The Borough of Wood-Ridge issues construction permits through its Construction Code Office, on the second floor of the Municipal Building at 85 Humboldt Street (201-939-5188). Chris Cunningham is the Construction Code Official, directs the office and also serves as electrical subcode official; appointments with him are recommended. Applications can be picked up from the rack by the office door whenever the building is open, permits are issued from 9 a.m. to 3 p.m., and inspections are scheduled by phone, Monday to Friday. When the Zoning Officer denies a plan, the case goes to the Planning Board.
What requires a building permit in Wood-Ridge?
The borough’s own advice is short: building permits are required for most work, and owners should call the Construction Code Office at 201-939-5188 before starting to find out whether their job needs one. The dividing line comes from the state Uniform Construction Code. Ordinary maintenance can be done with no permit at all; minor work needs a permit but may begin once the office has been notified; everything else waits until the permit is issued.
Construction permit
- New buildings, additions and second floors
- Decks, porches and renovations that change structure
- Electrical work under the electrical subcode
- Plumbing and gas piping
- Fire protection systems, alarms and sprinklers
- Heating, cooling and fuel-burning equipment
- Demolition
Borough land-use approvals
- Zoning review by the Zoning Officer against Chapter 530
- Planning Board variances and site plans
- Stormwater rules under Chapter 464
- Temporary trailers, containers and pods (allowed only on active construction sites)
Under Ordinance 2026-4, which amended section 530-48 of the zoning chapter in early 2026, office trailers, vehicles, storage or shipping containers and moving pods may sit on a construction site only while it is actively operating and only within the site itself; catering trucks may visit and park on the adjacent street to serve the crew.
What Wood-Ridge decides and what the state holds
The construction rules themselves are the state’s. Wood-Ridge controls who enforces them and the local land-use layer. Its Chapter 249, Uniform Construction Codes, was rewritten by Ordinance 2022-21 (adopted December 20, 2022) to rename the enforcing agency the “Construction Code Office”, made up of a Construction Code Official and subcode officials for building, plumbing, electrical and fire protection, with the option of contracting an on-site inspection agency in place of any subcode official. The office is to be open whenever Borough Hall is open to the public. Zoning sits in Chapter 530, amended in 2026 by Ordinance 2026-2 to add an affordable housing overlay zone and a new Article XVIII on affordable housing, and the borough’s Master Plan and Zoning Map are posted on the Construction Department page.
Short on time to read all of this?
Get a free quote →Wood-Ridge building department: who handles permitting
The Construction Code Office is the only permit office for construction in Wood-Ridge. DCA’s roster (as of September 2, 2026) lists the borough’s own officials for the construction official, building, electrical, plumbing and fire protection posts and shows no private agency or DCA office in any of them; the elevator line is blank, so ask the office who reviews elevator and lift work before you file. One official covers building and plumbing, another fire protection, and the Construction Code Official handles electrical work himself. The office also has a Zoning Officer, a Property Maintenance Officer and a technical assistant, and the Construction Code Official answers planning questions.
| Detail | Information |
|---|---|
| Office | Construction Code Office, second floor, Municipal Building, 85 Humboldt Street, Wood-Ridge, NJ 07075 |
| Phone / fax | 201-939-5188 / 201-939-4425 (Borough Hall main line 201-939-0202, option 2) |
| Permit hours | Permits issued 9 a.m. to 3 p.m.; applications on the rack whenever the building is open |
| Construction Code Official | Chris Cunningham (also electrical subcode official); appointments recommended |
| Inspections | Monday to Friday, by phone at 201-939-5188 |
| Fire Prevention Bureau | Uniform Fire Code inspections by the fire official and state-certified inspectors |
Wood-Ridge permit types
Wood-Ridge uses the state UCC application: the construction permit jacket naming the owner, the contractor and the work, plus the technical section for each subcode the job touches. Blank applications sit on the rack by the office door, and the office will tell you which sections your project needs when you call or visit.
Residential permits
- Additions and second stories. Most go through the Zoning Officer first. In 2026 the Planning Board heard several house additions that the Zoning Officer had denied, for reasons such as enlarging a non-conforming front, rear or side setback, going over the 30% maximum building coverage in the R1 zone, adding to a house that already exceeded the height limit, or placing a wrap-around deck where it was not permitted.
- Fences and walls on corner lots. Ordinance 2024-8 (adopted April 17, 2024) rewrote section 530-32G: on a corner lot one street line is designated the front lot line, and no wall or fence may go in that front yard unless the fence rules specifically allow it. A fence may run along the second street line only if that line does not adjoin a neighbor’s front yard; if it does, the fence must stay at least 12 feet back from that street line.
- Alterations and systems. Kitchens, baths, basements, boilers, furnaces, water heaters and electrical service changes go on the same jacket with the matching technical sections.
Not sure this scope needs a permit?
Get a free quote →Building or remodeling a home here? Alliance handles residential permit filing, so the crew isn't waiting on the counter.
Commercial permits
Store fit-outs, offices and mixed-use buildings follow the same application, and many go to the Planning Board first: recent board cases include auto body, car dealership, salon and pet-care businesses. Food businesses also need a food establishment license from the borough’s Health Department. Parts of the Wesmont Station Redevelopment Area carry their own financial agreements adopted by ordinance (for example Ordinances 2020-10 and 2020-11). The Fire Prevention Bureau, whose inspectors are certified by the state Division of Fire Safety, inspects commercial and industrial buildings and enforces the Uniform Fire Code in every building except owner-occupied one- and two-family homes.
For tenant improvements and new commercial builds, Alliance handles commercial permit expediting through issuance. More on this: commercial building permits explained.
What comes before the construction permit
- Zoning. The Zoning Officer reviews the plan against Chapter 530 and the bulk schedule. A denial is written up as a notice of application to the Planning Board, listing each reason. Since Ordinance 2024-8, Construction Code Office officials and inspectors, fire inspectors, property maintenance officers, police officers and the Borough Engineer also act as special assistant zoning officers under the Zoning Officer’s direction, so zoning problems can be flagged at any inspection.
- Planning Board. In 2026 the board meets at 7 p.m. at Borough Hall, 85 Humboldt Street, generally on the first Tuesday of the month (June 9 is the exception, and no November date is scheduled). Applications are posted on the board’s page by meeting date, and the board has its own engineer and planner under 2026 contracts.
- Soil and stormwater. Disturbing more than 5,000 square feet requires a soil erosion and sediment control plan certified by the Bergen County Soil Conservation District; the borough’s stormwater rules are in Chapter 464.
- County roads. Bergen County reviews site plans, subdivisions and residential driveways on county roads through its GeoCivix portal, and digging between the curbs of a county road needs a county road opening permit from the Operations Division (201-336-7678).
- Health. A Bergen County Health Department sanitary inspector is in the borough every Wednesday from 8:30 a.m. to 4 p.m.; the Borough Council sits as the Board of Health.
Rather talk it over?
Call 1-855-478-4290 →Wood-Ridge permit costs and fees
Construction permit fees in Wood-Ridge are fixed in Chapter 249 of the Borough Code, which the borough publishes on eCode360 rather than as a fee sheet on its website. No new Chapter 249 fee ordinance appears among the borough’s 2025 and 2026 legal notices or posted ordinances. Call the Construction Code Office for the fee on your plans before you file; the plan review portion is paid with the application and credited against the permit fee under state rules, and the state surcharge (N.J.A.C. 5:23-4.19) is added on top.
| Item | Amount |
|---|---|
| Planning Board application for a house addition (notices 2026-72A and 2026-74A) | $400 fee + $1,750 escrow |
| Planning Board application for a renovation affecting building height (notice 2026-73A) | $300 fee + $1,500 escrow |
| Building, electrical, plumbing and fire protection permits | Chapter 249 fee schedule; quoted by the Construction Code Office |
| State surcharge | Added to construction permits under N.J.A.C. 5:23-4.19 |
The Planning Board figures are what the board’s posted notices showed for those cases, not a full fee schedule, so ask the board secretary what your own application will need.
Trade permits and who may pull them
Trade work is permitted through the technical section for each subcode on the same application. In Wood-Ridge, electrical work is reviewed and inspected by the Construction Code Official in his role as electrical subcode official; plumbing goes to the official who also holds the building subcode; fire alarms and sprinklers go to the fire protection subcode official. Each inspects only their own trade.
- State licenses. Electrical contractors, master plumbers and HVACR contractors are licensed by the state.
- Contractor registration. New Jersey has no general-contractor license; home improvement contractors register with the Division of Consumer Affairs and builders of new homes register with DCA. Owners working on their own home are exempt from registration.
- Fire code. Separately from the construction permit, the Fire Prevention Bureau’s certified inspectors check commercial, industrial and multi-family buildings for Uniform Fire Code compliance.
Rather not deal with the Wood-Ridge Borough building department?
Get a free quote →How to apply for a Wood-Ridge building permit
Phone 201-939-5188, or book an appointment with the Construction Code Official, to confirm what permits and zoning review the job needs.
Have the Zoning Officer check the plan against Chapter 530; if denied, file with the Planning Board.
Pay the board fee and escrow and attend the 7 p.m. hearing; the board’s resolution becomes a prior approval.
Take the UCC jacket and technical sections from the rack by the office door.
Return the completed sections with construction drawings and any county or soil district approvals.
Permits are issued between 9 a.m. and 3 p.m.; pay the fee and keep the permit and approved plans on site.
Review, corrections and what causes delay
Each subcode official reviews their own section, and under N.J.A.C. 5:23-2.16 a complete application must be approved or denied within 20 business days. In the borough’s 2026 records the hold-ups that show up are zoning ones: setback, coverage and height problems send house additions to the Planning Board, which meets once a month. A decision on a construction code question can be appealed to the Bergen County Construction Board of Appeals.
Inspections and certificates in Wood-Ridge
Inspections run Monday through Friday and are booked by calling the Construction Code Office at 201-939-5188. State rules ask for at least 24 hours’ notice, and on one- and two-family homes work stops for the required inspections, beginning with the footing trenches and the foundation before backfill; a new house also needs a foundation location survey. Each subcode official signs off their own work before walls are closed and at the final.
When the finals pass, the Construction Code Official issues a certificate of occupancy for a new building or a certificate of approval for altered space; do not move into new space before it is issued. Home sellers and landlords of one- and two-family homes should also plan for the smoke and carbon monoxide alarm certificate the state fire code requires before a sale or new tenancy; Wood-Ridge’s pages do not describe it, so ask the Fire Prevention Bureau what it checks, what it costs and how it is scheduled.
New Jersey building code in Wood-Ridge
Wood-Ridge enforces the state Uniform Construction Code through its Construction Code Office under Chapter 249 of the Borough Code; the 2022 rewrite also lets the Mayor and Council add a deputy construction code official, deputy subcode officials and assistant inspectors, and the Construction Code Official reports to the Borough Administrator on office matters and to DCA’s Division of Codes and Standards on code matters. FEMA’s Community Status Book lists Wood-Ridge (community 340083) as participating in the National Flood Insurance Program, with flood maps effective August 28, 2019.
Want this handled start to finish?
Get a free quote →New Jersey has one Uniform Construction Code for every municipality; the town supplies the enforcing agency, the fee ordinance and the zoning approvals. New Jersey rules
Wood-Ridge permit search and official resources
To get copies of permits, plans or certificates, make an Open Public Records Act request to the borough at Borough Hall, 85 Humboldt Street (main line 201-939-0202). Planning Board applications for each meeting, and many adopted ordinances, are posted as PDFs on the borough’s site.
- Wood-Ridge Construction Department
- Ordinance 2022-21, Chapter 249 Uniform Construction Codes
- Planning Board applications
- Planning Board 2026 meeting dates (Resolution 2026-2BR)
- Wood-Ridge zoning map
- Wood-Ridge Master Plan
- Ordinance 2026-4, portable structures and construction sites
- Borough ordinances
- Legal notices
- Fire Prevention Bureau
- Health Department
- Bergen County Planning and Engineering
- Bergen County Construction Board of Appeals
- DCA roster of local construction offices
- FEMA Community Status Book, New Jersey
Inspections are where schedules slip.
Get a free quote →Wood-Ridge building permit FAQs
Where is the Wood-Ridge building department?
The Construction Code Office is on the second floor of the Municipal Building, 85 Humboldt Street; call 201-939-5188.
When are permits issued?
Between 9 a.m. and 3 p.m.; blank applications are on the rack by the office door whenever the building is open.
Who is the Construction Code Official?
Chris Cunningham, who also serves as electrical subcode official. Appointments with him are recommended.
What happens if zoning denies my addition?
The Zoning Officer lists the reasons on a notice of application, and you take it to the Planning Board, which meets at 7 p.m., usually on the first Tuesday of the month.
How much does a Planning Board application cost?
Recent house-addition cases posted by the board carried a $300 or $400 fee plus a $1,500 or $1,750 escrow.
Can I put a fence along the side street of my corner lot?
Yes, unless that street line adjoins a neighbor’s front yard; then the fence must stay at least 12 feet back from it (section 530-32G).
How do I schedule an inspection?
Call 201-939-5188; inspections are done Monday through Friday.
Can I park a storage pod or trailer at my job?
Only on an active construction site and within the site itself, under section 530-48 as amended in 2026.
Simplify Wood-Ridge Borough permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in New Jersey. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Wood-Ridge Borough sooner?
Let Alliance prepare, file, and track your Wood-Ridge Borough permits while your crew stays on the job.
More New Jersey permitting guides
Bergen County
Read guide →Wyckoff Township
Read guide →Bergenfield Borough
Read guide →Woodbridge Building Permit Guide
Read guide →Woodbury City Building Permit Guide
Read guide →Woodland Park Borough Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Wood-Ridge Borough permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.