Summit County, Utah Building Permit Guide

The Summit County Building Department in Coalville issues building permits for unincorporated Summit County, including the Snyderville Basin, entirely online through EPROCESS 360; Park City and the county’s other cities and towns run their own permitting.

Authority: Summit County Building DepartmentCode: Utah State Construction Code (2024 IBC, 2021 IRC, 2023 NEC)Phone: 435-336-3124
Authority
Building DepartmentBuilding Official Andy Davis
Apply
EPROCESS 360No paper plans or counter reviews
Review time
Up to 14 business daysNew homes; 21 for new commercial
2025 population
43,14126,559 in unincorporated areas

Building permits for unincorporated Summit County come from the County Building Department, 60 North Main Street, Coalville (435-336-3124), and every application, review and permit is handled online in EPROCESS 360. A new house can take up to 14 business days to review. Park City, Coalville, Francis, Henefer, Kamas and Oakley each permit construction inside their own limits.

What requires a building permit in Summit County?

The County requires a building permit to build, enlarge, alter, repair, move, improve, remove, convert or demolish any building or structure, and for solar PV systems. Its checklists cover accessory structures, additions, basement finishes, decks, EV chargers, exterior cladding, generators, geothermal and radiant heat, manufactured and modular homes, pools and hot tubs, retaining walls, roofing, signs, temporary structures, utility upgrades and windows, as well as new homes and commercial buildings.

Permit needed

  • New homes, multi-family and commercial buildings
  • Additions, remodels and basement finishes
  • Solar, generators, EV chargers and geothermal systems
  • Roofing, windows and exterior cladding
  • Decks, pools, hot tubs and retaining walls
  • Demolition

No permit

  • Residential accessory buildings under 200 sq ft
  • Commercial accessory buildings under 120 sq ft
  • Certain agricultural buildings (with the County’s agricultural exempt acknowledgement)
  • Fences under 7 feet tall

Some projects need a separate Planning permit before the building application can be filed; the Planning Department (435-336-3124) confirms whether yours does. Lots with a slope of 15% or more need a geotechnical report.

Who issues building permits in Summit County?

The County Building Department reviews plans, issues permits and inspects in the unincorporated county; Andy Davis is the Building Official. Its review routes plans to the fire district, water and sewer providers, the recreation district and other agencies that serve the lot, and the County Engineering Division inspects rough grading. Each city and town handles its own building permits:

Short on time to read all of this?

Get a free quote →
Building permits in Summit County’s cities and towns
TownWho issues building permits
Park CityPark City’s own Building Department (permits and plan review)
CoalvilleCoalville City: plans go to City Hall and need sign-off from Planning and Zoning, Public Works and the North Summit Fire District
FrancisFrancis City’s Building Department does plan review and inspections
KamasKamas City, with its own building inspector (City office 435-783-4630)
OakleyOakley City: $50 application fee, South Summit Fire District clearance, and a Dark Sky agreement
HeneferHenefer Town’s building inspector (435-513-2943); town office 435-336-5365
HideoutTown of Hideout, through its CityInspect portal (the town lies almost entirely in Wasatch County)
Summit County building contacts
DetailInformation
OfficeBuilding Department, 60 North Main Street, P.O. Box 128, Coalville, UT 84017
Phone435-336-3124 (Building and Planning)
HoursMonday to Friday, 8 a.m. to 5 p.m.
ApplyEPROCESS 360 online portal
Engineering435-336-3250
Address requestsGIS Mapping, 435-336-3145
SepticSummit County Health Department, Environmental Health Division, 650 Round Valley Drive, Park City, 435-333-1500; Coalville office 435-336-3234

How to apply in EPROCESS 360

Register for an EPROCESS 360 account, choose Building Permit Application (or Right of Way Permit Application) under Create New, fill in every section, pick the scope of work and upload the documents that scope requires as unrestricted PDFs, each labeled with its document type. The parcel must already have an assigned address; GIS Mapping assigns one if it does not. Applications that arrive after 5:00 p.m. count as submitted the next business day, and incomplete ones are rejected. The County sends email updates as each department comments or approves.

Not sure this scope needs a permit?

Get a free quote →

Forms the County may require include the Owner/Builder Certification (the owner’s name must match County records, and front-counter staff can notarize it), the Construction Acknowledgement, a Construction Mitigation Plan, the County Gas Clearance Form, a Certificate of Survey or Elevation, a Pre-Sheetrock Insulation Certificate, the Window and Door Permit Worksheet, a Revision Description Form for plan changes and a Permit Extension Request. Approval letters from an HOA, the fire district, water and sewer providers or the recreation district can be uploaded with the application.

Summit County permit fees

Fees are calculated in EPROCESS 360 and shown on the permit’s Fees tab. Once an application is accepted the County may ask for a deposit before review begins, and the permit fees are paid the same way when the permit is ready; card payments are made online and cash or checks at the Coalville office.

Other fees that can apply to a new home
ItemDetail
Transportation impact fee (Ordinance 958)Applies across unincorporated Summit County; Exhibit C, the fee schedule Ordinance 958 imposes, lists $3,427.03 per single-family home and $1,938.52 per low-rise multifamily unit, paid at development approval; the County decides during permit review whether a project owes it
Service Area #3 road work fee (Silver Creek area)$8,500 for a new home up to 5,000 sq ft, $15,000 above that

Transportation impact fee questions go to the County’s Transportation Planning Deputy Director at 435-699-3105. Fire, water and sewer approvals come from the district or company serving the lot, which may set its own charges.

Rather talk it over?

Call 1-855-478-4290 →

Electrical, plumbing, mechanical and gas work in Summit County

Trade work is part of the County building permit and is inspected by the County’s building inspectors. Gas line and power-to-panel inspections happen only after the 4-way inspection: the gas line diagram and the County Gas Clearance Form must be uploaded, and the line must be under test pressure. Power to panel needs at least two 20-amp GFCI-protected circuits. Temporary power uses temporary service equipment, not the permanent panel, except for some free-standing meter sets approved case by case.

Septic and wells: homes on septic need Final Wastewater Approval from the Summit County Health Department before occupancy, and homes on a well upload the well log with the final documents. Homes on a public system need an approval letter from the water provider and, for sewer, from the Snyderville Basin Water Reclamation District where it serves.

Summit County submittal checklists and design values

Every project type has its own checklist (updated April 21, 2026), and everything on it must be uploaded at submittal. The County’s design criteria, effective July 1, 2026, use the Utah ground snow load map for snow, 115 mph wind, Seismic Design Category D or D1, a 36-inch frost line, a −7°F winter design temperature and required ice barrier underlayment; flood hazards follow the FEMA flood map.

New single-family homes may take up to 14 business days for review and new commercial projects up to 21 business days. Comments from each department appear on the permit’s Submittals tab, and corrected plans are uploaded there.

How to apply: 6-step Summit County process

1. Confirm the lot is unincorporated

Parcels inside Park City or one of the towns go to that city or town.

2. Check planning, address and agency approvals

Ask Planning whether a planning permit comes first, get an address assigned, and collect HOA, fire, water and sewer approval letters.

3. Register in EPROCESS 360

Create an account and start a Building Permit Application.

4. Upload the checklist documents

Label every PDF by document type; add a geotechnical report for slopes of 15% or more.

5. Pay the deposit and answer comments

Pay any deposit so review can start, then respond to each department’s comments and pay the permit fees.

6. Schedule inspections in the portal

Book County inspections in EPROCESS 360 and fire district inspections directly with the district.

Rather not deal with the Summit County building department?

Get a free quote →

Summit County inspections

Inspections are scheduled through EPROCESS 360, and a printed copy of the County-stamped plan must be on site. County Engineering inspects the rough grade before the footing inspection, and the geotechnical report must be on site at the footing. Required certificates of elevation or survey must be approved before the shear or framing inspection. Windows, fireplaces and furnaces must be installed before the 4-way, and spray foam must be inspected before other insulation covers it.

The local fire district inspects first, usually at the 4-way, final and solar stages, and its inspections are booked directly with the district. Special inspections listed on the plans are done by independent third-party inspectors, whose reports are uploaded to the portal. Remote areas along the Mirror Lake Highway, such as Manor Lands, Wilderness Acres and Christmas Meadows, are not given fixed inspection times because of travel distance.

A passed final inspection is not a Certificate of Occupancy: the C of O is issued only after Building, Engineering, the fire district, the water provider, the sewer district or Health Department and, for projects with a site plan, Planning have all signed off.

Local Summit County details that matter

Many service providers: the County’s permit review agency list names three fire districts (Park City, North Summit and South Summit), the Snyderville Basin Recreation District, the Snyderville Basin Water Reclamation District and several water companies, including Summit Water Distribution, Mountain Regional Water and Gorgoza Mutual Water. Which ones apply depends on where the lot is.

Steep lots: a geotechnical report is required where the slope is 15% or greater, and it must be on site at the footing inspection.

Construction mitigation: the County may require a Construction Mitigation Plan and a Construction Acknowledgement, and bonds posted for a project are released with the Bond Release Request Form.

Want this handled start to finish?

Get a free quote →

Issued permits: the County posts lists of issued building permits on its Building page.

Utah building code

Utah adopts one construction code for the whole state; cities and counties enforce it, and any local amendments are set by the Legislature. Utah rules

Official Summit County permitting resources

County, town and state sources:

Inspections are where schedules slip.

Get a free quote →

Summit County building permit FAQs

Who issues building permits in Summit County?

The County Building Department in Coalville (435-336-3124) for unincorporated areas, including the Snyderville Basin. Park City, Coalville, Francis, Henefer, Kamas and Oakley issue their own.

How do I apply?

Online only, through EPROCESS 360. The County does not take paper plans or do over-the-counter reviews.

How long does review take?

Up to 14 business days for a new single-family home and up to 21 business days for new commercial projects.

Do I need a permit for a shed or fence?

Not for a residential accessory building under 200 sq ft or a fence under 7 feet; larger sheds and taller fences need a permit.

Are there impact fees?

Yes. Ordinance 958 applies transportation impact fees across unincorporated Summit County, and its fee schedule (Exhibit C) charges $3,427.03 for a single-family home; whether your project owes it is decided during review.

Who approves septic systems?

The Summit County Health Department’s Environmental Health Division (435-333-1500), which reviews septic permit applications and inspects the installation; its final wastewater approval is needed before a Certificate of Occupancy.

Simplify Summit County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Utah. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Summit County sooner?

Let Alliance prepare, file, and track your Summit County permits while your crew stays on the job.