Municipal GuideNew JerseyPaterson · Passaic County

Paterson Building Permit — Filed & Tracked For You

Paterson will not issue a construction permit until the Tax Collector certifies that the property's municipal taxes are current — and it adds a debris disposal fee to every permit, with proof of licensed disposal due before the certificate of occupancy.

Scope: City of PatersonCode route: New Jersey Uniform Construction Code (N.J.A.C. 5:23)Trades: State licensed
Authority
Division of Community ImprovementsUniform Construction Code office
Counter
111 BroadwayOne office location by ordinance
Before issuance
Tax Collector certificationTaxes and assessments current
Demolition
Historic Preservation Commission approvalCitywide, regardless of district

Paterson's Division of Community Improvements enforces the Uniform Construction Code from a single office at 111 Broadway, and Chapter 183 of the city code attaches two conditions the state code does not: before a construction permit issues, the applicant files a certification from the Tax Collector that all municipal taxes and assessments on the property are paid and current, and every permit carries a twenty-dollar safe disposal fee for debris, with documentation of disposal at a licensed facility filed before the certificate of occupancy.

The city's four municipal historic districts — Great Falls, Downtown Commercial, Eastside Park and Court House — add a third layer. The Historic Preservation Commission reviews building permit applications for exterior alterations in the districts and on designated landmarks, and every demolition in Paterson, wherever it stands, requires the commission's approval.

This guide covers the City of Paterson. Clifton, Passaic, Wayne and the rest of Passaic County's municipalities each run their own enforcing agency, and the county issues no construction permits.

📜

Two Chapter 183 conditions found late. The ordinance says the applicant shall file with the Construction Official a certification from the Tax Collector that municipal taxes and assessments are current before a permit issues, and that the permit fee is the sum of the subcode fees plus a twenty-dollar safe disposal fee for debris, paid before issuance — with proof of disposal at a licensed facility filed before the certificate of occupancy.

What requires a building permit in Paterson?

New Jersey runs on a single statewide instrument, the Uniform Construction Code (N.J.A.C. 5:23), in force since January 1977 and administered by the Department of Community Affairs. Rather than writing its own code, the state adopts the national model codes as subcodes with New Jersey amendments: the International Building Code (building subcode), the International Residential Code for one- and two-family dwellings, the National Standard Plumbing Code — not the International Plumbing Code used in neighbouring states — the National Electrical Code, and the mechanical, fuel gas and energy codes. The 2024 editions of the I-codes and the NSPC, with the 2023 NEC, took effect on August 17, 2026 and replace the 2021 editions and the 2020 NEC; the usual six-month grace period lets an applicant file under either edition until roughly mid-February 2027. Under N.J.S.A. 52:27D-119 et seq. no municipality, Paterson included, may adopt different technical standards — what is local is the enforcing agency, the fee ordinance, the zoning approvals that precede the permit, and the certificates that follow it.

The UCC itself draws the exemption line. Ordinary maintenance under N.J.A.C. 5:23-2.7 needs no permit, no notice and no inspection; minor work under 5:23-2.17A needs a permit but may begin once the enforcing agency has been notified, with the application filed and inspected afterwards. Everything else waits for the issued permit.

Typically permit required

  • Exterior alterations in the Great Falls, Downtown Commercial, Eastside Park or Court House historic districts, reviewed by the Historic Preservation Commission
  • Every demolition in the city, which needs commission approval regardless of location
  • Signs and awnings, filed with the zoning permit application
  • New buildings, additions and any structural work on an existing building
  • Interior alterations that reconfigure space, add plumbing fixtures or extend circuits — renovation, alteration and reconstruction under the rehabilitation subcode
  • Decks, and sheds over 200 square feet, over ten feet tall or with any utility connection

Often exempt

  • Ordinary maintenance under N.J.A.C. 5:23-2.7 — though exterior changes in a historic district still go to the commission
  • Painting, wallpapering and interior finishes on less than a quarter of the wall area of a house
  • Like-for-like replacement of windows and doors in the same opening, and glass in any window or door
  • Roofing and siding replacement on a one- or two-family dwelling
  • Garden sheds up to 200 square feet and ten feet high with no utilities, and fences up to six feet — the zoning permit still applies to both

What is actually local, and what is not

Technical standards are the state's. Paterson's layer is the local enforcing agency — the construction official and the building, electrical, plumbing and fire subcode officials, each licensed by the state under N.J.A.C. 5:23-5 — plus the municipal fee ordinance, the zoning officer's sign-off, and the Tax Collector's certification and the historic commission's review that Chapter 183 and the preservation ordinance place ahead of the permit.

Who handles permitting in Paterson?

The Division of Community Improvements is the enforcing agency; its building, electrical, plumbing and fire inspectors are licensed by the Department of Community Affairs and issue permits, inspect, and issue certificates of occupancy and continued certificates of occupancy. The zoning officer issues the zoning permit that precedes the construction permit, and the Historic Preservation Commission advises the Planning Board and Zoning Board and reviews permit applications in the districts.

Paterson permitting contact
DetailInformation
DepartmentCity of Paterson Division of Community Improvements — Uniform Construction Code office
Office111 Broadway, Paterson, NJ 07505
Phone(973) 321-1232
HoursMonday to Friday, 8:30 am to 4:30 pm
Before issuanceTax Collector certification that taxes and assessments are current
Historic Preservation CommissionStaff at (973) 321-1220; meets monthly at City Hall, 155 Market Street

Permit types

Residential permits

A Paterson house project takes a zoning permit from the zoning officer first, then files the state UCC jacket at 111 Broadway with the tax certification. Contractors put the home improvement registration number on the application. In a historic district the commission reviews exterior work against the district's design guidelines before the permit, and a rental property in a mixed commercial building carries the city's re-rental inspection.

How New Jersey contractor credentials work

New Jersey has no state general contractor license. What it has instead is a registration that doubles as a permit gate: a home improvement contractor business must be registered with the Division of Consumer Affairs under the Contractors' Registration Act (N.J.S.A. 56:8-136 et seq.), and N.J.A.C. 5:23-2.15(b)8 requires the registration number on the construction permit application — an enforcing agency may not issue a home improvement permit to an unregistered contractor. Registration now carries commercial general liability insurance of at least five hundred thousand dollars per occurrence, workers' compensation cover and a tiered compliance bond, and the 2024 Home Improvement and Home Elevation Contractor Licensing Act is phasing in individual licensing through a new state board. New construction is different: a new-home builder registers with the Department of Community Affairs under the New Home Warranty and Builders' Registration Act and shows the builder registration card at permit. Electrical contractors, master plumbers and HVACR contractors hold separate state licenses from Consumer Affairs boards. Owners working on their own home are exempt from registration, and Paterson licenses no trades of its own.

Commercial permits

Commercial work in Paterson files the zoning permit and, where the Planning Board or Zoning Board is involved, carries the commission's advice on the application. Chapter 183 prices new construction by building volume with a stated minimum, the fire subcode official issues permits for fire protection work, and a change of use needs a new certificate of occupancy after every subcode official has signed.

Prior approvals, subcode review and the twenty-day clock

A New Jersey construction permit is one application with technical sections — the state's UCC F100 jacket with building, electrical, plumbing, fire and mechanical subcode forms — and each subcode official reviews their own section. The permit cannot issue until the prior approvals are in hand: zoning or planning board approval under the Municipal Land Use Law is a separate track that precedes the construction permit, and where a project touches a county road or county drainage the county planning board signs off as well. Sites disturbing 5,000 square feet or more need soil erosion certification from the regional soil conservation district, and DEP approvals apply in flood hazard, wetland and coastal areas. In Paterson the Passaic River and its floodway shape the map: DEP flood hazard approvals apply along the river and the Great Falls, and the Passaic Valley Sewerage Commission signs off on connections. Once complete, N.J.A.C. 5:23-2.16 gives the enforcing agency twenty business days to approve or reject a complete application, with a written list of deficiencies on any rejection.

Paterson permit costs and fees

Fees follow Chapter 183 of the Paterson city code: the sum of the subcode fees plus the safe disposal fee, paid before the permit issues, with volume-based charges for new construction.

Paterson fee reference points
ItemFee or rule
Construction permitSum of the subcode fees plus a twenty-dollar safe disposal fee for debris
New constructionThree and four-tenths cents per cubic foot of building volume, with a fifty-dollar minimum
Temporary certificate of occupancyThirty-five dollars
Before issuanceTax Collector certification that municipal taxes and assessments are current
Before the certificateDocumentation that debris went to a licensed facility
State training feeAdded to every permit under N.J.A.C. 5:23-4.19
⚠️

The debris fee has a second half. The twenty dollars is the easy part. Chapter 183 also requires the applicant to file documentation with the Construction Official verifying that all debris has been disposed of at a licensed facility before a certificate of occupancy issues — keep the disposal receipts from the first dumpster.

Rather not deal with the building department?

We prepare, file and track the application through to issuance — including the fees above, the submittal package, and every correction the department comes back with.

Get a fixed quote →

Trade permits and who may pull them

Trade work is permitted through the same application under the electrical, plumbing, fire and mechanical subcode sections, and inspected by the subcode official for each.

Permit required

  • Fire protection work — a permit from the fire subcode official under Chapter 183
  • Electrical — state-licensed electrical contractor; electrical subcode section
  • Plumbing and gas piping — state-licensed master plumber; plumbing subcode section under the NSPC
  • HVAC and fuel-fired equipment — licensed HVACR contractor; mechanical or fire subcode section
  • Fire protection, alarms and sprinklers — fire subcode section, with fire official review

Typically exempt

  • Like-for-like fixture, receptacle, switch and light fixture replacement in the same location
  • Communications and low-voltage wiring in a house that does not penetrate a fire-rated assembly

How to apply for a Paterson building permit

1. Settle zoning first

A zoning permit or planning board approval under the Municipal Land Use Law precedes the construction permit.

2. Confirm the credential the permit needs

The home improvement registration number, or the new-home builder registration card, goes on the application.

3. Assemble the UCC jacket and subcode forms

One F100 application with the building, electrical, plumbing, fire and mechanical sections the scope requires, plus sealed plans where the UCC demands them.

4. Clear prior approvals

Soil conservation, county planning board, DEP or overlay agency sign-offs are attached before the permit can issue.

5. Pay on the municipal fee ordinance

Fees follow the local ordinance plus the state training fee surcharge, and are due before issuance.

6. Call inspections in sequence and close out

Footing to final under 5:23-2.18, then the certificate of occupancy or approval that closes the permit.

Review, corrections and what actually causes delay

Paterson reviews at one office and on the state's twenty-business-day clock. The items that stall applications here are the zoning permit not yet issued, a tax certification not yet obtained, and historic district work filed without the commission's review; the commission's monthly meeting calendar sets the pace for anything in the four districts.

Inspections in Paterson

N.J.A.C. 5:23-2.18 sets the inspection sequence statewide — bottom of footing trenches, foundation and backfill, rough framing, electrical and plumbing, insulation, and final — and the enforcing agency must inspect within three business days of the request. Work that passes final receives a certificate of occupancy for new buildings or changes of use, or a certificate of approval for everything else. Paterson's inspectors are licensed by the state and inspect by subcode; the certificate of occupancy waits for the debris disposal documentation as well as the final inspections, and continued certificates of occupancy are issued by the same division.

Paterson permit search and official resources

Frequently asked questions

What does Paterson require before a permit issues?

A certification from the Tax Collector that all municipal taxes and assessments on the property are paid and current, plus payment of the subcode fees and the twenty-dollar safe disposal fee.

Is there a fee for demolition debris?

Chapter 183 adds a twenty-dollar safe disposal fee to every construction permit, and requires documentation that debris went to a licensed facility before the certificate of occupancy.

Does every demolition go to the historic commission?

Yes. Paterson requires Historic Preservation Commission approval for all demolitions, regardless of whether the property is in a district.

Which districts trigger design review?

Great Falls, Downtown Commercial, Eastside Park and Court House, plus designated landmarks; exterior alterations are reviewed against the district design guidelines.

How is new construction priced?

By volume — three and four-tenths cents per cubic foot — with a fifty-dollar minimum, plus the other subcode fees and the state training fee.

Which code edition applies?

The New Jersey editions of the 2024 I-codes with the 2023 National Electrical Code and the 2024 National Standard Plumbing Code, effective August 17, 2026, with a six-month grace period during which the 2021 editions may still be used.

Simplify Paterson permitting with Alliance Permitting

Paterson's ordinance puts three things ahead of the permit that most applicants meet at the counter: the tax certification, the zoning permit and the commission's review. We assemble all three before filing at 111 Broadway and keep the disposal paperwork the certificate will need.

Ready to break ground in Paterson sooner?

Send us the scope and the parcel. We confirm the review path with the City of Paterson Division of Community Improvements, assemble the submittal, file it, and track it through issuance — corrections included.

More New Jersey permitting guides

This guide is provided by Alliance Permitting for general information about Paterson permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.

Expedite Your Permits Today!

Free Quote1-855-478-4290