fee, and inspections are included apart from repeat re-inspections at $35.

Does Raleigh County enforce the State Building Code?

Yes. The county has had a building code ordinance since 2003, and the version effective June 6, 2023 adopts the State Building Code with the 2018 International codes and the 2020 National Electrical Code.

Do I need a permit for a shed or a deck?

Not for a one-story detached shed of up to 200 square feet with no utilities, or a deck of up to 200 square feet no more than 30 inches above grade. Both still need the zoning and floodplain pre-application.

How long is a Raleigh County building permit valid?

One year from issue. It can be renewed before it expires for $20; after more than 10 days expired, a new permit is needed.

Who issues building permits in Beckley?

The City of Beckley’s Code Enforcement Office at 232 Industrial Drive, (304) 256-1738, not the county.

What happens if I start work without a permit?

The county issues a stop work order, charges double the permit fee and $35 for each inspection, and may require a report from a West Virginia design professional before the order is lifted.

Simplify Raleigh County permitting with Alliance Permitting

In Raleigh County the parcel's history underground decides more than the code above it. We read the mining record and the geotechnical report before anything is sited.

Ready to break ground in Raleigh County sooner?

Send us the scope and the parcel. We confirm the review path with the Raleigh County building inspection office, assemble the submittal, file it, and track it through issuance — corrections included.

More West Virginia permitting guides

This guide is provided by Alliance Permitting for general information about Raleigh County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.