Williams County, Ohio Building Permit Guide

To get a building permit in Williams County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Williams County’s pages show no building department, and the county has no zoning: the Auditor in Bryan issues building notices for new construction, the Engineer handles floodplain, driveway and subdivision steps, and three townships and the municipalities do their own zoning.

Building notices: Williams County AuditorFloodplain and roads: County EngineerPhone: 419-636-5639
County building notice
$25Over $2,000; free below that
County zoning
NoneCenter, Pulaski, Springfield Twps zone
Floodplain permit
FreeCounty Engineer, 419-636-2454
Septic and wells
County Health Dept.Montpelier, 419-485-3141

Williams County’s pages show no county building department. What the county does require for a new house, addition, deck or large shed outside the city and villages is a building notice from the County Auditor (One Courthouse Square, second floor, Bryan; 419-636-5639), which Ohio law ties to any structural improvement costing more than $2,000. The County Engineer on County Road G issues free floodplain, driveway and right-of-way permits, the Health Department in Montpelier permits septic systems and wells, and for commercial building permits the county’s own instructions point to the state.

What requires a permit in Williams County?

The county’s own trigger is the building notice. Under Ohio Revised Code 5713.17 anyone making structural improvements that cost more than $2,000 must give written notice to the County Auditor, and the county still wants a notice, at no charge, for smaller work. A structure the Auditor finds without one is appraised and taxed back to the date of construction, plus a penalty equal to 50% of the taxes that would have been charged.

Building notice needed

  • New houses and any addition to an existing structure
  • Decks, patios and porches
  • Replacing at least 25% of a building’s windows or siding
  • Finishing an attic or basement into living space
  • Utility sheds of 150 square feet or more, on skids or a foundation
  • Non-residential, accessory and business buildings

Other county approvals

  • A floodplain development permit for any property with federally regulated floodplain on it
  • Regional Planning Commission review of land splits that create parcels of 20 acres or less
  • Health Department permits for septic systems and most well work
  • Engineer’s permits for driveways, road-ditch closing and work in a county road right-of-way
  • A five-digit house number from the 911 Communications Agency

What the county decides and what the state holds

Plan approval and inspections under the Ohio codes are the work of departments certified by the Ohio Board of Building Standards, and no county page names one serving Williams County. Where no department certified for residential buildings has jurisdiction, state law does not require the owner to submit plans for a house (ORC 3791.04(A)(1)); check the address on the Board of Building Standards look-up map. The Board of County Commissioners sets the $25 notice fee by resolution and adopted the special hauling permit policy; the Regional Planning Commission writes the subdivision regulations, revised as of February 13, 2026; and the Health Department applies the state sewage and private water rules through its own permits.

Williams County building department: who handles permitting

There is no single permit office. The Auditor issues building notices for unincorporated land and the villages of Blakeslee and Holiday City, together with the new house number. Everyone else in a city or village gets the notice from that municipality’s office, and the cost may vary from village to village. The County Engineer, Todd J. Roth, runs floodplain permits, road permits and the county sanitary sewer system, and the Regional Planning Commission meets at his office.

Short on time to read all of this?

Get a free quote →
Williams County offices for building projects
OfficeRole and contact
County AuditorBuilding notices and house-number paperwork; One Courthouse Square, 2nd floor, Bryan, OH 43506; 419-636-5639 (ext. 1121 for building notices); 8:30 a.m. to 4:30 p.m. weekdays
County EngineerFloodplain development permits, driveway, ditch and right-of-way permits, county sewer permits in sewer districts; 12953 County Road G, Bryan; 419-636-2454; 8:00 a.m. to 4:30 p.m. weekdays
Regional Planning CommissionSubdivision review for unincorporated areas; meets as needed at the Engineer’s Office; staffed through the Maumee Valley Planning Organization, 419-784-3882
Williams County Health DepartmentSeptic system and well permits; 310 Lincoln Avenue, Montpelier, OH 43543; 419-485-3141; 8:30 to 4:30 weekdays
911 Communications AgencyFive-digit house numbers; 1425 E High Street, Bryan; 419-636-8497
Township zoningCenter, Pulaski and Springfield townships share one zoning inspector, 419-630-4828

The city and villages

Williams County has one city and eight villages. The county’s zoning page links the municipal zoning offices, and its building notice page sends residents of each municipality, except Blakeslee and Holiday City, to their own village or city office.

Municipalities in Williams County
PlaceWhat the official pages show
Bryan (city, 8,579 people in the Census estimate)The City Engineering Department handles zoning and permits for all construction in the city, at the Don North Municipal Building, 419-633-6010
MontpelierOwn Planning and Zoning Commission, meeting the second Monday of each month at 5 p.m. at 221 Empire Street, and a zoning inspector available 8 a.m. to 4:30 p.m. weekdays
Edgerton, Edon, Pioneer, Stryker, West UnityZoned municipalities on the county’s list; building notices from the village office
Blakeslee, Holiday CityCounty building notice from the Auditor

Permit types in Williams County

The county posts a building notice application on the Auditor’s real estate site and publishes three sets of step-by-step instructions: one for houses, one for non-residential and accessory buildings, and one for business or industrial structures.

Not sure this scope needs a permit?

Get a free quote →

Residential permits

  • Floodplain check: contact the Planning Commission at the Engineer’s Office to confirm whether the lot is in a floodplain and take out a permit if needed.
  • Zoning: in Center, Pulaski or Springfield Township, the township zoning permit comes before the county notice; at Lake Seneca the property owners issue their own permit before the county’s.
  • Septic and well: permits from the Health Department in Montpelier.
  • Sewer and driveway: a county sewer permit where the lot is in a county sewer district, and a driveway permit, both from the Engineer.
  • Address and notice: a five-digit number from the 911 agency, then the building notice from the Auditor, issued with the number. The number goes on the house and on both sides of the mailbox.

Commercial permits

For business and industrial buildings the county lists three calls: the Northwest District Office of Ohio EPA (800-686-6930) for non-residential sewage systems and for water systems serving 25 or more people or more than 15 connections; the state (the county page still uses the old name “Ohio Industrial Relations”, 800-523-3581) for commercial building permits; and the Auditor for the county building notice. That matches the state rule that nonresidential plans go to the state where no certified department has jurisdiction. Inside Bryan, the city also asks for two sets of state-approved plans with its own commercial permit.

What comes before the building permit

  • Land division. A split that creates parcels of 20 acres or less, platted or not, is reviewed under the county subdivision regulations (Article IV for unplatted splits); book a pre-submission meeting with the County Engineer or the planning director before filing a plat consideration application.
  • Zoning. The county has none. Only Center, Pulaski and Springfield townships and the municipalities zone.
  • Floodplain. Any property with federally regulated floodplain needs the county’s free floodplain development permit; flood zones can be viewed on the Auditor’s map.
  • Road access. The Engineer’s driveway permit for a county road. The owner pays for and maintains the driveway and its culvert, and closing a road ditch with tile takes a separate free permit.
  • Heavy deliveries. Under the special hauling permit policy the commissioners adopted on January 18, 2007, oversize or overweight loads need an Engineer’s permit before using any of the county’s 396 miles of highway.

Williams County permit costs and fees

The county’s own charges are few. The building notice fee is set by resolution of the Board of County Commissioners, and the Engineer charges nothing for its road and floodplain permits. Where a certified department or the state reviews plans, a Board of Building Standards assessment of 1% on residential and 3% on nonresidential fees is added to that department’s charges.

Rather talk it over?

Call 1-855-478-4290 →
County and Bryan fees
ItemFee
County building notice, work over $2,000$25
County building notice, work under $2,000No charge
Notice not obtained before construction startsUp to $100 penalty, plus the notice fee
Floodplain development permitFree
Driveway, road-ditch closing or county right-of-way permitFree
Septic operation permit (existing systems)$60, valid 5 years
Bryan residential building permit$0.08 per sq ft of living area, $20 minimum
Bryan garage or accessory building$0.04 per sq ft, $20 minimum
Bryan commercial and industrial building$2.00 per $1,000 of construction cost
Bryan fence, deck, pool, driveway, siding or windows (over 25%)$20 each
Bryan variance, rezoning, conditional use or site plan$150

Unpaid notice fees and penalties may be added to the property’s real estate taxes. Worked example from Bryan’s list: a new house with 1,800 square feet of living area costs 1,800 × $0.08 = $144, and a 24-by-24-foot detached garage (576 square feet) costs 576 × $0.04 = $23.04. A commercial building costing $400,000 would be 400 × $2.00 = $800, and Bryan’s City Council must approve the permit.

Trade permits and who may pull them

No Williams County page sets up county electrical, plumbing or HVAC permits, or a county contractor registration. Ohio licenses commercial electrical, HVAC, hydronics, plumbing and refrigeration contractors through the Construction Industry Licensing Board, and has no state license for general or residential contractors.

Rather not deal with the Williams County building department?

Get a free quote →
  • Septic work: the Health Department keeps a list of registered contractors (current as of September 2026); owners may register as a homeowner service provider to evaluate their own system under the operation and maintenance program, but septic tanks must be pumped by a registered septage hauler at least every five years.
  • Wells: new wells and work on existing wells must be done by a contractor registered with the Ohio Department of Health, and most of that work needs a Health Department permit; agricultural wells are outside the department’s jurisdiction.
  • Failing septic systems: owner-occupants who qualify by household income can get help replacing a failing home system through the Water Pollution Control Loan Fund money the Health Department receives from Ohio EPA; rentals and commercial properties are not eligible.
  • County sewer customers: the county sanitary department runs 5 treatment plants and 3 lagoon systems for nearly 1,500 customers and asks them to call it before calling a plumber about a problem.
  • Bryan: a contractor working in the city must be on file with the city income tax department before a permit is issued.

How to get a building notice and permits in Williams County

1. Find the jurisdiction

Check the parcel on the Auditor’s map: inside Bryan or a village, start with that office; in a township or Blakeslee or Holiday City, follow the county steps.

2. Check the floodplain

Call the Engineer’s Office (419-636-2454) and take out the free floodplain permit if the lot has mapped floodplain.

3. Get zoning where it exists

Township zoning in Center, Pulaski or Springfield; Lake Seneca approval at the lake.

4. Sort out water and sewage

Septic and well permits from the Health Department, or a county sewer permit from the Engineer in a sewer district.

5. Driveway and address

Driveway permit from the Engineer, then a house number from the 911 agency.

6. File the building notice

At the Auditor’s office with the $25 fee if the work tops $2,000; business buildings also go to the state for commercial plan approval.

Review, corrections and what causes delay

The building notice is an Auditor’s record, not a plan review, so the usual hold-ups come earlier: a lot split that still needs Regional Planning Commission review, a septic site that does not pass, or floodplain on the parcel. In Bryan the city asks applicants to allow two weeks for the zoning administrator to process paperwork, and commercial permits go to a meeting of eight department heads on the following Wednesday, which the applicant is encouraged to attend.

Inspections and follow-up

After a notice is issued, a field listing technician from the Auditor’s office visits each property with reported new construction or demolition, records the improvement and its cost, and inspects the interior so the parcel can be revalued. If nobody is home, a card is left asking for the details, and the owner can call 419-636-5639 for an appointment. No county page describes county building code inspections; septic installations and wells are inspected under the Health Department’s permits, and commercial building inspections follow whichever certified department or state office approved the plans.

Want this handled start to finish?

Get a free quote →

Ohio building code in Williams County

FEMA’s Community Status Book lists unincorporated Williams County (community 390785) as participating in the National Flood Insurance Program, with flood maps dated August 19, 1987 on which no flood elevations were determined; the county’s floodplain permit applies there. That entry covers unincorporated land only; the city and villages are separate communities in FEMA’s list.

Ohio has statewide building codes: the Ohio Building Code for commercial and other nonresidential buildings and the Residential Code of Ohio for detached one-, two- and three-family dwellings. Only departments certified by the Ohio Board of Building Standards may approve plans and inspect, and residential rules are uniform statewide. How Ohio’s statewide code works

Williams County permit search and official resources

Building notice and new-construction records sit with the County Auditor, and the Auditor’s real estate site shows parcels and flood zones. Floodplain, road and subdivision files are at the Engineer’s Office, which posts its public records request policy; septic and well records are at the Health Department.

Inspections are where schedules slip.

Get a free quote →

Williams County building permit FAQs

Does Williams County issue building permits?

The county pages show no building department. Outside the municipalities the Auditor issues a building notice for construction, and commercial building permits go to the state.

How much is a county building notice?

$25 for work costing more than $2,000. A notice is still needed for cheaper work but costs nothing, and a $100 penalty may be added if construction starts first.

Do I need zoning approval in Williams County?

Only in Center, Pulaski and Springfield townships and in the zoned municipalities; the county has no zoning.

Do I need a notice for a shed?

Yes for a utility shed of 150 square feet or more, whether on skids or a foundation.

Where do I get a septic or well permit?

From the Williams County Health Department, 310 Lincoln Avenue, Montpelier (419-485-3141).

Is a floodplain permit required?

Yes, if any federally regulated floodplain is on the property. It is free from the County Engineer’s Office.

Who handles permits in Bryan?

The City Engineering Department, which handles zoning and permits for all construction in the city (419-633-6010).

Simplify Williams County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Ohio. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Williams County sooner?

Let Alliance prepare, file, and track your Williams County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Williams County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.