Manville, New Jersey Building Permit Guide

To get a building permit in Manville, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Manville’s Code Enforcement Office in Borough Hall, 325 North Main Street, issues UCC permits under the borough’s 2023 construction fee ordinance, after zoning and, for some jobs, engineering approval.

Authority: Manville Code Enforcement OfficeFees: Ordinance 2023-1307 (Dec. 11, 2023)Phone: 908-725-9478
Alterations
$4 per $1,000$100 minimum, Ordinance 2023-1307
Inspections
908-448-8782Call with permit and block/lot; no voicemail booking
Home sale
$50 + smoke/CO from $45Home sale certificate and fire certificate
Flood
CRS class 5 (25%)NFIP community 340437, maps Nov. 4, 2016

In the Borough of Manville, the Code Enforcement Office at Borough Hall, 325 North Main Street (908-725-9478), administers the UCC and issues construction permits, with Frank LaGuarina as Construction Official; DCA covers elevators. Fees come from Ordinance 2023-1307, adopted December 11, 2023: alterations and repairs are $4 per $1,000 of cost with a $100 minimum, and new buildings $0.05 per cubic foot. A home sale needs a $50 home sale certificate and a smoke, carbon monoxide and extinguisher certificate.

What requires a building permit in Manville?

Manville names three kinds of permit: zoning and engineering permits, both enforcing borough ordinances, and the state UCC permit with its building, electrical, plumbing, fire and mechanical subcodes. Its construction guide says which a job needs. State rules exempt ordinary maintenance (N.J.A.C. 5:23-2.7) from permits entirely, while minor work (5:23-2.17A) needs a permit but may start once the office is notified.

Zoning plus UCC

  • Additions (zoning and all subcodes) and tenant fit-outs
  • Decks, garages, carports, ramps and signs (zoning and building)
  • New air conditioning (zoning, electrical and mechanical)
  • Generators and solar panels
  • Above-ground pools (zoning, building, electrical); in-ground pools also engineering and plumbing
  • Sheds over 200 square feet; gazebos over 200 square feet
  • Fences on a property with a pool
  • House lifts (zoning, engineering, building, utility disconnect)
  • Windows that are added, enlarged or removed

Zoning only, or no permit

  • Sheds of 200 square feet or less, fences without a pool, dumpsters and pods: zoning only
  • Roofing on a house: no permit (roof permits are for commercial buildings)
  • Siding on a single-family house: no permit unless it is polypropylene
  • Direct replacement of bathroom fixtures with no piping changes

Two job types catch owners out. Finishing a basement starts with confirming the property is not in a flood zone, and lawn sprinklers need a plumbing permit and a landscape irrigation license.

What the borough decides and what the state holds

The building code is the state’s. Manville sets the construction fees in Ordinance 2023-1307, the zoning fees in section 31-1203.3 (Ordinance 2023-1308), its floodplain management rules and flood hazard maps in Ordinance 2022-1285, the home sale certificate, fire safety rules in Ordinance 2023-1306, and rental registration under Ordinance 2020-1232.

Manville building department: who handles permitting

The Code Enforcement Office issues construction permits and inspects the work, and also enforces the borough’s property maintenance code. DCA’s roster as of September 2, 2026 lists borough officials in the construction, building, electrical, fire protection and plumbing posts and the Department of Community Affairs as elevator subcode official, at 325 North Main Street, phone 908-725-9478, fax 908-231-8620. Permit application forms are available from the office in Borough Hall.

Short on time to read all of this?

Get a free quote →
Manville permit contacts
OfficeContact
Code Enforcement OfficeBorough Hall, 325 North Main Street, Manville, NJ 08835; 908-725-9478 ext. 117; Monday to Friday 9:00 a.m. to 5:00 p.m.
Construction OfficialFrank LaGuarina, ext. 123
Inspection line908-448-8782
Bureau of Fire SafetyOffice of the Fire Marshal, 325 North Main Street; ext. 112
Property maintenance complaints908-448-8782, or report online through the borough’s SDL portal

Manville permit types

The borough uses the state’s UCC forms, with the folder and technical cards for each subcode. Most permits need two sets of signed and sealed plans from a licensed professional, and every zoning application needs a survey showing the lot’s current impervious coverage. The technical assistant can tell you what a particular job needs beyond the guide.

Residential permits

  • Pools. Zoning approval comes first, with a survey (applications without one are denied automatically); in-ground pools also need Engineering approval, and a lot with a well or septic system needs Somerset County Board of Health approval. An above-ground pool files the jacket, building and electrical cards and the maker’s booklet; an in-ground pool adds the plumbing card, a mechanical card for a gas heater and two sets of sealed plans from a New Jersey architect or engineer. The barrier must be at least 4 feet high, no more than 2 inches off the ground, unclimbable, with gates that open outward and self-close and latch.
  • Home elevations. The borough’s home elevation guide explains substantially damaged homes and the lift process, which needs zoning, engineering and building permits and a utility disconnect.
  • Driveways and sidewalks. Widening a driveway or cutting the curb or sidewalk needs zoning and Engineering approval.
  • Rentals. Landlords file the annual rental housing registration under Ordinance 2020-1232.

Commercial permits

A business moving into existing space files the 2024 commercial zoning application and the commercial continuing occupancy (CCO) application. The commercial zoning fee is $100 and covers mixed-use property, all signs including real estate signs, continuing occupancy, change of tenancy and permitted changes of use. The CCO certificate is $300, a commercial certificate of occupancy $2,000, and a tenant fit-out needs zoning and every UCC subcode. The CCO application (updated July 2023) must carry a copy of the zoning approval and, for food businesses, health department approval; it is signed off by the building, plumbing, electrical and fire inspectors, and it does not by itself allow anyone to move in or start construction. Businesses register non-life-hazard uses and apply for fire permits with the Bureau of Fire Safety.

Not sure this scope needs a permit?

Get a free quote →

What comes before the construction permit

  • Zoning. $25 for a residential application ($50 for solar), $100 for commercial, with the impervious coverage survey.
  • Engineering. In-ground pools, driveway widening, curb and sidewalk cuts, sidewalks, house lifts and cell towers. Digging in a borough street needs an excavation (road opening) permit: a $30 application fee, three copies of plans showing the section of street to be opened, a liability insurance certificate (at least $100,000 per person, $300,000 per accident and $50,000 property damage), and a performance guarantee set by the Borough Engineer, payable in cash or by certified check or replaced by a surety bond.
  • Flood rules. Ordinance 2022-1285 adopted the borough’s flood hazard maps and floodplain management rules and named a floodplain administrator, noting that Tropical Storm Ida flooded well beyond the FEMA maps; a basement project starts by confirming the lot is outside a flood zone.
  • Soil conservation. Land disturbance of 5,000 square feet or more is certified by the Somerset-Union Soil Conservation District, whose office is at 308 Milltown Road in Bridgewater (908-526-2701).
  • Health. Well and septic approvals come from the Somerset County Board of Health.

Manville permit costs and fees

Ordinance 2023-1307, introduced November 27, 2023 and adopted December 11, 2023, amends the 2001 construction fee ordinance (No. 2001-966). Every subcode carries a $100 minimum inspection charge. The main house rates (use groups R-3 and R-5) are below.

Manville construction fees, Ordinance 2023-1307 (houses)
WorkFee
New construction$0.05 per cubic foot ($250 minimum)
Renovations, alterations and repairs$4 per $1,000 of estimated cost ($100 minimum)
Roofing or siding (where a permit is needed)$3 per $1,000 ($100 minimum)
Deck / solar$200 flat (the ordinance also prints a $250 minimum) / $250
Shed up to 144 sq ft / 145 sq ft and up$100 / $150
Fence / accessory structure$100 / $125
Above-ground / in-ground pool (building)$125 / $500; electrical $100 / $200
Demolition (houses) / other buildings$500 / $3,000
Plumbing fixtures (R-5) / water heater (R-5)$30 each / $100
Electrical fixtures (R-5)$125 for the first 50, $35 per further 25
Electrical service 1–200 amps$150
Mechanical$85 base plus, for example, $110 water heater, $185 furnace, $125 air conditioner, $230 generator
Residential certificate of occupancy$150 per unit
Change of contractor / variation$100 / $500
Commercial continuing occupancy (CCO) / commercial CO$300 / $2,000
Road opening (excavation) permit application$30, plus the Engineer’s performance guarantee
Zoning (Ordinance 2023-1308)$25 residential, $50 residential solar, $100 commercial
State training surcharge (DCA)$1.90 per $1,000 of value, or $0.00371 per cubic foot of new building (N.J.A.C. 5:23-4.19)

Rather talk it over?

Call 1-855-478-4290 →

Worked example using the ordinance’s rates: a $30,000 kitchen renovation in a house is 30 × $4 = $120 in the building subcode, above the $100 minimum; the state training surcharge adds 30 × $1.90 = $57, and the electrical, plumbing and mechanical work is priced separately in its own subcode.

Trade permits and who may pull them

Each trade is filed on its technical card and inspected by Manville’s subcode official for it. The state licenses electrical contractors, master plumbers and HVACR contractors; there is no state general contractor license, but home improvement contractors register with the Division of Consumer Affairs and new-home builders with DCA, and owners working on their own home are exempt from registration.

  • Electrical covers car chargers (with a load calculation), generators, alarms, range hoods and pool bonding.
  • Plumbing covers piping changes, electric water heaters, lawn sprinklers and pool main drains; a direct fixture swap needs none.
  • Mechanical covers boilers, furnaces, gas piping and gas water heaters.
  • Fire covers chimney liners, fireplaces, sprinklers, kitchen hoods, alarm systems and fuel tank removal.
  • Elevators are DCA’s subcode in Manville.

Rather not deal with the building department?

Get a free quote →

How to apply for a Manville building permit

1. Look up the job in the construction guide

It shows whether you need zoning, engineering and which UCC subcodes.

2. File zoning first

Submit the zoning application with a survey showing current impervious coverage and the fee.

3. Get Engineering approval

Needed for in-ground pools, driveway and curb work, sidewalks and house lifts.

4. Complete the UCC folder

The jacket and technical cards, with two sets of signed and sealed plans where the job needs them.

5. Submit at Borough Hall

Deliver the package to the Code Enforcement Office, 325 North Main Street.

6. Pay and schedule

Pay the ordinance fees by check to the Borough of Manville and call the inspection line when work is ready.

Review, corrections and what causes delay

Under N.J.A.C. 5:23-2.16 the construction official must approve or deny a complete application within 20 business days. In Manville, several checks come before that clock starts: a zoning file without its impervious coverage survey, a pool without Engineering or county health approval, or a basement or addition on a lot that has to be checked against the flood maps and Ordinance 2022-1285.

Inspections and certificates in Manville

Call the office at 908-448-8782 with the permit number, the property address with block and lot, and the inspection type. Do not leave a voicemail asking for an inspection; leave your contact details and the office will call back to schedule it. Pools show the pattern: an above-ground pool needs only building and electrical finals, while an in-ground pool needs the building collar and final, electrical trench, bonding and final, plumbing main drain and final, and a pressure test and final for a gas heater. Failing to follow the pool steps brings multiple violations, the borough warns.

Selling or renting a home

The Bureau of Fire Safety enforces the smoke alarm, carbon monoxide alarm and portable fire extinguisher certificate on the sale or change of tenancy of a one- or two-family home, and in Manville the extinguisher is still part of the inspection under borough ordinance. The same application covers the borough’s certificate for home sale ($50), signed by a housing inspector and the Fire Marshal. Book the inspection by calling 908-725-9478 ext. 117. The fire certificate fee is $45 more than 10 business days before the change of occupant, $90 at four to 10 days and $161 under four, with $35 for a re-inspection; checks go to the Borough of Manville. Changing owners or tenants before the certificate is issued can bring penalties of up to $500 under the state fire code.

New Jersey building code in Manville

Manville’s own subcode officials apply the state UCC, except for elevators. The current editions, effective August 17, 2026, are the 2024 I-codes, the 2024 National Standard Plumbing Code and the 2023 NEC; a complete application with all prior approvals may use the 2021 codes and 2020 NEC through the grace period ending February 17, 2027. FEMA’s Community Status Book lists Manville (community 340437) as participating in the National Flood Insurance Program, with flood maps dated November 4, 2016 and a Community Rating System class 5 that gives a 25% insurance discount. The borough joined the program on February 15, 1978, and its flood page links river gauges for the Millstone and Raritan, the FEMA elevation certificate, the Somerset County Flood Mitigation Program and Blue Acres buyout applications.

Want this handled start to finish?

Get a free quote →

New Jersey has one Uniform Construction Code for every municipality; the town supplies the enforcing agency, the fee ordinance and the zoning approvals. New Jersey rules

Manville permit search and official resources

Ask the Code Enforcement Office about the permit history of a property; copies of permits, certificates and other borough records are requested from the Clerk’s Office on its Open Public Records Act request form.

Inspections are where schedules slip.

Get a free quote →

Manville building permit FAQs

How much is a building permit in Manville?

Alterations and repairs are $4 per $1,000 of estimated cost with a $100 minimum; new construction is $0.05 per cubic foot.

Do I need a permit for a new roof on my house?

No. Manville’s guide limits roof permits to commercial buildings; siding on a single-family house needs one only if it is polypropylene.

Does a shed need a permit?

Every shed needs zoning; a shed over 200 square feet also needs a building permit, priced at $150 for a house shed under the fee ordinance.

How do I schedule an inspection?

Call 908-448-8782 with the permit number, block and lot, and inspection type; voicemail requests are not booked.

What do I need to sell my house?

The $50 home sale certificate and the smoke, CO and fire extinguisher certificate ($45 if requested more than 10 business days ahead).

Can I finish my basement?

First confirm the property is not in a flood zone; then the job needs the UCC permits for the work.

Simplify Manville permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in New Jersey. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Manville sooner?

Let Alliance prepare, file, and track your Manville permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Manville permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.