In Cecil Township, building permits come from the Building & Zoning Department at the municipal building, 3599 Millers Run Road (724-745-2227), and plan review and inspections are done by the township’s building inspector, Municipal Consulting Service, LLC. File the 2026 Construction Permit Application with a plot plan, two sets of drawings and a sewage approval letter. Under the fee resolution enacted on January 6, 2025, a new house costs $0.30 per square foot up to 5,000 square feet, plus the $4.50 state UCC fee.
What requires a building permit in Cecil Township?
The township’s Unified Development Ordinance (UDO, Ordinance 5-00 of May 17, 2000, now Chapter 240 of the township code) requires a permit before any building or structure, or part of one, is erected, built, altered or demolished, and before a use is started or changed. It also requires a township permit before anyone uses or occupies a building after new construction, an alteration, a change of use, a change of ownership, or a new tenant or renter in a leased building.
Permit needed
- New houses, commercial buildings and tenant spaces
- Additions, remodeling and interior alterations (fee set by construction cost)
- Garages and storage buildings; those of 1,000 square feet or less still need the zoning permit
- Above-ground and in-ground pools holding more than 24 inches of water, with the barrier shown on the plot plan
- Tennis courts and similar private recreation facilities
- Demolition, grading and signs
- Driveways and other work in a township road right-of-way (encroachment permit)
- New agricultural buildings (fee and zoning permit)
No permit, or no building-code review
- Maintenance such as new shingles, windows, siding, soffit and fascia, unless interior renovation goes with it and the building cannot reasonably be lived in during the work
- Hot tubs and spas fitted with a cover that meets ASTM F 1346 (no building permit or fence)
- Accessory buildings under 1,000 square feet with no mechanical systems or electricity are exempt from building-code requirements, though they still go through zoning
The UDO defines a storage shed as a building of no more than 12 by 16 feet used for household items, without a door big enough for a vehicle, boat or camper.
What Cecil Township decides and what the state holds
Cecil opted in to enforce the Uniform Construction Code itself from June 1, 2004, with no older local building-code amendments kept, and it uses Municipal Consulting Service as its building inspector. The township page says the Supervisors adopted the 2021 International Building and Residential Codes and the 2012 International Property Maintenance Code. Land use stays local: the UDO, its boards, stormwater and floodplain rules, occupancy permits, road encroachments and the fee resolution.
Cecil Township building department: who handles permitting
The Building & Zoning Department is the township’s permit counter and its first stop for subdivisions, land development and construction. A permit application must be signed off by the Zoning Officer and the Building Inspector, and for non-residential work also by the fire department the township designates. A permit counts as issued only on the day the applicant picks it up and pays. Contractors may apply for an owner only with written proof that they are the owner’s authorized agent.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Building & Zoning, Cecil Township Municipal Building, 3599 Millers Run Road, Cecil, PA 15321 |
| Phone | 724-745-2227 (Zoning Officer ext. 110, Code Enforcement ext. 102); fax 724-745-2905 |
| Building inspector | Municipal Consulting Service, LLC, 724-263-0377 |
| Forms | Applications, Permits, Licenses & Forms page (2026 Construction Permit Application, demolition, grading, encroachment, commercial occupancy) |
| Sewer taps | Cecil Township Municipal Authority, 724-746-4848 |
| On-lot septic | Washington County Sewage Council, 724-223-0504 |
Cecil Township permit types
One form, the 2026 Construction Permit Application, covers new construction, additions, tenant spaces and other work. Its checklist marks each item for houses, commercial buildings or accessory structures.
Residential permits
For a house or addition the plot plan must show property lines, setbacks, easements, wetlands and flood plains, the structure, rain conductors and stormwater outlets, ground elevations, the driveway and its grade, and any retaining walls with their height. Every new single-family house needs a sealed survey; a small addition or accessory building may go ahead with a signed survey waiver from the building department. The two sets of drawings cover footings, framing, lumber grade, stairs, egress windows, smoke detectors, a plumbing schematic and energy-code proof (REScheck). Footings in Cecil go 36 inches deep to the bottom. Pools and accessory buildings under 1,000 square feet need no construction drawings, but a pool’s plot plan must show the fencing.
Building or remodeling a home here? Alliance handles residential permit filing, so the crew isn't waiting on the counter.
Commercial permits
Commercial drawings must be sealed by a Pennsylvania-licensed architect and add sprinkler, fire alarm and fire-resistance details where they apply, COMcheck energy proof and a complete set of accessibility (ADA) details. The township’s fire department signs off on non-residential applications, and the fee resolution sets separate fire inspection permit fees by gross floor area. A new business in an existing space needs a commercial occupancy certificate.
For tenant improvements and new commercial builds, Alliance handles commercial permit expediting through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Zoning. Any variance, special exception, conditional use, site plan or nonconforming-use expansion must be approved before a building permit can issue. The Zoning Hearing Board meets on the third Monday at 7 p.m.; the Planning Commission on the third Thursday at 7 p.m.
- Sewage. New homes and commercial buildings need an approved sewage permit before the application is accepted: a tap from the Cecil Township Municipal Authority for public sewer, or an on-lot permit through the Washington County Sewage Council.
- Stormwater. The township’s Stormwater Management Ordinance (Ordinance 7-2016) requires developers to install practices that cut runoff; a stormwater management plan review is $350.
- Floodplain. Cecil participates in the National Flood Insurance Program. The UDO’s floodplain article requires new or substantially improved homes in a floodplain district to have the lowest floor at least 1½ feet above the 100-year flood elevation, and the plot plan must give the structure’s elevation where it sits in a floodway.
- Driveways. A driveway onto a township road follows Township Driveway Standard C-11 and needs a township encroachment permit; one onto a state road needs a PennDOT Highway Occupancy Permit, which the application lists as a required attachment.
Cecil Township permit costs and fees
Fees come from the township’s fee resolution enacted by the Board of Supervisors on January 6, 2025 and posted as the “Fee Schedule eff 1-7-2025”; its posted copy leaves the number blank.
| Item | Fee |
|---|---|
| New house, up to 5,000 sq ft (crawl and attic space excluded) | $0.30 per sq ft |
| New house, each sq ft over 5,000 | $0.20 per sq ft |
| Garage or storage building over 1,000 sq ft | $0.25 per sq ft |
| Garage or storage building of 1,000 sq ft or less | $0.20 per sq ft, minimum $35 (zoning permit) |
| Residential remodeling, cost up to $4,000 / $4,001–$7,000 / $7,001–$10,000 | $50 / $60 / $70 |
| Residential remodeling, $10,001–$15,000 / $15,001–$20,000 / $20,001–$30,000 | $80 / $90 / $125 |
| Residential remodeling, $30,001–$40,000 / $40,001–$50,000 | $175 / $250 |
| Residential remodeling, $50,001 and up | $250 plus $5 per $1,000 over |
| New commercial building, complete build-out or shell and common areas | $0.55 per sq ft |
| Tenant build-out and remodeling | $0.40 per sq ft |
| Pool with fence or deck, above-ground / in-ground | $100 / $200 |
| Occupancy permit, residential / commercial | $50 / $100 |
| Demolition, residential / non-residential | $50 / $100 |
| Zoning Hearing Board, residential variance or appeal / commercial or special exception | $375 / $525, plus $1,000 escrow |
| Conditional use or rezoning request | $525 |
| Board of Appeals (building and property maintenance) | $400 |
| Driveway encroachment, single-family (minimum use) | $25 |
| Pennsylvania UCC state fee | $4.50 per permit |
Rather talk it over?
Call 1-855-478-4290 →Two examples follow from the table: a kitchen remodel costing $25,000 falls in the $20,001–$30,000 band, so the building fee is $125, and a new 2,400-square-foot house has a building fee of $720 (2,400 × $0.30). The permit form then adds the $4.50 state fee and separate lines for zoning, occupancy and electrical.
Property sales have their own township charges: a lien letter costs $35 per parcel, and the Change of Owner/Occupant Registration filed with it costs $35 for a new owner, $60 for a commercial property and $15 for a residential tenant.
Trade permits and who may pull them
- Electrical: handled on the same construction permit, which carries its own electrical fee line. For pools the UDO requires a licensed electrical inspector to inspect the wiring and pumps and send the report to the township building department. Ask Municipal Consulting Service which inspection agency to use for other electrical work.
- Plumbing: house and commercial drawings must include a plumbing schematic and calculations showing the work meets the UCC; it is reviewed and inspected with the building permit.
- Mechanical: mechanical details are part of the house and commercial drawing checklist.
- Fire protection: sprinkler and fire alarm plans go with commercial applications, and the township’s Fire Protection System Inspection and Safety Policy sets the fire inspection permit; visits after the second cost $75 an hour.
Cecil’s pages set no township license for electricians, plumbers or general contractors. Anyone with employees must show a workers’ compensation certificate or a waiver with the application, and home improvement contractors register with the state Attorney General under HICPA.
Rather not deal with the building department?
Get a free quote →How to apply for a Cecil Township building permit
Call the Zoning Officer (ext. 110) for the district and its setbacks, and settle any variance, special exception or conditional use first.
Obtain the Municipal Authority tap letter or the Washington County Sewage Council on-lot permit; new buildings are not accepted without it.
Show lines, setbacks, easements, flood areas, drainage outlets, elevations, the driveway grade and retaining walls; add a sealed survey for a new house or commercial building.
Include footing, framing, egress, mechanical, plumbing and energy details (architect-sealed for commercial work).
Add the workers’ compensation certificate or waiver, any PennDOT Highway Occupancy Permit and the water-supply details.
Submit the 2026 Construction Permit Application at 3599 Millers Run Road; the permit is issued when you pick it up and pay.
Call for inspections, then obtain the occupancy permit before anyone moves in.
Review, corrections and what causes delay
The application form promises a decision within 15 days for residential and 30 days for commercial work once every required document is in, in line with the state’s 15- and 30-business-day limits; the older UDO text says 20 and 45 days. Incomplete packages are not accepted. The application form, quoting the zoning ordinance, says a permit is void if work has not started or been diligently carried on within three months of issue, and once work starts it stays valid for one year while construction is diligently pursued.
Inspections in Cecil Township
Municipal Consulting Service carries out the UCC inspections and sets the stages for each permit; call 724-263-0377 to book them. Work may not be occupied until the township’s occupancy permit is issued, and the completion notice goes to the Zoning Officer, whose permit certifies that the work, including any required landscaping, driveway and sidewalks, matches the approved permit. Occupancy permits are granted or denied within 10 days of application. A temporary occupancy permit of up to one year is possible when weather delays outdoor work, backed by a bond for all unfinished improvements.
Occupancy permits at a sale or new tenancy
Cecil’s occupancy permits expire when the use, owner or tenant changes. A seller’s closing therefore involves three township steps: a written lien-letter request ($35 per parcel, with the parcel ID, address and buyer’s and seller’s names, mailed with a check to the township), the Change of Owner/Occupant Registration filed with it, and the renewed occupancy permit, which the Zoning Officer can reissue in the new owner’s name after an inspection when nothing about the use changes. Landlords must also send the township a tenant list before March 31 and again before September 30 each year.
Pennsylvania building code in Cecil Township
Cecil enforces the Uniform Construction Code locally under its June 1, 2004 opt-in, through Municipal Consulting Service. FEMA’s Community Status Book lists Cecil Township (community 422143) as participating in the National Flood Insurance Program, with flood maps effective September 30, 2015.
Want this handled start to finish?
Get a free quote →Pennsylvania has one Uniform Construction Code for the whole state, based on the 2021 International Codes since January 1, 2026. Most municipalities enforce it themselves or through a certified third-party agency; where a municipality has opted out, the Department of Labor and Industry handles commercial work and home owners hire a certified agency. Counties do not issue building permits. Pennsylvania rules
Cecil Township permit search and official resources
There is no online permit lookup. For permit, zoning and occupancy records on a property, ask Building & Zoning or file a request on the township’s Right-to-Know form; the Township Manager is the Right-to-Know Officer.
- Cecil Township Building & Zoning
- Applications, permits, licenses and forms
- 2026 Construction Permit Application
- Fee schedule effective January 7, 2025
- Lien letters and change of owner registration
- Unified Development Ordinance (posted text)
- New ordinances pending codification
- Agendas and minutes
- Right-to-Know application and procedures
- Pennsylvania L&I municipal UCC elections list
- FEMA Community Status Book, Pennsylvania
Inspections are where schedules slip.
Get a free quote →Cecil Township building permit FAQs
Who inspects construction in Cecil Township?
Municipal Consulting Service, LLC, the township’s building inspector, at 724-263-0377. Applications are filed with the township’s Building & Zoning Department.
How much is a building permit for a new house in Cecil Township?
$0.30 per square foot up to 5,000 square feet and $0.20 per square foot above that, plus the $4.50 state fee and the zoning, occupancy and electrical lines on the form.
Do I need a permit for a shed in Cecil Township?
Yes, a zoning permit at $0.20 per square foot with a $35 minimum. A shed under 1,000 square feet with no electricity or mechanical systems is exempt from building-code review and needs no construction drawings.
Do I need a permit to replace my roof or windows?
Not for maintenance such as shingles, windows, siding, soffit and fascia, unless interior renovation is part of the job and the house cannot reasonably be occupied during the work.
Do I need anything from the township when I sell my house?
Yes. Order a $35 lien letter, file the Change of Owner/Occupant Registration ($35 for a new owner) and have the occupancy permit renewed in the buyer’s name.
Who approves septic systems in Cecil Township?
The Washington County Sewage Council (724-223-0504) handles on-lot systems; public sewer taps come from the Cecil Township Municipal Authority (724-746-4848). Either approval is needed before a new building application is accepted.
Does a hot tub need a permit in Cecil Township?
Not if it has a cover that meets ASTM F 1346. A pool holding more than 24 inches of water needs a permit: $100 above ground or $200 in ground, fence and deck included.
Simplify Cecil Township permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Pennsylvania. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Cecil Township sooner?
Let Alliance prepare, file, and track your Cecil Township permits while your crew stays on the job.
More Pennsylvania permitting guides
North Strabane Township
Read guide →Peters Township
Read guide →Washington
Read guide →Chambersburg Building Permit Guide