The Town of Hope Mills Inspections Department issues building, electrical, mechanical, plumbing and insulation permits inside town limits, and applications are emailed to the Town’s two Permit Specialists. Building permits are priced on construction value, from $100 up to $50,000 and $6 per $1,000 above that, plus a $25 application fee; fire-related permits have come from the Fire Marshal’s Office since August 1, 2023.
What requires a permit in Hope Mills?
The Building Inspections & Permitting Department lists the permits it issues inside town limits:
Building
- New commercial and residential buildings
- Renovations and additions
- Accessory buildings
- Mobile home tie-downs
- House moving
- Demolition
- Swimming pools
- Signs
- Piers, docks and bulkheads
Trades
- Electrical
- Mechanical and gas piping
- Plumbing
- Insulation
- Conditional temporary power
Development & Planning issues separate zoning permits for signs, structures, fences, home occupations, new businesses, swimming pools and fundraisers, and driveway work has its own Town application.
Hope Mills building department: who handles permitting
| Detail | Information |
|---|---|
| Authority | Town of Hope Mills Inspections Department (Building Inspections & Permitting) |
| Contact | Permit Specialists 910-426-4100 / 910-222-4280 |
| Office / hours | Mon–Thu 7:30 a.m.–5:00 p.m. (closed 12:30–1:00 p.m. for lunch); Fri 7:30–11:30 a.m. |
| Fire permits | Fire Marshal’s Office, 910-429-3397 |
| Chief Building Official / Director | Kenny Tatum, 910-426-4118 |
| Zoning | Development & Planning, (910) 424-4555 |
Office: 5770 Rockfish Road, Hope Mills, NC 28348-1848. Permit and payment processing stops 45 minutes before closing each day, so the last window is 4:15 p.m. Monday to Thursday and 10:45 a.m. on Friday.
Hope Mills permit applications and filing
Download the application for your project from the Building Inspections & Permitting page, complete it and email it to both Permit Specialists, as the Town asks. The forms it publishes are:
Short on time to read all of this?
Get a free quote →- New Residential Building Permit Application, with the general contractor’s state licence number, classification and limitation, the subcontractors, utility providers and heated and unheated square footage.
- New Commercial Building Permit Application, with occupancy, construction type, sprinkler status and total floor area.
- Additions/Renovations/Improvements Permit Application.
- Separate Electrical, Mechanical, Plumbing and Insulation permit applications.
- Demolition, Driveway and Sign permit applications, and the Zoning Application.
- Owner Exemption Affidavit, required when an unlicensed property owner applies for the building permit; the owner swears to personally superintend and manage the work.
- Worker Comp. Coverage Affidavit.
- Application for Conditional Temporary Power, signed by each contractor to confirm the systems are safe to energize before the final.
Every application states the value of the improvement: the market value of the finished construction without land, including the electrical, mechanical and plumbing work. That figure sets the building permit fee.
Permit fees in Hope Mills
Fees come from the Town’s 2024-2025 Inspections Fee Schedule. Building permits are charged on the value of the work, and a $25 application/technology fee is added to each building and trade permit.
| Project | Fee |
|---|---|
| Value up to $2,500 | $100 |
| $2,501–$10,000 | $115 |
| $10,001–$15,000 | $125 |
| $15,001–$20,000 | $135 |
| $20,001–$25,000 | $155 |
| $25,001–$30,000 | $165 |
| $30,001–$35,000 | $185 |
| $35,001–$40,000 | $195 |
| $40,001–$45,000 | $215 |
| $45,001–$50,000 | $225 |
| $50,001 and above | $6 per $1,000 of value |
| Application/technology fee | $25 |
| Extra inspection (call-back) or not-ready fee | $100 each |
| Temporary CO application | $200 |
| Stocking CO application | $100 |
Not sure this scope needs a permit?
Get a free quote →Building plan review is a separate charge set by floor area: $200 up to 5,000 sq ft, $350 to 10,000 sq ft, $500 to 15,000 sq ft, $650 to 25,000 sq ft, $950 to 40,000 sq ft and $1,100 above that. Stand-alone electrical, mechanical or plumbing plan review is $125. Fire-related permits and payments go to the Fire Marshal’s Office, not to Inspections.
Electrical, plumbing, mechanical and gas permits
The Inspections Department issues each trade on its own application, even when the work is part of a building project. Trade permits carry a minimum fee of $100 for residents and $125 for non-residents, plus the $25 application fee, and call-backs or not-ready inspections cost $100.
| Permit | Fee |
|---|---|
| Electrical service, residential up to 200 A / over 200 A | $100 / $125 |
| Electrical service, commercial up to 400 A / over 400 A | $125 / $150 |
| Sub-panel | $100 |
| Outlets | $25 for the first 10, then $1 each |
| Furnace, condensing unit, air handler or appliance circuit | $50 |
| Temporary pole | $100 |
| Heat or A/C, residential / commercial | $125 / $150 per system |
| Gas piping | $75 including one appliance, $40 each additional |
| LP gas tank and piping | $75 |
| Commercial kitchen hood | $125 |
| Plumbing fixtures and water heaters | $35 each |
| Main sewer, water or irrigation line | $50 each |
| Fire sprinkler | $20 tap connection plus $1 per head, $50 minimum |
Alliance handles electrical permit filing for contractors here. More on this: who pulls the electrical permit.
Rather talk it over?
Call 1-855-478-4290 →Application documents and plan review
The residential application doubles as a checklist of the approvals the Town expects to see before it issues a permit:
New home
- Completed New Residential Building Permit Application with the parcel number
- Licensed general contractor details, or the Owner Exemption Affidavit
- Electrical, plumbing, mechanical and insulation contractors
- Flood hazard development permit if the lot is in a special flood hazard area
- Approved soil erosion and sedimentation plan where one is required
- Health Department approval for a well or septic tank
- Heated and unheated square footage and construction value
Commercial
- Completed New Commercial Building Permit Application
- Occupancy group and construction type
- Total floor area and area per floor
- Sprinkler status and fire sprinkler permit where needed
- Utility details (public or private water and sewer)
- Construction drawings for plan review, priced by floor area
Both applications also ask whether the job needs NC Department of Labor elevator approval, new curb cuts or digging in the right-of-way, or is in a watershed. The Town does not publish a plan review turnaround time.
Before you file
Check the property’s zoning district and setbacks with Development & Planning at (910) 424-4555 first. Properties in the Municipal Influence Area must meet both the Town’s development standards and Cumberland County’s zoning rules. The Town adopted an amended Zoning Ordinance in August 2025 and an amended Subdivision Ordinance in October 2025, and it publishes site plan requirements for projects that need one.
Rather not deal with the building department?
Get a free quote →How to apply: 6-step Hope Mills process
Make sure the lot is inside Hope Mills town limits and check its district and setbacks with Development & Planning.
Line up any flood hazard development permit, erosion control plan, septic or well approval and driveway permit the lot needs.
Use the residential, commercial or additions form, list every subcontractor and state the full construction value. Owner-builders add the Owner Exemption Affidavit.
Send the application and drawings to both Permit Specialists, and file separate electrical, mechanical, plumbing and insulation applications.
Pay the permit, plan review and $25 application fees before the daily processing cut-off, then post the permit on site out of the weather.
Request each inspection by phone when the work is ready, through the final and Certificate of Occupancy.
Inspections and closeout in Hope Mills
Call 910-426-4100 or 910-222-4280 to request an inspection and give the permit number, inspection type, property address, your name, phone and email, and any lock box or gate codes. Requests missing any of these may not be scheduled. Requests called in before 9:00 a.m. can be scheduled the same day if needed; later requests go to the next business day.
Only call when the work is ready: a not-ready inspection or a call-back costs $100. If temporary power is needed before the final, each contractor signs the Conditional Temporary Power form; it does not replace the final inspection, and missing the final deadline is grounds for disconnecting the power. A temporary Certificate of Occupancy application costs $200 and a stocking CO $100.
Local details that matter in Hope Mills
Fire Marshal: since August 1, 2023 all fire-related permits and payments go through the Fire Marshal’s Office (910-429-3397), so a commercial job can have separate Inspections and Fire Marshal records.
Short Fridays: the department closes at 11:30 a.m. on Fridays and for lunch from 12:30 to 1:00 p.m. Monday to Thursday.
Waterfront work: piers, docks and bulkheads are on the Town’s list of building permits.
Non-resident trade fees: the minimum electrical, mechanical and plumbing fee is $25 higher for non-residents.
North Carolina building code
The 2018 North Carolina State Building Code family applies statewide, with the 2020 North Carolina Electrical Code; one- and two-family homes and townhouses still use the 2017 edition. The 2024 code has been delayed and cannot take effect before late 2027. The NC State Building Code and the delayed 2024 edition
Want this handled start to finish?
Get a free quote →Official permitting resources
These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.
- Current state codes
- Hope Mills zoning
- How to schedule an inspection
- Inspections Department
- Building Inspections & Permitting and application forms
- Hope Mills 2024-2025 Inspections Fee Schedule
- New Residential Building Permit Application
- New Commercial Building Permit Application
- Owner Exemption Affidavit
- Application for Conditional Temporary Power
Hope Mills permit FAQ
Who issues building permits in Hope Mills, NC?
The Town of Hope Mills Inspections Department issues building, electrical, mechanical, plumbing and insulation permits inside town limits. Fire-related permits come from the Fire Marshal’s Office.
Inspections are where schedules slip.
Get a free quote →How much is a building permit in Hope Mills?
It depends on construction value: $100 for work up to $2,500, rising in steps to $225 at $50,000, then $6 per $1,000 of value. A $25 application fee and any plan review fee are added.
Can I submit a Hope Mills permit application by email?
Yes. The Town takes permit applications by email and asks you to copy both Permit Specialists.
Can a homeowner pull a building permit in Hope Mills?
Yes. An unlicensed property owner fills in the Owner Exemption Affidavit with the application and agrees to personally manage the construction.
How do I schedule a Hope Mills building inspection?
Call 910-426-4100 or 910-222-4280 with the permit number, inspection type, address, your contact details and any access codes. Calls before 9:00 a.m. can be scheduled the same day if needed.
What happens if the work is not ready for inspection?
The Town charges a $100 not-ready fee, and each extra call-back inspection is also $100.
Who handles fire permits in Hope Mills?
The Fire Marshal’s Office, at 910-429-3397, handles fire-related permits and payments separately from Building Inspections.
Simplify Hope Mills permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in North Carolina. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Hope Mills sooner?
Let Alliance prepare, file, and track your Hope Mills permits while your crew stays on the job.
More North Carolina permitting guides
Cumberland County
Read guide →Fayetteville
Read guide →Spring Lake
Read guide →Huntersville Building Permit Guide
Read guide →Indian Trail Building Permit Guide
Read guide →Iredell County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Hope Mills permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.