Skip to main content

Wayne County, New York Building Permit Guide

To get a building permit in Wayne County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Wayne County has no county building department: each of its 15 towns, and the villages that run their own code offices, issue building permits, while the county issues highway work permits and reviews referred zoning actions.

Authority: Town and village code enforcement officesCode: 2025 NYS Uniform Code and Energy Code
Building permits
Town or village15 towns, 7 villages counted by the Census
County roads
Highway work permit7227 Route 31, Lyons; 315-946-5600
County referrals
No feeFiled by the town or village, not the applicant
Flood maps
New mapsMost dated November 13, 2026 by FEMA

Building permits in Wayne County come from the town where the land lies, or from the village where a village runs its own code office; the county government lists no building or code enforcement department of its own. The county’s part is narrower: the Highway Department in Lyons issues work permits for county road rights-of-way, including new driveways, which county crews install, and the County Planning Board reviews zoning and site plan actions that towns and villages must refer under General Municipal Law 239-m.

What requires a building permit in Wayne County?

Each town and village works from its own code and application. The Town of Ontario, for example, lists additions, decks, fences, new buildings, signs, sheds, pools and hot tubs, fill and excavation, driveways, roofs, plumbing, electrical and heating systems, generators and solar arrays. Arcadia’s one application covers new homes through stoves and mobile homes. Septic systems are a town matter too: the Town of Lyons, for one, has its own Septic Law in Chapter 247 of its code.

Town or village permit

  • New homes, additions and alterations
  • Sheds, garages, decks and fences where the local code lists them
  • Pools, hot tubs and their barriers
  • Roofs, generators and solar arrays
  • Plumbing, electrical and heating work
  • Septic systems under town septic laws
  • Demolition and changes of use

County approvals

  • Any work in or next to a county road right-of-way
  • New private driveways onto county roads, installed by county forces
  • Signs and utility lines in the county right-of-way
  • Over-size and over-weight hauling on county roads

What the towns decide and what the state holds

All of these offices apply the same 2025 Uniform Code and Energy Code. What they set themselves is the local layer: zoning districts and setbacks, which small projects they exempt, septic rules, permit lifetimes and the fee schedule. Ontario’s code, for example, limits permits to six and twelve months with two renewals, while Macedon still posts a 2014 fee schedule that adds escrow and recreation charges to a new house.

Wayne County building department: who handles permitting

The table lists every town and village the Census Bureau counts in the county. A town code office covers land outside any village that has its own office.

Short on time to read all of this?

Get a free quote →
Building permit offices in Wayne County (22 municipalities)
PlaceWho issues building permitsOfficial page
Arcadia (town)Town Code Enforcement Officer, 201 Frey Street, Newark; see the Arcadia guideLinked in that guide
Newark (village, in Arcadia)Village code enforcement, Village Hall, 100 E. Miller Street; 315-331-4770Village Code Chapter 62; see the Arcadia guide
Butler (town)Town officeNo official page found
Galen (town)Town Zoning and Code Enforcement Officer, 6 South Park Street, Clyde; 315-923-7259 ext. 5Zoning & Codes
Clyde (village, in Galen)Village code enforcement under Village Code Chapter 67; village office (315) 923-3971Village Code Ch. 67
Huron (town)Town Building Department; appointments 315-594-8074 ext. 201Building Department
Lyons (town)Town planning, zoning and code office, Town Hall, 43 Phelps Street; 315-946-6252Planning and Zoning
Macedon (town)Town Building & Zoning; 315-986-5932Building & Zoning
Marion (town)Town Code Enforcement/Building Department; 315-573-0233, weekdays 9 a.m. to 1 p.m.Code Enforcement
Ontario (town, no villages)Town Building Department & Code Enforcement, 1850 Ridge Road; see the Ontario guideLinked in that guide
Palmyra (town)Town Office of Code Enforcement; (315) 597-4999, weekdays 8 a.m. to 4 p.m.Office of Code Enforcement
Palmyra (village, in Palmyra)Village officeNo official page found
Rose (town)Town code enforcement officerCode Enforcement
Savannah (town)Town officeNo official page found
Sodus (town)Town Code Enforcement, 14-16 Mill Street, Sodus; 315-812-0609Code Enforcement
Sodus (village, in Sodus)Village Building & Code Enforcement; same office number, 315-812-0609Building & Code Enforcement
Sodus Point (village, in Sodus)Village Code Enforcement Office; village office (315) 483-9881Code Enforcement Office
Walworth (town)Town Building & Code; (315) 986-1400, weekdays 8 a.m. to 4 p.m.Building & Code
Williamson (town)Town code enforcementNo readable official page
Wolcott (town)Town code enforcementTown website
Wolcott (village, in Wolcott and Butler)Village Code Enforcement; 315-594-9501Code Enforcement
Red Creek (village, in Wolcott)Village officeNo official page found

Not sure this scope needs a permit?

Get a free quote →

Three places need care. Clyde’s village office and Galen’s town code office share the 6 South Park Street building, but Galen’s zoning map covers only the town outside the village, and Clyde enforces the code under its own Chapter 67. The Town and Village of Sodus list the same code office number, 315-812-0609, while Sodus Point, also in the Town of Sodus, runs its own code enforcement office. The Village of Wolcott straddles the Towns of Wolcott and Butler, and its own code enforcement office covers both parts.

What Wayne County itself does

  • Highway Department: a highway work permit is required for any work within or immediately next to a county road right-of-way. Applicants return the application with the fee and a site plan to 7227 Route 31, Lyons (315-946-5600), and a county representative calls to discuss the work. Permit holders do their own work at their own expense, except new private driveways, which county forces install. Forms include a driveway permit and a Section 136 Highway Law permit.
  • Planning Board: reviews referrals from towns and villages for actions within 500 feet of a municipal line, a county or state road or park, county drainage channels, state or county land, or a farm in an agricultural district. There is no fee, and the county warns that any payment request in its name is a scam.
  • Real Property Tax Service: posts tax maps for finding a parcel’s town.

Wayne County permit types and applications

Rather talk it over?

Call 1-855-478-4290 →

Residential permits

Each office has its own process. Galen’s code officer handles the full range in one post: Uniform Code and Energy Code enforcement, fire safety and property maintenance inspections, floodplain administration and the Multiple Residence Law, as well as the town zoning law. Arcadia files building permits and books inspections through Cloudpermit, Ontario wants an application, a survey map showing distances from lot lines, specification sheets and a workers’ compensation certificate and takes no money until the permit is approved, and Huron meets applicants by appointment. Macedon keeps its building, zoning and planning forms on one page and takes questions at 315-986-5932.

Commercial permits

Commercial projects usually need a town or village site plan approval first, and many of them trigger a county referral: a building on a county or state road, near a town line or next to farmland in an agricultural district is the kind of action the Planning Board sees. The County Planning Board meets on the last Wednesday of each month (with one combined meeting on the second Wednesday of December), and referrals are due the Monday a week before.

What comes before the building permit

  • Zoning: the town or village zoning officer, Zoning Board of Appeals and Planning Board.
  • County referral: sent by the local board, not the applicant; the county returns its recommendation within 10 days of its meeting.
  • Septic: the town’s septic rules and, in Macedon, a witnessed percolation test.
  • Driveway: a county highway work permit for access onto a county road; town and state roads have their own.
  • Utilities: sewer connection charges where a district serves the lot, such as Macedon’s $1,000 minimum and Gananda’s $800.

Building permit fees in Wayne County

There is no county building permit fee. Each town and village adopts its own schedule, and the published examples vary widely in form.

Rather not deal with the Wayne County building department?

Get a free quote →
Published building fee rules in Wayne County towns
PlacePublished fee ruleSchedule
Town of MacedonOne- or two-family building permit and certificate: $0.10 per sq ft, $200 minimum; plus a $500 refundable escrow for a new house and a $600 parks and recreation fee per living unit2014 fee schedule posted by the town
Town of MacedonPercolation test witnessing: $125 for a single lot2014 fee schedule posted by the town
Town of OntarioFee set when the permit is approved; $100 for work started without a permit2026 schedule adopted January 5, 2026
Town of ArcadiaFee assessed by the code officer when the permit is processedNo schedule posted
Town of WalworthPermit fee, escrow and parks and recreation columns by type of structure2026 schedule, adopted effective January 1, 2026

Worked example from Macedon’s posted schedule: a 2,200-square-foot new house is 2,200 × $0.10, or $220 for the permit and certificate, above the $200 minimum. The same house also pays the $600 parks and recreation fee and posts a $500 escrow that is refunded after final cleanup and grading. Other towns price the same house under their own schedules.

Trade permits and who may pull them

The county has no licensing office for electricians, plumbers or home improvement contractors. Electrical work is inspected under each town’s own rule: Ontario’s code names three electrical inspection agencies it has deputized, and Arcadia’s pool sheet calls for a third-party electrical inspection. Ontario asks for a workers’ compensation certificate with every application and refuses ACORD forms.

How to get a building permit in Wayne County

1. Identify the municipality

Use the county tax maps, then check whether the parcel is inside a village with its own office.

2. Talk to the code office

Confirm zoning, setbacks and any board approval; the local board starts any county referral.

3. Plan septic and access

Follow the town septic law and file a county highway work permit for a county road driveway.

4. Assemble the application

Site plan or survey, drawings, specification sheets and insurance proof.

5. File and pay

Use the town’s portal or counter; some towns bill the fee only once the permit is approved.

6. Inspect and close

Book inspections with the town or village and get the certificate before use.

Review, corrections and what causes delay

Review times are local: Ontario allows a minimum of 15 working days with no exceptions. Short office hours slow things in several towns; Marion’s code office is open from 9 a.m. to 1 p.m., Galen closes at 1 p.m. on Wednesdays, and the Sodus code office is closed on Fridays. A project that needs a county referral cannot be decided by the local board until the county responds or its time runs out.

Want this handled start to finish?

Get a free quote →

Inspections and certificates

Inspections are scheduled with the office that issued the permit. Marion publishes its full sequence: site plan, footers and floor preparation before concrete, foundation walls and footer drains before backfill, then framing, plumbing, HVAC, electrical wiring and insulation before anything is covered, plus wood stove and chimney connections. All wiring there is inspected by an independent agency that certifies it to the town, the town inspects every septic system, and the design engineer must also inspect each new system and certify it was built to the approved plans. Marion needs 24 hours’ notice for the final, which closes the permit with a certificate of compliance, and it considers inspections by appointment on Mondays, Wednesdays, Thursdays and Fridays; Arcadia books them in Cloudpermit; Ontario issues a certificate of occupancy or compliance after the final inspection, and the building may not be used before it. Macedon charges $25 for a certificate of compliance or occupancy, and its escrow is released after final cleanup, grading and seeding are approved.

New York building code

New York builds on one statewide code, the Uniform Code, outside New York City; the 2025 edition and 2025 Energy Code took effect on 31 December 2025 (the all-electric provisions remain suspended by court order). Cities, towns and villages administer it, and local standards stricter than the code need Code Council approval. The Uniform Code in New York

In Wayne County that code is applied by each town and by the villages that keep their own code officers.

Wayne County permit FAQ

Does Wayne County issue building permits?

No. The town, or a village with its own code office, issues them. The county issues highway work permits for county roads and reviews referred zoning actions.

Who installs a new driveway culvert on a county road?

County forces install new private driveways onto county roads under a highway work permit; other work in the right-of-way is done by the permit holder at their own expense.

Who issues permits in the Village of Newark?

The village’s own code enforcement office at Village Hall, 100 E. Miller Street, not the Town of Arcadia.

Does the county charge for a planning referral?

No. County Planning Board review is free, and the county accepts referrals only from towns and villages, never from applicants.

Who handles septic systems?

The town, under its own rules; Lyons, for example, has a Septic Law in its town code, and Macedon witnesses percolation tests for $125 a lot.

Which office covers Clyde?

The Village of Clyde enforces the code inside the village under its Chapter 67; the Town of Galen’s officer, in the same building, covers the town outside it.

How long does a building permit last?

It depends on the town. Marion permits expire on the date written on the application, and the work must be finished by then; Ontario’s code sets six- and twelve-month limits with up to two renewals.

Are new flood maps coming?

Yes. FEMA’s Community Status Book shows every Wayne County community as participating, with new maps dated November 13, 2026 for most.

Inspections are where schedules slip.

Get a free quote →

Wayne County permit search and official resources

Permit records are kept by the town or village that issued the permit; ask its code office or clerk for copies, or file a Freedom of Information Law request. Arcadia’s Cloudpermit account shows the status of applications filed there.

Simplify Wayne County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in New York. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Wayne County sooner?

Let Alliance prepare, file, and track your Wayne County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Wayne County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.