Building permits inside the City of Cleveland are issued by the city’s Department of Building & Housing, through its Division of Construction Permitting. The Ohio Board of Building Standards certifies the city for both commercial and residential work. Cleveland is Ohio’s second-largest city, with 363,608 people in the Census Bureau’s 2025 estimate, and the seat of Cuyahoga County.
This guide covers the department and how to reach it, the local conditions that shape a filing here, what permits cost and who may pull them, and how inspections are booked. Rules that apply everywhere in Ohio are summarized in each section, with a link to the full statewide explanation.
This guide covers work inside the City of Cleveland limits. The surrounding municipalities are separate authorities, most with their own certified building department. Cuyahoga County has no building department of its own.
Cleveland shares its boundary with many separate municipalities. A parcel a few streets outside the city belongs to a different government, and most municipalities in Cuyahoga County have their own certified building department, fee schedule and local requirements. The county itself has no building department. Confirm the boundary against the address first; the Board’s building-department lookup shows which department has authority.
What requires a building permit in Cleveland?
Under the Ohio Building Code and the Residential Code of Ohio, a permit is required for most construction activity inside the city limits.
Permit required
- New residential and commercial construction, additions, alterations and conversions
- Structural and load-bearing work, foundations, decks, porches, ramps and stairs
- Finishing basements and attics, and any change of occupancy or use
- Electrical service changes, panel work, new circuits, solar and EV charging equipment
- Plumbing alterations, repipes, water heaters, backflow and sewer or gas connections
- HVAC installation and change-out, ductwork and venting; reroofing, siding, windows, pools and signs
Typically exempt
- Painting, wallpapering, tiling, carpeting and cabinet installation
- Minor repairs that do not cut away walls, touch structural supports or change the means of egress
- Fences up to 6 feet at houses (7 feet under the Ohio Building Code) and retaining walls up to 4 feet that support no surcharge
- One-story detached sheds and playhouses up to 200 square feet at houses (120 square feet under the Ohio Building Code)
The exempt list is set statewide in Section 102.10 of the Ohio Building Code and the Residential Code of Ohio, and an exemption from a building permit is not an exemption from zoning, setbacks, floodplain rules, utility approval or a fire authority review. Confirm scope with the department before work starts rather than after.
Short on time to read all of this?
Get a free quote →Which code edition applies
Cleveland enforces the statewide Ohio codes through the Department of Building & Housing, with city zoning and development standards alongside them. The city’s contribution is zoning, submittal requirements, fees, inspection scheduling and any additional local regulations. For one-, two- and three-family dwellings the city publishes local design criteria for RCO Table R301.2(1): a 30 psf ground snow load, footings at least 42 inches below finished grade, and wind exposure category D within 600 feet of the Lake Erie shoreline.
Permits in Cleveland are governed by Ohio’s statewide codes: the Ohio Building Code for commercial and other nonresidential buildings, and the Residential Code of Ohio for detached one-, two- and three-family dwellings. The Ohio Building, Mechanical and Plumbing Codes in force since 1 March 2024 are based on the 2021 International Codes; the Residential Code of Ohio is the 2019 edition, based on the 2018 International Residential Code; both use the 2023 National Electrical Code. Only departments certified by the Ohio Board of Building Standards may approve plans, and residential rules are uniform statewide. How Ohio’s statewide code works
Who handles permitting in Cleveland?
The Department of Building & Housing handles plan review, permit issuance and inspections inside the city limits through its Division of Construction Permitting. Since 13 April 2026 it accepts no paper plans or paper applications: applications go through the city’s Permit Portal and plans through its Digital Plan Room. Plan sets under five pages can be scanned, and kiosks are available, in City Hall Room 505. The division is at 601 Lakeside Ave., Room 505, Cleveland, Ohio 44114, (216) 664-2910; the department’s office is Room 510, (216) 664-2282.
| Detail | Information |
|---|---|
| Authority | City of Cleveland Department of Building & Housing, Division of Construction Permitting, certified for commercial and residential work |
| Jurisdiction | City of Cleveland limits only |
| County | Cuyahoga County, which has no certified building department; most of its municipalities have their own |
| Office | 601 Lakeside Ave., Room 505, Cleveland, OH 44114; (216) 664-2910 |
| Site considerations | Wind exposure category D within 600 feet of the Lake Erie shoreline (city design criteria) |
| Confirm the department | Use the BBS building-department lookup before filing |
| Code | Ohio Building Code on the 2021 International Codes (since 1 March 2024); Residential Code of Ohio, 2019 edition on the 2018 IRC; 2023 NEC |
| Contractor credentials | The city publishes a general contractor registration application, electrical, HVAC and plumbing contractor packages, and a notarized homeowner affidavit for owners’ own permits; OCILB licence for commercial electrical, HVAC, hydronics, plumbing and refrigeration work |
The Landmarks Commission reviews building and demolition permits for designated Cleveland landmarks and for the city’s 29 locally designated historic districts, and issues Certificates of Appropriateness. It reviews exterior changes only. Establish designation before exterior work is designed.
Not sure this scope needs a permit?
Get a free quote →In 2025, building permits issued in Cleveland authorized 706 new privately owned housing units, 143 of them single-family homes, according to the U.S. Census Bureau Building Permits Survey.
Zoning is reviewed in the project application
To apply for a building permit in Cleveland you must first complete a project application and receive approval. The city routes that application to Zoning, Planning, Landmarks, Right of Way and the other review bodies the project’s complexity and location call for, so zoning is settled before the building application.
The Ohio Board of Building Standards certifies which departments may enforce the code, and for which buildings; the certified department’s political subdivision sets fees, and zoning is a separate approval. Where no certified department has jurisdiction, nonresidential plans go to the state, while houses need no plan submission. The Board’s building-department look-up shows which department has authority over an address. Who has authority in Ohio
Permit types
Residential permits
One-, two- and three-family dwellings follow the Residential Code of Ohio. Cleveland charges $10 per $1,000 of estimated cost for new houses and additions (minimum $150) and $5 per $1,000 for alterations and repairs (minimum $30), plus a $20 residential zoning fee.
Commercial permits
Buildings regulated by the Ohio Building Code are charged $12 per $1,000 of estimated cost for new buildings, additions and first tenant build-outs under $1,000,000 (minimum $300) and $15 per $1,000 for alterations and repairs under $1,000,000 (minimum $150), with lower rates on the cost above $1,000,000. The zoning fee for commercial, multifamily and parking-lot projects is $150.
Two statewide topics shape most Ohio submittals: energy compliance (the 2021 IECC or ASHRAE 90.1-2019 for commercial buildings, Chapter 11 of the Residential Code of Ohio for houses) and work on existing buildings, where alteration, repair, addition and change of occupancy each carry their own requirements. Energy and existing buildings in Ohio
Cleveland permit costs and fees
Cleveland fees follow the Department of Building & Housing’s Plan Examination and Permit Fee Schedule, effective 2 January 2014. Plan examination is charged by floor area and paid when plans are submitted; permit fees are mostly charged on the estimated cost of the work. A State of Ohio surcharge of 1 percent (1–3 family) or 3 percent (Ohio Building Code buildings) is added to the permit fee (ORC 3781.102). Neighbouring municipalities publish separate schedules.
Rather talk it over?
Call 1-855-478-4290 →| Fee component | How it works |
|---|---|
| Plan review | $20 per 1,000 sq ft of floor area examined (minimum $20), non-refundable and due at submission; plans revised after the permit is issued are charged again |
| Building permit | $10 per $1,000 of estimated cost for new 1–3 family work (minimum $150); $12 per $1,000 for new Ohio Building Code work under $1,000,000 (minimum $300) |
| Trade permits | Separate electrical, HVAC and plumbing schedules; electrical work in new construction, additions and alterations is $50 per 1,000 sq ft (minimum $50) |
| State BBS assessment | Collected on top of local fees for the Board of Building Standards: 3% of nonresidential and 1% of residential fees (ORC 3781.102) |
| Certificate of Occupancy | $60 |
| Work without a permit | A late fee of $100 plus 25% of the permit fee if reported within 72 hours, or $200 plus 25% after that |
Need a real number for a specific Cleveland project? Send us the scope, address and valuation and we will identify the filing path, the reviews it will trigger and the fee categories that will apply.
Fee schedules are revised on each jurisdiction’s own cycle, so ask the issuing department for the schedule in force on your filing date, and ask separately about plan review, trade, re-inspection and revision charges. A Board of Building Standards assessment of 3 percent (nonresidential) or 1 percent (residential) is added to local fees. How Ohio permit fees work
Trade permits and who may pull them
Permit required
- Service installations, panel upgrades, new circuits, solar PV and EV chargers
- New plumbing, repipes, water heater change-outs, fixtures, backflow and gas piping
- HVAC installation and change-out, ductwork, venting and commercial kitchen exhaust
- Sprinkler, standpipe and fire alarm work under the OBC fire-protection provisions
Typically exempt
- Replacing lamps, reinstalling plug receptacles and replacing circuit breakers of the same capacity and type in the same location
- Clearing stoppages and repairing leaks, where no more than one fixture is replaced and no pipes are rearranged
- Replacing a mechanical-equipment part that does not alter the equipment’s approval or make it unsafe
- Replacing a minor gas-appliance part that does not alter the equipment’s approval or make it unsafe
Rather not deal with the building department?
Get a free quote →Ohio licenses five commercial trades statewide through the Ohio Construction Industry Licensing Board: electrical, HVAC, hydronics, plumbing and refrigeration. The state does not license general or residential contractors, so those are licensed or registered locally, if at all. Home construction contracts of $25,000 or more must be in writing under ORC 4722. Contractor licensing in Ohio
How to apply for a Cleveland building permit
Use the Board’s building-department lookup; most neighbouring municipalities have their own department.
Upload the site plan, floor plan or section and elevation drawing, and pay the application fees, in the Permit Portal.
The Landmarks Commission reviews exterior changes to designated landmarks and districts.
Once the project application is approved, submit construction drawings, pay the fees and download the permit.
The city sends the list of electrical, HVAC and plumbing permits the project needs.
Commercial trade contractors need an OCILB licence; the city has its own contractor registration and trade packages.
Approved plans become invalid if work has not started within twelve months, with one twelve-month extension available. Before filing, confirm the department has authority over the address for the work, whether the Ohio Building Code or the Residential Code of Ohio governs, and which approvals must be in hand first. Review and corrections in Ohio
Inspections in Cleveland
The city requires inspections before concrete is placed for footers, slabs and garage foundations; before backfilling over waterproofing and drain tile; before insulation, plumbing, mechanical and electrical work is covered; before rough framing is covered; at final, with the Certificate of Occupancy; and for all exterior demolition. The contractor or owner calls the inspector named on the permit at least 24 hours ahead, and the drawings stamped “APPROVED” must be on site.
The city charges a useless-trip fee when an inspection is booked and the work is not ready, and says the homeowner must be present for inspections.
No building may be occupied until a certificate of occupancy or completion is issued, and a change of occupancy needs approved construction documents even without other work. Address correction notices before requesting a re-inspection, and do not cover work before it has been inspected and approved. Inspections and occupancy in Ohio
Want this handled start to finish?
Get a free quote →Cleveland permit search and official resources
Permit records sit with the department that issued them, which in Ohio makes record research a certification question first. A property may have records with a municipal department, a county department, a township department or the state, depending on who held authority at the time the work was done — and that can have changed if a department gained or gave up certification, or if the property was annexed. Cleveland’s Permit Portal shows the permit history at an address to anyone, with no login needed; ask the Department of Building & Housing whether earlier records may sit elsewhere.
The Board's building-department lookup helps here too: it establishes who has authority today, which is the right starting point even when the history is more complicated.
Confirm two things before you file: the code, and the department. The Ohio Building Code has been based on the 2021 International Codes since 1 March 2024, the Residential Code of Ohio is the 2019 edition based on the 2018 International Residential Code, and both use the 2023 National Electrical Code — but the department with authority over your address, and the scope of its certification, is the answer that changes from parcel to parcel. Use the Board's building-department lookup, then confirm fees, submittal requirements and review turnaround with that department for your filing date.
These are the primary sources behind this guide. Codes, fee schedules and portal procedures change. Confirm the position for your filing date.
- City of Cleveland Division of Construction Permitting
- Ohio Board of Building Standards
- BBS — find the building department for your address
- Ohio Construction Industry Licensing Board
- ORC Chapter 4722, home construction service contracts
Frequently asked questions
How do I confirm I am inside Cleveland?
Check the address against the Board’s building-department lookup. Most of the municipalities around Cleveland have their own certified department; Cuyahoga County has none.
Inspections are where schedules slip.
Get a free quote →What governs a renovation here?
For buildings under the Ohio Building Code, the International Existing Building Code as modified by OBC Chapter 34 (OBC 102.7); for one-, two- and three-family dwellings, RCO Section 113 (RCO 102.7). They set how much of the structure must be brought to current requirements and what a change of occupancy triggers.
Does my project fall under the OBC or the RCO?
Commercial, industrial and public buildings follow the Ohio Building Code. One-, two- and three-family dwellings follow the Residential Code of Ohio. Ohio’s residential code reaches three-family dwellings, where the International Residential Code stops at two.
How do I know which department issues my permit?
Use the Board of Building Standards building-department lookup, which maps an address to the department with authority over it. Only a BBS-certified department, or the state, may approve plans and issue permits, and certification does not follow automatically from being a city, county or township.
Does my general contractor need an Ohio licence?
There is no statewide general-contractor licence in Ohio. The state licenses five commercial trades through the OCILB — electrical, HVAC, hydronics, plumbing and refrigeration — while general contractors, and trade contractors on residential work, are licensed or registered only where a local government requires it. Home construction and improvement contracts of $25,000 or more on one-, two- and three-family dwellings must be in writing under ORC 4722, and the supplier must carry at least $250,000 of general liability insurance.
How long is my approval good for?
Approved construction documents are valid where work commences within 12 months, with one 12-month extension available under Section 105 of the Ohio Building Code and the Residential Code of Ohio. Confirm the position with the issuing department before an approval is allowed to age.
Simplify Cleveland permitting with Alliance Permitting
In Cleveland two questions come first: whether the parcel is inside the city, and what the project application must clear before the building permit.
Trusted by leading builders, developers, and national contractors — 21+ years of filing in the jurisdictions we write about.
Contractors and builders choose Alliance for Cleveland because the work is done by people who have stood at the counter:
- We confirm the parcel is inside the city before filing.
- We agree the existing-building compliance path before design develops.
- We check historic and landmarks designation before exterior work.
- We clear zoning ahead of the building application.
- We sequence inspections so concealed and rated work stays observable.
Alliance Permitting is a permit documentation and submission company in Ohio. We prepare your paperwork, file it correctly and coordinate with the building department through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Cleveland sooner?
Let Alliance prepare, file, and track your Cleveland permits while your crew stays on the job.
More Ohio permitting guides
This guide is provided by Alliance Permitting for general information about Cleveland permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.