Noble County, Oklahoma Building Permit Guide

Noble County issues no building permits; its commissioners approve road crossing permits, and Perry and Morrison permit buildings inside their limits.

Authority: Noble County Board of County CommissionersBuilding permits: none issued by the countyCrossing applications: County Clerk, 580-336-2141
2025 population
10,899
County building permits
None
Bored road crossing
$750 per crossing
City permits
Perry, 580-336-4241

Noble County does not issue building permits; the state building code commission lists it among the counties that issue none. What the county does run is a road crossing permit, approved by the county commissioners ($750 for a bored crossing, up to $2,500 for a permanent trenched one), and a floodplain review for development on unincorporated land. In Perry, building permits are filed through the City’s online iWorQ portal.

Who handles permits in Noble County?

The Board of County Commissioners decides road crossing permits at its regular meetings, after the commissioner for the district has inspected the site. The County Clerk’s office on the courthouse’s second floor hands out the forms, takes the applications and records subdivision plats. The state floodplain list gives the county floodplain administrator’s number as 580-336-2141, the County Clerk’s line. Septic systems are permitted by the Oklahoma Department of Environmental Quality.

Short on time to read all of this?

Get a free quote →
Noble County contacts
OfficeContact
County Clerk (forms, applications, plats)300 Courthouse Drive #11, Perry, OK 73077; 580-336-2141 or 580-336-2596; Monday to Friday, 8:00 a.m. to 4:30 p.m.
County floodplain administrator(580) 336-2141 (state floodplain list)
District 1 commissioner9051 County Road 110, Red Rock; shop 580-723-4564
District 2 commissioner300 Courthouse Dr. #1, Perry; 580-336-2771
District 3 commissioner419 South Boundary, Perry; shop 580-336-4414
City of Perry City Hall580-336-4241

Towns in Noble County

Who issues building permits in each town
TownBuilding permits
PerryYes: City building permits, certificates of occupancy and floodplain permits are applied for in the City’s iWorQ portal; inspections through City Hall, 580-336-4241
MorrisonYes: on the State Fire Marshal’s July 14, 2026 list of places that do their own plan review, permitting and inspections; town office 580-724-3531
Red RockThe published sources do not say; ask the town (580-723-4474)
Billings, MarlandListed by the state building code commission as issuing no permits

Billings, Morrison, Perry and Red Rock each appear on the Oklahoma Water Resources Board’s list of local floodplain administrators, so a flood-zone project inside one of those towns is reviewed by the town.

Not sure this scope needs a permit?

Get a free quote →

What Noble County permits

Road crossings and pipelines. Any pipeline, utility or other line placed along or across a county road needs a numbered county permit for each crossing, approved by the commissioners before work starts. Blacktop roads must be bored; cutting or trenching is allowed on dirt roads only with the board’s approval. Temporary production lines carrying salt water are not approved.

Development on unincorporated land. The county’s Notice of Intent form covers proposed buildings, roads, utilities, filling, excavation and paving outside the towns. Staff record the flood map panel and zone and tell the applicant whether a floodplain permit application is needed.

Road crossing permit fees

The county’s crossing application (revised June 2, 2014, and still the form the Clerk posts) sets these fees, paid to the County Treasurer’s office:

Noble County road crossing fees
CrossingFee
Bored road crossing$750
Overhead line$500
Cut or trenched crossing, permanent$2,500
Cut or trenched crossing, temporary$1,500
Temporary lines through culverts or bridges$500 each
Water-only pipeline laid on the ground beside the road (one-mile minimum, up to 30 days)$250 per mile

Rather talk it over?

Call 1-855-478-4290 →

An application is not put on the commissioners’ agenda until the fees are paid. A permit is good for 30 days from approval, and work started without approval can bring fines of up to $10,000. There is no county building permit fee; in Perry and Morrison, the city or town sets its own.

How to get a Noble County road crossing permit

1. Pick up the forms

Get the Notice of Intent and the crossing application from the County Clerk on the courthouse’s second floor.

2. Map the route

Complete every field and attach a printed map marking where the line will go.

3. Have the site inspected

Ask the commissioner for that district to inspect the site before the permit is put on the agenda.

4. File and pay

Hand the original application and fees to the County Clerk.

5. Floodplain board, if needed

A bore or trench in a flood zone first goes to the Noble County Floodplain Management Board, which meets on the third Thursday of each month; the permit then goes to the commissioners the following Monday.

Rather not deal with the Noble County building department?

Get a free quote →

Inspections

There is no county building inspection. For road crossings, the applicant calls the county highway or commissioners’ office 24 hours before construction so an inspector can attend if the board requires it. In Perry, inspections are requested through City Hall; they are scheduled in morning or afternoon blocks, and calls after 8 a.m. are booked for the next business day.

Oklahoma building code

Oklahoma sets statewide minimum codes (the 2024 editions since September 14, 2026) that cities enforce and may strengthen; most counties issue no building permits for unincorporated land, though a few do. Oklahoma rules

Official Noble County permit resources

These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.

Want this handled start to finish?

Get a free quote →

Noble County permit FAQs

Does Noble County issue building permits?

No. The state building code commission lists Noble County as not issuing permits. The county’s permits cover road crossings and floodplain review.

Inspections are where schedules slip.

Get a free quote →

How much is a road crossing permit in Noble County?

$750 for a bored crossing, $500 for an overhead line and $2,500 for a permanent cut or trenched crossing, paid to the County Treasurer.

How long is a crossing permit good for?

30 days from the commissioners’ approval; more time needs another permit.

Which towns in Noble County issue building permits?

Perry and Morrison. Billings and Marland are listed as issuing none; for Red Rock, ask the town.

Who permits septic systems in rural Noble County?

The Oklahoma Department of Environmental Quality.

Simplify Noble County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Oklahoma. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Noble County sooner?

Let Alliance prepare, file, and track your Noble County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Noble County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.