To get a building permit in Neptune Township, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Neptune Township’s Construction Department at 25 Neptune Boulevard issues UCC permits through its SDL portal, charges under Ordinance 18-25, and its Code Enforcement office inspects every home that is sold or rented.

Authority: Neptune Township Construction DepartmentPhone: 732-988-5200Fee ordinance: No. 18-25 (2018)
Office
25 Neptune BoulevardMunicipal building, Neptune
Alterations
$42 per $1,000Up to $50,000 of work; lower rates above
Zoning permit
$35Not accepted by fax or email
Resale inspection
$150 per structurePlus $75 per extra unit (Code Enforcement)

Neptune Township’s Construction Department at 25 Neptune Boulevard (732-988-5200) is the UCC enforcing agency, led by Donald Clare as Director of Code and Construction, Construction Official and Electrical Subcode Official; DCA handles elevators. Permits are applied for through the township’s SDL portal after a $35 zoning permit and any other prior approvals, and fees follow Ordinance 18-25, adopted August 13, 2018. Ocean Grove’s historic district adds review by the Historic Preservation Commission, and every sale or new tenancy needs a Code Enforcement certificate of inspection.

What requires a building permit in Neptune Township?

Neptune’s fee ordinance shows the range of work the department permits: new buildings and additions, renovations and repairs, roofing and siding, pools and pool barriers, retaining walls, signs, fences over 6 feet, demolition, asbestos and lead abatement, moving a building, plumbing fixtures, heating and cooling equipment, gas piping, electrical devices and services, solar systems, EV chargers, sprinklers, alarms and fuel tanks. The state’s ordinary maintenance list (N.J.A.C. 5:23-2.7) needs no permit, and minor work (N.J.A.C. 5:23-2.17A) is permitted but may start after notice to the department.

Neptune-specific triggers

  • Any construction in a Special Flood Hazard Area needs a Floodplain Development Permit first
  • Exterior work in Ocean Grove needs Historic Preservation Commission approval
  • Raising a house needs a letter from JCP&L on power-line clearances
  • An oil-to-gas conversion needs a demolition permit for the oil tank before the gas permit

Zoning still applies

  • Zoning permits cover even interior remodeling, driveways, fences, sheds, solar panels and a new owner continuing a use
  • Historic district AC units, generators and exhaust fans are on the zoning form
  • Dumpsters and storage pods use a Code Enforcement permit

What Neptune decides and what the state holds

The code itself is the state’s. Neptune’s own rules are the construction fee schedule in Chapter XI section 11-1.3 (Ordinance 18-25), the Land Development Ordinance, whose Section 1102 requires a zoning permit before construction, occupancy or a change of use, the Flood Damage Prevention Ordinance 22-20, the Ocean Grove historic district rules, affordable housing (COAH) contribution fees, and the certificates of inspection that Code Enforcement issues on sales and rentals.

Neptune Township building department: who handles permitting

The Construction Department reviews plans, issues permits and inspects for the building, electrical, plumbing and fire subcodes. The township page names Donald Clare as Director of Code and Construction, Construction Official and Electrical Subcode Official, and he also serves as floodplain administrator. DCA’s roster as of September 2, 2026 matches: township officials hold the construction, building, electrical, fire protection and plumbing posts, and DCA is elevator subcode official, so elevator sections go to DCA’s Elevator Safety Unit (609-984-7833). Neptune City is a separate borough with its own office.

Short on time to read all of this?

Get a free quote →
Neptune Township permit contacts
OfficeContact
Construction Department25 Neptune Boulevard, Neptune, NJ 07753 (mail: PO Box 1125, Neptune, NJ 07754-1125); 732-988-5200, ext. 261 (department secretary); fax 732-988-0062
Director of Code and ConstructionDonald Clare, ext. 263
Inspection requests732-988-5200, ext. 260, 261 or 262
Zoning (Land Use Department)Zoning Officer, ext. 278; assistant, ext. 270
Historic Preservation CommissionLand Use Department, ext. 204
Township Engineer (grading)Ext. 228
Street openingsPublic Works, 732-775-8797

Neptune Township permit types

Permits are applied for through Neptune’s SDL construction portal or on the state forms: the F100 jacket with building, electrical, plumbing, fire and elevator sections, plus the certificate application (F270), chimney verification (F370), framing checklist (F390) and air barrier checklist (F392). The department’s instruction sheet asks for one original and three copies of each paper application, four in all.

Residential permits

  • Who may do the work: owners of owner-occupied homes may do their own work and prepare plans for a single-family house; otherwise home improvement registration covers most residential work and licensed contractors do electrical, plumbing and mechanical work. New single-family houses need a registered new-home builder.
  • Furnace and AC swaps: the township’s replacement form asks for the old and new BTU ratings and efficiency, or else heating and cooling loads, the duct layout and the maker’s specifications.
  • House raising: elevating a structure needs grading approval, a JCP&L clearance letter and, in a flood zone, a Floodplain Development Permit.

Commercial permits

Commercial projects use the same jacket and sections, often after a site plan from the Planning Board or variance relief from the Zoning Board of Adjustment; the township posts both application packages (updated February 2025). Commercial sales and rentals need their own Code Enforcement certificate of inspection.

On any project, residential or commercial, the department’s checklist asks for a plan to protect adjoining properties where a new foundation sits right next to an existing one, footings sit at different depths close together, or the new roof rises above the neighbor’s; no permit issues until that plan is filed.

Not sure this scope needs a permit?

Get a free quote →

What comes before the construction permit

  • Zoning permit ($35). Filed with the Land Use Department, not the Construction Department, with three copies of a land-surveyor survey or site plan and three sets of plans (four of each in the historic districts), coverage calculations for additions and accessory structures, and any board resolution with the approved plans. Both owner and applicant sign, and fax or email filings are not accepted.
  • Historic Preservation Commission. Exterior work in Ocean Grove needs a certificate of appropriateness.
  • Grading approval. The Township Engineer approves grading for new construction, additions, house raising, demolition, retaining walls and in-ground pools.
  • Flood, soil, state and county. Floodplain Development Permits are filed with the Construction Department; Freehold Soil Conservation District certification applies at 5,000 square feet of disturbance (732-683-8500); NJDEP CAFRA or wetlands permits where they apply; the Monmouth County Development Review Committee for projects affecting county roads or drainage.
  • Utilities and fees. Street opening permits from Public Works, the sewer connection application, and COAH contribution forms. Plans for the construction permit must match those used for every prior approval.

Neptune Township permit costs and fees

The department posts Ordinance 18-25, adopted August 13, 2018, as its current fee schedule. The basic permit fee is the sum of the subcode fees, with a $95 minimum per subcode; plan review is 10% of the new construction permit fee, and reviewing an amendment to released plans costs $65 an hour per subcode. Selected fees:

Neptune construction fees (Ordinance 18-25)
ItemFee
New buildings and additions$0.046 per cubic foot ($0.038 for F and S groups); minimum $250
Renovations and repairs$42 per $1,000 up to $50,000; $36 per $1,000 from $50,001 to $100,000; $31 per $1,000 above $100,000
Roofing or siding, one- and two-family$95 per structure
PoolsAbove-ground $110; in-ground $200 ($337 over 800 sq ft); barrier replacement $95
Fence over 6 feet / retaining wall (homes)$95 / $115 up to 550 sq ft, $235 above
Plumbing$27 per fixture; $115 per special device; furnace or boiler up to 250,000 BTU $100
Gas piping / home air conditioning$95 plus $20 per appliance / $90
Electrical devices$80 for the first 25; $35 for each further 25
Electrical service up to 200 amps$115
Solar / home EV charger$210 for the first 10 kW plus $85 per 20 kW / $86
Demolition$150 for houses and small structures; $200 others; $60 for sheds and garages without utilities
Certificate of occupancy12% of permit fees, minimum $60; change of use $300; continued CO $300
Lapsed permit / change of contractor10% of the original fee, minimum $95 / $95
State surcharge$0.00371 per cubic foot; $1.90 per $1,000 for other work

Rather talk it over?

Call 1-855-478-4290 →

Worked example: a $40,000 interior renovation carries a building fee of 40 × $42 = $1,680 and a state surcharge of 40 × $1.90 = $76. The plumbing and electrical sections are added separately, each at least $95. Fees are rounded to the nearest dollar.

Trade permits and who may pull them

Trade work goes on the state technical sections and is inspected by Neptune’s subcode officials; the Construction Official also holds the electrical post. New Jersey licenses electrical contractors, master plumbers and HVACR contractors and has no general contractor license; home improvement contractors register with the Division of Consumer Affairs.

  • Electrical: devices are priced in blocks of 25, and service, solar, generator and EV charger work is priced by rating.
  • Plumbing and mechanical: the plumbing subcode official also serves as mechanical inspector; furnaces, boilers, water heaters, gas piping, AC and mini-splits are priced in the plumbing part of the schedule.
  • Fire: sprinklers, detectors, fire alarm panels, gas fireplaces, flues and fuel tanks carry fire fees; tank removal is $95 under 2,000 gallons.
  • Owner exemption: owners of owner-occupied single-family homes may do their own electrical, plumbing and mechanical work.

How to apply for a Neptune Township building permit

1. Zoning first

File the $35 zoning permit with the Land Use Department, with surveys, plans and coverage figures.

2. Other prior approvals

HPC in Ocean Grove, grading from the Township Engineer, floodplain, soil district and sewer approvals as the job requires.

3. Prepare the UCC package

F100 jacket, technical sections, two sets of plans and the contractor’s registration or license number.

4. Apply through the portal

Submit through Neptune’s SDL construction portal, or on paper at 25 Neptune Boulevard.

5. Plan review and fees

Each subcode official reviews its section; pay the permit fee when it is issued.

6. Inspections and certificate

Call for inspections 24 hours ahead and close out with the CO checklist items.

Review, corrections and what causes delay

One hold-up the department’s checklist warns about is a mismatch: it requires the plans filed for the construction permit to be the same plans used for zoning, HPC and other prior approvals. Incomplete zoning applications are returned unprocessed. N.J.A.C. 5:23-2.16 gives the department 20 business days to act on a complete application.

Rather not deal with the building department?

Get a free quote →

Inspections and certificates in Neptune Township

Call 732-988-5200, ext. 260, 261 or 262 at least 24 hours before the inspection you want, with the address, block and lot, permit number, your name and phone number; inspections are made within three business days. On one- and two-family homes the sequence runs from footing trenches and the foundation (with a foundation location survey, plus a flood elevation certificate in a flood hazard area) through slabs, sheathing, rough trades, framing, insulation and finals, and the approved plans must be on site.

The certificate of occupancy checklist lists what may be needed before a CO: final approvals from every subcode, soil district and Township Engineer sign-offs, HPC approval, an as-built survey, a flood elevation certificate, new home warranty papers, the names and ages of occupants under 18, elevator or multiple dwelling registrations, sewer connection fees (with Ocean Grove Sewerage Authority approval where it applies), COAH fees and any outstanding fees or penalties.

Certificate of inspection at sale or rental

Code Enforcement inspects homes and businesses for every sale and change of occupancy, with online applications and the fees in its schedule updated October 18, 2022:

Neptune Code Enforcement certificate fees
CertificateFee
Sale or yearly rental, per structure$150 plus $75 per additional unit
Change of tenant$100
Transfer of title (no occupancy allowed)$85
Short-term summer / winter seasonal rental$500 plus $250 per unit / $250 plus $125 per unit
Re-inspection$50 plus $35 per additional unit
Late application (five business days or less)$50 more per inspection

The township’s 2026 requirements sheet covers smoke alarms, carbon monoxide alarms and fire extinguishers for these inspections, and an inspection outside business hours costs $150 for up to two hours.

New Jersey building code in Neptune Township

Neptune applies the statewide UCC: the 2024 I-codes, 2024 National Standard Plumbing Code and 2023 NEC since August 17, 2026, with the 2021 codes and 2020 NEC still accepted until February 17, 2027 for applications that are complete with all prior approvals. FEMA’s Community Status Book lists Neptune Township (community 340317) as participating in the National Flood Insurance Program, with maps effective June 15, 2022, and in the Community Rating System at class 6, a 20% flood insurance discount.

New Jersey has one Uniform Construction Code for every municipality; the town supplies the enforcing agency, the fee ordinance and the zoning approvals. New Jersey rules

Want this handled start to finish?

Get a free quote →

Neptune Township permit search and official resources

Permit status is followed through the township’s SDL construction portal. For flood information on a property, the township’s Forerunner site shows zones and elevations, and the floodplain administrator answers address-specific questions by email; formal zones come from FEMA’s map service.

Inspections are where schedules slip.

Get a free quote →

Neptune Township building permit FAQs

How much is a building permit in Neptune Township?

Renovations cost $42 per $1,000 of work up to $50,000, new space $0.046 per cubic foot, and each subcode has a $95 minimum under Ordinance 18-25; the state surcharge is added.

How much is a zoning permit?

$35, filed with the Land Use Department rather than the Construction Department; fax and email filings are not accepted.

Do I need HPC approval in Ocean Grove?

Yes, for exterior work; the Historic Preservation Commission application comes before the construction permit.

Is Neptune Township the same office as Neptune City?

No. Neptune City is a separate borough with its own construction office on West Sylvania Avenue.

What does a resale inspection cost?

A Code Enforcement certificate of inspection is $150 per structure plus $75 for each extra unit, and $50 more per inspection if you apply five or fewer business days before closing.

Can I raise my house in a flood zone?

Yes, with a Floodplain Development Permit, grading approval, a JCP&L clearance letter and the construction permit, and an elevation certificate at the end.

Can a homeowner do the work?

Owners of owner-occupied single-family homes may do their own work, including electrical, plumbing and mechanical, and prepare their own plans.

Simplify Neptune Township permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in New Jersey. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Neptune Township sooner?

Let Alliance prepare, file, and track your Neptune Township permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Neptune Township permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.