In Preble County, building and electrical permits are taken by the county’s Office of Land Use Management (Building Regulations, Planning and Zoning, Tax Map and GIS) at 101 East Main Street, Eaton (937-456-8171), and building questions and inspections go to its inspection firm, National Inspection Corporation, at 888-433-4642. A new house costs $125 plus 9 cents a square foot under Commission Resolution 400-17-180. The City of Eaton runs its own building department, and plumbing everywhere in the county is permitted by Preble County Public Health.
What requires a building permit in Preble County?
The county’s combined building and electrical application and its fee resolution show the work Land Use Management permits. Each item has its own fee line, so if it appears in the schedule, plan on a permit.
Residential work in the fee schedule
- Houses (one-, two- and three-family), reconstruction and additions
- Decks, breezeways, porches, garages and carports
- Detached accessory structures over 200 square feet
- Roof replacement with structural work
- HVAC replacement or new systems, gas lines, geothermal
- Electrical services, upgrades, temporary poles, pools, generators
- Retaining walls over 4 feet, fences over 6 feet, solar, wind turbines, demolition
Commercial work in the fee schedule
- New buildings, shells, footings and tenant build-outs
- Mechanical, electrical, fire suppression, hood and fire alarm systems
- Industrialized units and storage racks
- Temporary structures and tents
- Signs, solar arrays and wind turbines
- Minor alterations, per type of permit
A zoning permit or certificate is often needed too: the county lists zoning fees for new dwellings, additions, accessory buildings, commercial buildings, wind turbines, solar farms and signs, plus an agriculture use certificate zoning permit. Work started without a permit is charged double, and the temporary use, conditional use, variance, appeal and rezoning application fees double if work begins before approval.
What the county decides and what the state holds
Ohio adopts the building codes; the county commissioners set the building and zoning fees (Resolution 400-17-180, adopted July 19, 2017 and in force since September 1, 2017), run county zoning through the Rural Zoning Commission, the Board of Zoning Appeals and the Planning Commission, keep the flood hazard area rules, and recommend contractor registration. Preble County Public Health, not the building office, handles plumbing, private water systems and sewage treatment systems.
Preble County building department: who handles permitting
Land Use Management, led by Director Brad Kramer, receives building and electrical applications for residential and commercial work and also handles zoning, floodplain matters, the tax map and GIS. Plan review questions and inspections go to National Inspection Corporation (NIC), the inspection firm named on the county’s building pages. The application asks for the township and section or the village, because the office covers more than one kind of place.
Short on time to read all of this?
Get a free quote →| Place | Building permits |
|---|---|
| Unincorporated townships | Preble County Land Use Management, with NIC inspections |
| City of Eaton | Eaton Building Inspection & Zoning, 328 North Maple Street (937-456-7155); city portal; inspections booked with NIC since November 1, 2025 |
| Villages: Camden, College Corner (part), Eldorado, Gratis, Lewisburg, New Paris, Verona (part), West Alexandria, West Elkton, West Manchester | The county form has a village field, but the published county pages do not list which villages it serves; ask Land Use Management or the village office |
| Plumbing, everywhere in the county | Preble County Public Health, 615 Hillcrest Drive, Eaton (937-472-0087) |
| Item | Detail |
|---|---|
| Land Use Management | 101 East Main Street, Eaton, OH 45320; 937-456-8171; Monday to Friday, 8 a.m. to 4 p.m. |
| Applications by e-mail | landusemgmt@prebco.org |
| Building questions and inspections | National Inspection Corporation, 888-433-4642 (the residential checklist lists 937-433-4642) |
| Tax map office (parcels) | 937-456-8129 |
| Driveways and drainage | Preble County Engineer’s Office |
Preble County permit types
One form, the Building/Electrical Permit Application, covers residential and commercial work. You tick the reviews you need, from new building, addition, alteration, deck, shed or garage to HVAC, electrical, gas line, re-roof, fire alarm and suppression systems, hood exhaust, certificate of occupancy, change of use, signs, pools, temporary poles and generators. Services of 400 amps and over need a line drawing.
Residential permits
- New homes follow the residential plan submittal checklist: a site plan with property lines and distances, all four elevations, footer and foundation and crawl space plans, a labelled floor plan showing egress windows, headers, beams, joists, engineered lumber and HVAC and plumbing locations, a wall cross-section from footing to roof, and the energy-code path chosen.
- Decks and post-frame buildings have their own submittal checklists, and the county posts a residential site plan example.
- Manufactured homes, pools, spas and hot tubs, solar PV and roofing each have a requirements sheet.
- Resubmittals after review comments use the county’s resubmittal application.
Building or remodeling a home here? Alliance handles home building permits, so the crew isn't waiting on the counter.
Not sure this scope needs a permit?
Get a free quote →Commercial permits
The county’s commercial workflow runs in four phases: planning and application (with an optional pre-application meeting), plan review routed to zoning, fire, health and engineering, permit issuance, and inspections. If the plans are not approved, an adjudication order lists the corrections, and revised plans go back in. Once approved, the final fees are paid and the permit is issued with an inspection card and one set of approved plans to keep on site. Commercial fees are a process fee plus a square-foot charge for each discipline, with the 3% state fee on the subtotal.
For tenant improvements and new commercial builds, Alliance handles commercial permit filing through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning: the application has a zoning approval line; county zoning certificates are $100 for a new dwelling and $50 for additions or accessory buildings. The Rural Zoning Commission, Board of Zoning Appeals and Planning Commission meet on the county’s published 2026 dates (Planning Commission November 19, Zoning Appeals November 24 and Rural Zoning Commission December 1, 2026).
- Floodplain: the application asks whether the property is in a floodplain, and Planning and Zoning issues the Flood Hazard Area Development Permit.
- Health: the application records health department approval; septic and well permits come from Preble County Public Health. Wells, cisterns, hauled-water tanks and ponds used for drinking water need a health district permit before they are installed or altered.
- Driveway and drainage: access and drainage approvals come from the County Engineer’s Office.
- Recorded deed and any variance are also checked before the permit is issued.
Preble County permit costs and fees
The building and zoning fees were set by Commission Resolution 400-17-180, adopted July 19, 2017 and effective September 1, 2017. The base amounts marked on the schedule are non-refundable deposits, and the state Board of Building Standards fee is added: 1% on residential and 3% on commercial permits.
Rather talk it over?
Call 1-855-478-4290 →| Work | Fee |
|---|---|
| House (1, 2 or 3 family) / reconstruction | $125 + $0.09 per sq ft |
| Deck, porch, garage, addition, accessory over 200 sq ft, structural re-roof | $50 + $0.09 per sq ft |
| HVAC: new home / replacement | $60 + $0.09 per sq ft / $60 single unit, $90 furnace and AC |
| Electric: new construction service | $70 + $0.09 per sq ft (service, permit and three inspections) |
| Electric: upgrade, temporary pole, pool, generator | $70 each |
| New gas line / geothermal / prefab home foundation | $75 / $120 / $125 |
| Fence over 6 ft / retaining wall over 4 ft / demolition | $50 / $50 + $2 per lin ft / $75 |
| Residential certificate of occupancy / re-inspection (3rd and later) | $50 / $70 |
| Commercial structural | $250 + $0.12 per sq ft of floor area |
| Commercial partial permits: footer and foundation, exterior shell, tenant build-out | $200 + $0.05 per sq ft each |
| Commercial mechanical, electrical or fire suppression | $250 + $0.06 per sq ft each |
| Commercial fire alarm / industrialized unit | $250 + $4.50 per device / $200 + $0.02 per sq ft |
| Commercial plan review / certificate of occupancy | $100 per hour / $100 |
| Zoning: new dwelling / addition or accessory building | $100 / $50 |
| Variance, conditional use or appeal / rezoning | $150 / $350 |
| Work without a permit | Double the permit fee |
Worked example from the schedule: a 2,000-square-foot house is $125 plus 2,000 × $0.09 ($180), or $305, plus the 1% state fee of $3.05, for $308.05 before the electrical and HVAC permits and the $100 zoning certificate. A second or later plan review costs $60 an hour, and inspections outside normal hours are $125 an hour with a three-hour minimum.
Trade permits and who may pull them
Electrical and HVAC permits are part of the county building and electrical application; plumbing is not. Plumbing permits for any address in Preble County must be obtained from Preble County Public Health before work starts, and the health district registers everyone in the plumbing business in the county.
- County contractor registration: Preble County recommends that every contractor register with Land Use Management, with $250,000 of liability insurance and workers’ compensation; registration is listed separately for general contractors and for other trades.
- State licenses: the county asks for a state contractor license for commercial electrical, refrigeration, hydronics and HVAC permits only, in line with the Ohio Construction Industry Licensing Board’s commercial licenses; Ohio does not license general or residential contractors.
- Plumbing and sewage contractors register with the health district, not the county building office.
- Homeowners: the health district says homeowners may get plumbing permits in limited cases; ask Land Use Management about building and electrical work on your own house.
Rather not deal with the Preble County building department?
Get a free quote →How to apply for a Preble County building permit
Use the township or village and parcel; Eaton addresses go to the city.
Get the zoning certificate and, in a mapped flood area, the flood hazard area development permit.
Septic, well and plumbing through the health district; driveway and drainage through the County Engineer.
Follow the residential or commercial checklist and the site plan example.
E-mail it to landusemgmt@prebco.org or deliver it to 101 East Main Street with the deposit.
Respond to any adjudication order, pay the balance, and collect the permit and inspection card.
Review, corrections and what causes delay
The county’s commercial workflow says a submittal is first checked for completeness and may be returned if documents are missing. The application’s office section records the zoning, health, driveway, deed and variance approvals, so a missing one holds up the permit, and commercial plans that need revisions come back with an adjudication order. Additional plan reviews are billed hourly ($60 residential, $100 commercial), and revisions that add square footage also pay the area charge. Questions on code issues go to NIC at 888-433-4642.
Inspections and certificates in Preble County
Inspections are scheduled with National Inspection Corporation at least one day in advance: give the address, city, permit number and inspection type, then call between 8:00 and 8:30 a.m. on the day to get a two-hour window. The approved drawings must be on site for every inspection, and the plan review notes on them should be read before work starts.
A typical house is inspected at the footing, foundation, backfill (after waterproofing and drain tile), crawl space or slab, rough gas, rough electric (temporary pole, trench, service and building wiring), rough HVAC and rough framing, and at final. Third and later re-inspections cost $70 on residential work and $100 on commercial work, and a special inspection is $150. The certificate of occupancy is $50 for a house and $100 for a commercial building, with temporary certificates (30 days for houses) at the same price.
Want this handled start to finish?
Get a free quote →Ohio building code in Preble County
Preble County enforces the state codes through Land Use Management and its inspection firm, and its residential checklist lists the energy-code paths the county accepts. FEMA’s Community Status Book lists Preble County’s unincorporated area (community 390460) as participating in the National Flood Insurance Program, with a current flood map dated May 8, 2024, and as a Community Rating System class 9 community (a 5% flood insurance discount). Cities and villages take part separately.
Ohio has statewide building codes: the Ohio Building Code for commercial and other nonresidential buildings and the Residential Code of Ohio for detached one-, two- and three-family dwellings. Only departments certified by the Ohio Board of Building Standards may approve plans and inspect, and residential rules are uniform statewide. How Ohio’s statewide code works
Preble County permit search and official resources
For a past permit, plan or inspection record in the county’s area, ask Land Use Management at 937-456-8171 or by e-mail at landusemgmt@prebco.org; parcel information is available from the county tax map and GIS office in the same department. Eaton permits can be looked up by permit number on the city’s online portal.
- Preble County Land Use Management
- Building Regulations forms and documents
- Building and zoning fee schedule, Resolution 400-17-180
- Building/electrical permit application
- Residential plan submittal checklist
- Residential inspection guide
- Commercial permit workflow
- Contractor registration form
- Planning and Zoning forms and meeting dates
- Flood hazard area development permit application
- Preble County Public Health plumbing
- Preble County Public Health environmental health (septic, wells)
- City of Eaton Building Inspection and Zoning
- FEMA Community Status Book, Ohio
Inspections are where schedules slip.
Get a free quote →Preble County building permit FAQs
Who issues building permits in Preble County?
The county’s Office of Land Use Management in Eaton (937-456-8171), with inspections by National Inspection Corporation; the City of Eaton has its own building department.
How much is a permit for a new house?
$125 plus 9 cents per square foot plus the 1% state fee; a 2,000-square-foot house is $308.05 before electrical, HVAC and zoning.
Who issues plumbing permits?
Preble County Public Health, for all areas of the county, before work starts.
Do I need a permit for a shed or fence?
Detached accessory structures over 200 square feet and fences over 6 feet are on the county building fee schedule; accessory buildings also need a $50 zoning certificate.
How do I schedule an inspection?
Call National Inspection Corporation at least a day ahead, then call between 8:00 and 8:30 a.m. that morning for a two-hour window.
Do contractors have to register with the county?
The county recommends registration with $250,000 liability insurance and workers’ compensation; plumbers and septic installers register with the health district.
Who approves driveways?
The Preble County Engineer’s Office handles access (driveway) and drainage approvals.
Simplify Preble County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Ohio. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Preble County sooner?
Let Alliance prepare, file, and track your Preble County permits while your crew stays on the job.
More Ohio permitting guides
Montgomery County
Read guide →Butler County
Read guide →Darke County
Read guide →Putnam County Building Permit Guide
Read guide →Ravenna Building Permit Guide
Read guide →Reading Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Preble County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.