Skip to main content
Municipal GuideNew JerseyMiddle Township · Cape May County

Middle Township, New Jersey Building Permit Guide

To get a building permit in Middle Township, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Middle Township’s Construction Office at 10 South Boyd Street in Cape May Court House issues UCC permits, with Trinity Code Inspections, LLC holding the building, electrical, fire and plumbing subcode posts, and the township issues no certificate of occupancy when a home is sold or rented.

Authority: Middle Township Construction OfficePermit search: SDL portalPhone: (609) 465-8740
Authority
Township Construction OfficeSubcodes: Trinity Code Inspections; elevators: DCA
Zoning permit
$50New homes add $100 grading review
Home sales
No resale COCOs only for new buildings, additions, change of use
BCEGS
Class 3Residential and commercial

Construction permits in Middle Township come from the township Construction Office at 10 South Boyd Street, Cape May Court House ((609) 465-8740), open 8:30 a.m. to 4:00 p.m. on weekdays, where Daniel Speigel is the Construction Official. A $50 zoning permit is filed together with the construction application, plan review does not start until zoning is approved, and permits can be looked up on the township’s SDL portal. The township does not issue a certificate of occupancy for a sale or rental.

What requires a building permit in Middle Township?

Middle Township applies the Uniform Construction Code without local changes to its technical rules: new buildings, additions, reconstruction, alterations and the trade systems in them need permits; ordinary maintenance needs none; and minor work may begin after notice. The township’s own checklists show which projects carry extra paperwork here.

Construction Office

  • New homes, which follow the township’s new construction checklist
  • Additions, reconstruction and changes of use, which end with a certificate of occupancy
  • Demolition, and the elevation of an existing structure (demolition/elevation checklist)
  • Electrical, plumbing, fire and elevator work on the state subcode forms
  • Public pools, which need a yearly bonding and grounding inspection

Zoning Office

  • A zoning permit for construction, filed with the construction application
  • Fences, signs and storage containers, each on its own permit form
  • Bulkheads, on the township’s bulkhead application
  • Business changes and changes of use
  • Sewer connections, on the zoning and sewer packet

The construction office states plainly that a certificate of occupancy is issued only when a building is first built, when its use changes, or after a reconstruction or addition, as the UCC provides; there is no township CO or zoning certificate for the transfer of a property or business, or for renting one.

What Middle Township decides and what the state holds

The state sets the code. Middle Township decides who enforces it locally (a township construction official with a private inspection agency in the subcode posts), its fees, its zoning in Chapter 250, its development fees in Chapter 116, which Ordinance 1735-26 repealed and replaced on March 11, 2026, and local rules such as Chapter 179’s construction hours. The township reports a Building Code Effectiveness Grading classification of 3 for one- and two-family homes and 3 for commercial and industrial buildings, on a 1 to 10 scale where Class 1 represents exemplary code enforcement.

Middle Township building department: who handles permitting

The Construction Office is the township’s enforcing agency. DCA’s roster dated September 2, 2026 names Daniel Speigel as construction official and lists Trinity Code Inspections, LLC, a private on-site inspection agency, as the building, electrical, fire protection and plumbing subcode official, with the Department of Community Affairs as elevator subcode official. The roster prints Township Hall’s address, 33 Mechanic Street; the construction and zoning offices are at 10 South Boyd Street.

Short on time to read all of this?

Get a free quote →
Middle Township permit contacts
OfficeContact
Construction Office10 South Boyd Street, Cape May Court House, NJ 08210; (609) 465-8740; fax (609) 465-1343
HoursMonday to Friday, 8:30 a.m. to 4:00 p.m.; permit pick-up until 3:30 p.m.; closed holidays and the Friday after Thanksgiving
Construction OfficialDaniel Speigel
Subcode inspectionsTrinity Code Inspections, LLC (building, electrical, fire, plumbing); DCA (elevator)
Zoning Office10 South Boyd Street; (609) 465-8742
Township Hall33 Mechanic Street; (609) 465-8732
Sewer Utility sign-off(609) 465-8713

Middle Township permit types

The Construction Office links the state construction permit packet for the jacket and technical sections and posts its own checklists for each stage of a new house.

Residential permits

  • New homes. The new construction checklist asks for the zoning form and $150 fee, a grading and drainage plan with a driveway apron detail, a signed and sealed survey, the residential development (fair share housing) application, every subcode application, availability letters from Cape May County Health for septic or wells and from the township for sewer or water, two sets of signed and sealed plans, water, sewer and gas risers, HVAC and water heater specifications and an electrical and fire diagram. Where they apply, add the soil district certificate, an elevator application, the “Development Fee Application (Flood Zone)”, and NJDEP permits and plans.
  • Demolition and house raising. Release letters from the electric, gas, sewer, water, cable and phone companies, a state asbestos form where needed, and a copy of the letter sent to the neighbors.
  • Fences. A $25 zoning fence permit with the fence drawn on a survey of current conditions.

Commercial permits

Commercial projects use the same packet, and the checklists add a flood-proofing certificate for commercial buildings and, for multiple dwellings, the BHI registration certificate before the CO. Public pools at motels and condominium associations need a yearly electrical bonding and grounding inspection: $85 per pool, with a valid five-year bonding certificate from a New Jersey licensed electrician, completed before the pool opens and no later than July 1. Business changes, changes of use and signs go through the Zoning Office.

Not sure this scope needs a permit?

Get a free quote →

What comes before the construction permit

  • Zoning permit. $50, plus $100 for grading and drainage review on a new home and $25 to re-review a revised application. File it with the construction application; the Zoning Office has 10 business days once the file is complete, and construction review does not begin until zoning is approved. The packet needs a current sealed survey (the zoning officer may waive it for minor work), proof from the tax collector that taxes and sewer charges are current, and the owner’s certification about wetlands, with any NJDEP permit number.
  • Sewer connections. Filed in quadruplicate with the township Sewer Utility, with DEP approval and a road opening permit before the connection; the form covers 4-inch and 6-inch connections only.
  • Boards. Variances and site plans go to the Zoning Board or Planning Board; hearing notices must run in the Cape May County Herald at least 10 days before the hearing.
  • Soil disturbance. Over 5,000 square feet needs a DelAtlantic Soil Conservation District certificate (the checklists still use the former Cape Atlantic name; Mays Landing office, 609-625-3144).

Middle Township permit costs and fees

Construction (UCC) permit fees are set in the township code and calculated by the Construction Office for each application; the township site does not post that schedule, so call (609) 465-8740 for a figure. Zoning and land use fees are in section 218-47, posted by the Zoning Office in a 2025 revision, and development fees follow the township’s fair share housing rules.

Middle Township fees posted by the township
ItemFee
Zoning permit / revised zoning permit$50 / $25
Grading and drainage review (new homes) / site inspection$100 / $400
Fence permit / change-of-use zoning permit$25 / $25
Sign permit$50
Hardship variance$500 plus $1,500 escrow
Use variance, residential$400 per unit plus $1,500 escrow
Minor subdivision$500 plus $1,000 escrow
Informal review$300 plus $300 escrow
Public pool bonding inspection$85 per pool
Residential development fee (notice effective January 1, 2023)1.5% of equalized assessed value; 6% for units added by variance
Non-residential development fee2.5% of equalized assessed value

Rather talk it over?

Call 1-855-478-4290 →

The township’s development fee notice splits the payment: 50% of the estimated fee when the construction permit is issued, then the balance, as confirmed by the assessor after the final inspection request, at the certificate of occupancy. On March 11, 2026 the Township Committee adopted Ordinance 1735-26, which repealed and replaced Chapter 116 on development fees; the replacement text is not posted with the notice, so the 2023 rates may have changed, and the Zoning Office has the current figures. The state’s training fee surcharge is added to construction permits.

Trade permits and who may pull them

Electrical, plumbing and fire protection work is filed on the state subcode forms with the construction application. In Middle Township, Trinity Code Inspections, LLC holds the building, electrical, fire and plumbing subcode official posts under the township’s construction official, and DCA holds the elevator post.

  • Credentials. Home improvement contractors register with the Division of Consumer Affairs; new-home builders register with DCA, and the CO checklist asks for the original new home warranty; electrical contractors, master plumbers and HVACR contractors hold state licenses. Owners working on their own homes are exempt from registration but not from permits.
  • Plans. New homes need signed and sealed plans, riser diagrams for water, sewer and gas, and an electrical and fire diagram.
  • Piles. Where a house sits on piles, signed and sealed pile logs must reach the office before the footing inspection is scheduled.
  • Pools. The yearly public-pool inspection is done by the electrical inspector, and any unsafe wiring must be corrected by a licensed electrician, which may need UCC permits.

How to apply for a Middle Township building permit

1. Assemble zoning and construction together

The zoning permit application must be submitted with the construction permit application and all pre-approvals.

2. Clear taxes and sewer

Get the tax and sewer collector’s certification on the zoning packet; zoning is not accepted until both are current.

3. Prepare plans and surveys

Sealed survey, grading and drainage plan, and two sets of signed and sealed plans for a new home.

4. Add outside approvals

County health, sewer or water availability letters, the soil district certificate and any NJDEP permits.

5. File at 10 South Boyd Street

Pay the zoning fees with the application and the construction fee calculated by the office.

6. Pick up the permit

Permits can be picked up until 3:30 p.m.; the approved plans stay on site.

Rather not deal with the building department?

Get a free quote →

Review, corrections and what causes delay

The Zoning Office has 10 business days on a complete zoning application and the Construction Office 20 business days on the construction application, and the township’s packet notes that construction review does not begin until zoning is approved. Unpaid taxes or sewer charges, a missing wetlands certification, and new-construction files filed without the development fee certification required since January 1, 2023 are the township-specific causes of delay.

Inspections and certificates in Middle Township

Request inspections at least 24 hours ahead; the township performs them within three business days of the request. The sequence is footing (with signed and sealed pile logs first where piles are used), a foundation location and height survey approved by the zoning official before the foundation inspection, underground plumbing, electrical and fire, rough trades, sill plate, sheathing and strapping, insulation, and a final for every subcode, with intermediate inspections as needed. The framing inspection comes only after every other rough inspection has passed, and a complete set of approved plans must be on the job site.

Certificate of occupancy. The August 2025 CO checklist asks for a top-of-block foundation survey, the framing checklist, all approved inspections, state form F-270 with the final construction cost, the new home warranty, Cape May County Health compliance for septic or wells or township sewer and water sign-offs, an as-built survey with grading, the final zoning inspection and paid development fees, plus, where they apply, an as-built elevation certificate, a sealed pile log, the engineer’s final site inspection and the soil district certificate.

Noise and timing. Under Chapter 179, construction and demolition are limited to 7:00 a.m. to 8:00 p.m. in commercial districts and 8:00 a.m. to 8:00 p.m. in residential districts, and pile driving is banned in June, July and August except for bulkheads.

New Jersey building code in Middle Township

Middle Township enforces the Uniform Construction Code through its own office, with Trinity Code Inspections in four subcode posts and DCA for elevators. FEMA’s Community Status Book lists the township (community 340154) as participating in the National Flood Insurance Program, with flood maps dated October 5, 2017; where they apply, the township’s checklists call for an as-built elevation certificate before the CO and a “Development Fee Application (Flood Zone)” with a new home. The Pinelands Commission lists Middle Township inside the Pinelands National Reserve but not in the state-designated Pinelands Area, and NJDEP permits and plans are part of the new construction checklist where they apply.

New Jersey has one Uniform Construction Code for every municipality; the town supplies the enforcing agency, the fee ordinance and the zoning approvals. New Jersey rules

Want this handled start to finish?

Get a free quote →

Middle Township permit search and official resources

Middle Township’s permit records are searchable on its SDL portal by block and lot, street name, or permit and control number. Copies of documents not online can be requested from the Township Clerk at 33 Mechanic Street under the Open Public Records Act. Ordinance introductions and adoptions are posted on the township’s public notices page.

Inspections are where schedules slip.

Get a free quote →

Middle Township building permit FAQs

Do I need a certificate of occupancy to sell my house in Middle Township?

No. The township issues no CO or zoning certificate for a sale or rental; COs are issued only for new buildings, changes of use, reconstructions and additions.

Who does the inspections?

Trinity Code Inspections, LLC holds the building, electrical, fire and plumbing subcode posts, and DCA handles elevators.

How much is a zoning permit for a new house?

$50 for the zoning permit plus $100 for grading and drainage review, the $150 on the new construction checklist.

How quickly are inspections done?

Within three business days of a request made at least 24 hours ahead.

Can I look up a permit online?

Yes, on the township’s SDL portal, by block and lot, street or permit number.

Can piles be driven in summer?

No. Chapter 179 bans pile driving in June, July and August, except for bulkheads.

Where must a variance hearing be advertised?

Only in the Cape May County Herald, the township’s official newspaper, at least 10 days before the hearing; notices placed in any other paper are not accepted.

What does a fence permit cost?

$25, with the fence shown on a survey of current conditions.

Simplify Middle Township permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in New Jersey. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Middle Township sooner?

Let Alliance prepare, file, and track your Middle Township permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Middle Township permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.