Wallington Borough, New Jersey Building Permit Guide

To get a building permit in Wallington Borough, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Wallington’s Building Department at the Municipal Building, 159–161 Maple Avenue, issues construction permits on the state F100 application; its office is open to the public on Tuesday and Thursday mornings from 7:30 to 9:30.

Authority: Wallington Building DepartmentOffice hours: Tue & Thu 7:30–9:30 a.m.Phone: 973-777-0318 ext. 210
Office
159–161 Maple AveMunicipal Building, Wallington
Counter hours
Tue & Thu, 7:30–9:30 a.m.Fax 973-473-2447
Elevators
DCA enforcesOther subcodes held locally
Road opening
$175 or $350Plus $500 restoration deposit

Construction permits in the Borough of Wallington are issued by the Building Department at the Municipal Building, 159–161 Maple Avenue (973-777-0318, ext. 210), where Nick Melfi serves as Construction Official and also as Zoning Officer. The office keeps short public hours, 7:30 to 9:30 a.m. on Tuesdays and Thursdays, so plan filings and questions around them. Applications use the state F100 construction permit jacket with a technical section for each trade; DCA itself handles elevator work in the borough.

What requires a building permit in Wallington?

Wallington follows the state Uniform Construction Code line on what needs a permit. Ordinary maintenance, as the UCC defines it, can be done with no permit, notice or inspection. Minor work still needs a permit, but the UCC lets it start once the Building Department has been notified, with the paperwork and inspection following. All other construction, alteration, demolition, change of use and trade work needs a permit issued before work begins.

Permits from the Building Department

  • New houses, additions and second-story additions
  • Interior alterations and renovations
  • Electrical, plumbing, heating and fire protection work
  • Demolition
  • Facilities covered by an annual permit (form F102)

Other borough permits

  • Road or street openings for utility, sewer or water connections
  • Zoning review by the Zoning Officer, with variances from the Zoning Board of Adjustment
  • Site plans and subdivisions before the Planning Board
  • Landlord registration for one- and two-unit rentals

If you are unsure whether a job counts as maintenance, minor work or full construction, the Building Department is the place to ask; the published forms are the state F100 jacket, the F110 building technical section and the F102 annual permit application.

What Wallington decides and what the state holds

No town in New Jersey writes its own building code, so construction standards in Wallington are the state’s. The borough’s own lever is its Code: zoning in Chapter 365, subdivision and site plan review in Chapter 330, and affordable housing in Chapter 153, which the borough moved to repeal and replace in early 2026 (Ordinance 2026-07). Ordinances 2026-08 and 2026-10, both listed for adoption in March 2026, add affordable housing zones along Midland Avenue and Main Avenue, and 2026 agendas also carry redevelopment plans for the Main Avenue area, the Latex site and 350 Mount Pleasant Avenue.

Short on time to read all of this?

Get a free quote →

Wallington building department: who handles permitting

The Building Department is Wallington’s construction office. DCA’s roster of local enforcing agencies, current to September 2, 2026, shows the borough’s own officials in the construction official, building, electrical and fire protection posts, and lists the Department of Community Affairs as the elevator subcode official, so elevator and lift work is reviewed and inspected by DCA. The roster leaves the plumbing line empty, while the borough’s staff list names a plumbing inspector. The same office answers zoning questions, because the Construction Official is also the borough’s Zoning Officer, and Code Enforcement (ext. 207) handles property maintenance. Neighbors who suspect an illegal apartment or unpermitted conversion can use the Building Department’s illegal housing complaint form, and property maintenance problems have their own complaint form.

Wallington permit contacts
DetailInformation
OfficeBuilding Department, Municipal Building, 159–161 Maple Avenue, Wallington, NJ 07057
Phone / fax973-777-0318, ext. 210 / 973-473-2447
Public hoursTuesday and Thursday, 7:30 to 9:30 a.m.
Construction Official and Zoning OfficerNick Melfi
Code Enforcement973-777-0318, ext. 207
Planning and zoning boardsRecording clerk, Wallington Civic Center, 24 Union Boulevard, ext. 214
ElevatorsNew Jersey DCA (state enforcement)

DCA’s roster prints the construction office address as 54 Union Boulevard; the borough’s own Building Department page gives the Municipal Building at 159–161 Maple Avenue, so call ext. 210 if in doubt before you go. Borough Hall functions such as the Clerk sit at the Civic Center, 24 Union Boulevard.

Wallington permit types

A Wallington construction permit is one application: the F100 jacket naming the owner, the contractor and the work, plus a technical section for every subcode involved (building, electrical, plumbing, fire protection, or elevator for DCA). The borough posts the F100, the F110 building section and the F102 annual permit form on its Building Department page.

Residential permits

  • New houses and additions. Expect zoning review first; in 2026 the Zoning Board of Adjustment has heard both a new single-family house on two combined lots and an appeal of the Zoning Officer’s decision on a second-story addition.
  • Alterations and trade work. Kitchens, baths, basements, heating systems and electrical upgrades go on the same F100 with the matching subcode sections.
  • Rental homes. Owners of a one-unit rental, or of a two-unit house they do not live in, file the state landlord identity registration statement with the Borough Clerk and give a copy to tenants; buildings of three or more units register with the state Bureau of Housing Inspection instead.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

Store fit-outs, restaurants, offices and apartment buildings follow the same F100 route; a new building or a change that needs site plan approval goes to the Planning Board first. Larger facilities that do continuous maintenance can apply for an annual permit on form F102, which lists the buildings covered and where the permit records are kept. The Bureau of Fire Safety separately inspects public buildings such as restaurants, schools, gas stations, churches, shopping plazas and apartment complexes under the state fire code.

What comes before the construction permit

  • Zoning. The Zoning Officer checks the plan against Chapter 365. If it does not comply, or you disagree with his decision, the Zoning Board of Adjustment hears variances and appeals at 7:30 p.m. on the last Tuesday of the month at the Civic Center.
  • Planning Board. Site plans and subdivisions under Chapter 330 go to the Planning Board, which meets at 7:30 p.m. on the third Tuesday of the month; the Borough Engineer and Planner sits with the board.
  • Soil disturbance. Sites disturbing more than 5,000 square feet need a soil erosion and sediment control plan certified by the Bergen County Soil Conservation District.
  • Road openings. Any cut into a borough street for a utility lateral or service needs Wallington’s road opening permit (see the fee table). On a county road the county’s own road opening permit applies instead, from the Bergen County Operations Division (201-336-7678), and county-road driveways, site plans and subdivisions go through the county’s GeoCivix portal.
  • Health. Wallington’s Board of Health is served by the Mid-Bergen Regional Health Commission (201-599-6290), the office to ask about any health approval a project needs.

Wallington permit costs and fees

Wallington’s construction permit fees are set by ordinance in the Borough Code, which is published on eCode360; the Building Department pages do not post a fee table, and none of the 2025–2026 Mayor and Council agendas carries a new construction fee ordinance. Ask the Building Department during office hours for the fee on your job before you file. Under state rules the plan review fee is paid when you submit and credited against the permit fee, and the state surcharge (N.J.A.C. 5:23-4.19) is added to the borough’s construction fees.

The fees Wallington does print are on its road opening permit application:

Rather talk it over?

Call 1-855-478-4290 →
Wallington road opening / street opening permit fees
ItemAmount
Extensive opening (100 feet or more, laterals less than 100 feet apart, or 20% or more of the frontage)$350, non-refundable
Any other road opening$175, non-refundable
Security deposit for pavement, curb and topsoil restoration$500, unless the Borough Engineer or an ordinance sets another amount
Construction, plumbing, electrical, fire and elevator permitsBorough fee ordinance; ask the Building Department (elevator fees are DCA’s)

The road opening form also sets the work rules that drive cost: backfill with dense graded aggregate or another approved material compacted in 6-inch lifts, a saw-cut edge, then 5 to 6 inches of stabilized base and 1 to 2 inches of surface asphalt unless the Borough Engineer directs otherwise. All fees, escrows and deposits are subject to the borough’s confirmation.

Trade permits and who may pull them

Wallington does not issue separate trade permits on its own forms: electrical, plumbing and fire protection work is added to the F100 jacket with the state technical section for that trade, and the borough’s electrical inspector, plumbing inspector and fire subcode official review and inspect it. Elevators, wheelchair lifts and similar devices are the one subcode the roster assigns to DCA.

  • Licensed trades. In New Jersey, electrical contractors, master plumbers and HVACR contractors hold state licenses.
  • Contractors. The state has no general-contractor license. Home improvement contractors register with the Division of Consumer Affairs and new-home builders with DCA; an owner working on their own home does not register.
  • Street work. A contractor cutting a borough road lists the company and its contact on the road opening application, and the owner signs a consent on the same form.

How to apply for a Wallington building permit

1. Check zoning

Ask the Zoning Officer during Tuesday or Thursday office hours whether the project meets Chapter 365.

2. Get board approval if needed

Apply to the Zoning Board of Adjustment for a variance, or the Planning Board for a site plan or subdivision, through the recording clerk at ext. 214.

3. Complete the F100 jacket

Download the F100 and the technical sections for each trade; licensed contractors complete their own sections.

4. Add drawings

Attach construction drawings and any prior approvals, such as a board resolution or a soil district certification.

5. File at the Building Department

Deliver the package to 159–161 Maple Avenue during office hours; questions go to ext. 210.

6. Pay and post the permit

Pay the fee the office calculates and keep the permit visible on site until the final inspection.

Rather not deal with the Wallington Borough building department?

Get a free quote →

Review, corrections and what causes delay

Each subcode official reviews their own section, and the state code gives the construction official 20 business days to approve or deny a complete application (N.J.A.C. 5:23-2.16). With only two short public windows a week, a missing drawing, an unsigned technical section or an approval still pending at a board usually means another trip. A refusal on a construction code question can be appealed to the Bergen County Construction Board of Appeals; zoning decisions go to the borough’s Zoning Board of Adjustment.

Inspections and certificates in Wallington

Call the Building Department at 973-777-0318, ext. 210, to book inspections. State rules require at least 24 hours’ notice, and the inspector for each trade signs off that trade’s work; on a new house the first stops are the footing trenches and the foundation before backfill. Road openings have their own notice rule: tell the Department of Public Works (ext. 501) and the construction office at least 24 hours ahead, and the Police Department (973-473-1715) 48 hours ahead; openings are not allowed on Fridays without the borough’s approval.

Once the finals pass, the construction official issues a certificate of occupancy for new buildings or a certificate of approval for altered space. Before a one- or two-family home is sold or newly rented, the state fire code requires a smoke and carbon monoxide alarm certificate from the local fire official. Wallington’s pages do not describe its version, so ask the Bureau of Fire Safety (973-777-0318, ext. 215, by appointment) what the inspection checks, how to schedule it and what it costs before you set a closing date.

New Jersey building code in Wallington

Wallington’s Building Department enforces the state Uniform Construction Code for every subcode except elevators, where DCA enforces directly. FEMA’s Community Status Book lists Wallington (community 340079) as a participating National Flood Insurance Program community with flood maps effective August 28, 2019, so check the flood zone before you design.

New Jersey has one Uniform Construction Code for every municipality; the town supplies the enforcing agency, the fee ordinance and the zoning approvals. New Jersey rules

Want this handled start to finish?

Get a free quote →

Wallington permit search and official resources

Permit records in Wallington come through the Borough Clerk. To see past permits, plans or certificates for a property, make an Open Public Records Act request to the Borough Clerk, either by e-mail as the Clerk’s page directs or on the borough’s OPRA form (Clerk’s office, Civic Center, 24 Union Boulevard, ext. 201, open 8:30 a.m. to 4:30 p.m.). The Building Department’s monthly report goes to the Mayor and Council and appears on their meeting agendas.

Inspections are where schedules slip.

Get a free quote →

Wallington building permit FAQs

When is the Wallington Building Department open?

Its public office hours are Tuesday and Thursday from 7:30 to 9:30 a.m. at 159–161 Maple Avenue; the phone is 973-777-0318, ext. 210.

Who is the Construction Official in Wallington?

Nick Melfi, who is also the borough’s Zoning Officer and building inspector.

How much does a road opening permit cost?

$175 for an ordinary opening or $350 for an extensive one, both non-refundable, plus a $500 restoration deposit.

Where do I appeal a zoning decision?

To the Zoning Board of Adjustment, which meets at 7:30 p.m. on the last Tuesday of the month at the Civic Center, 24 Union Boulevard.

Do I need to register a rental house?

Yes, for a one-unit rental or a two-unit house you do not live in: file the landlord identity registration statement with the Borough Clerk.

How much is a building permit in Wallington?

The amount comes from the borough’s fee ordinance in the Borough Code rather than a posted table, so ask the Building Department for the figure on your plans; the state surcharge is added on top.

Can a road be opened on a Friday?

Not unless the borough specifically approves it; otherwise give Public Works and the construction office 24 hours’ notice and the police 48 hours.

How do I get copies of old permits?

Send an OPRA request to the Borough Clerk at the Civic Center, by e-mail or on the borough’s OPRA form.

Simplify Wallington Borough permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in New Jersey. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Wallington Borough sooner?

Let Alliance prepare, file, and track your Wallington Borough permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Wallington Borough permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.