In the Borough of Fort Lee, construction permits come from the Building Department at 1365 Inwood Terrace (201-592-3500 x1503), where Brian Ribarro serves as Construction Official and Zoning Officer. The borough holds every subcode post itself, so building, electrical, plumbing, fire protection and elevator work are all reviewed and inspected by borough staff. A home sale or new tenancy also needs a $100 Certificate of Compliance from the Fire Prevention Bureau, issued only after every open permit is closed.
What requires a building permit in Fort Lee?
Fort Lee’s Permit Requirements page approaches the question from the other side: it reprints the state’s ordinary maintenance list (N.J.A.C. 5:23-2.7) as the work you may do at home without a permit, notice or inspection, and treats everything else as a matter for the Building Department. The department warns that skipping a required permit can cost up to $2,000 per violation, and that unpermitted work may have to be removed and redone or returned to its earlier condition.
No permit (ordinary maintenance)
- Painting, wallpaper and vinyl wall covering; new drywall or plaster on less than 25% of the walls of a room in a one- or two-family home
- Windows and doors, including garage doors, replaced in the same opening without changing the framing
- Roof repairs up to 25% of the roof area, and siding repairs up to 25% of the exterior walls, in any 12 months
- Gutters, leaders, screens, trim, cabinets and flooring (carpet included in one- and two-family homes)
- New faucets, valves, traps and, in a single-family home, a like-for-like toilet, sink, tub or shower with no change to the piping
- Swapping a receptacle, switch or light fixture of 20 amps or less, battery smoke alarms and battery or plug-in CO alarms
Needs a permit
- Cutting into any wall or partition, or removing a beam or bearing support
- Any change to exits or egress windows beyond a same-size swap
- New, moved or altered water, gas, drain, waste or vent piping
- New or altered electrical wiring (communications wiring has its own limited exemption)
- Work that affects structural or fire safety, or makes a building less compliant
- Lead abatement work
The department’s own page also mentions fences, driveway paving and home sales among the jobs it handles, and the borough publishes separate forms for signs and facades, tree removal, sidewalks, road openings and outdoor cafés. The page itself says the maintenance list is not all-inclusive, so raise anything that is not on it with the department before work starts.
What Fort Lee decides and what the state holds
The technical rules come from the state Uniform Construction Code, which Fort Lee cannot change. What the borough controls is the enforcing agency itself, its construction fee ordinance in the Borough Code, zoning (the Construction Official doubles as Zoning Officer), the 2008 Signs and Facades Ordinance with its Sign Committee review, tree removal, sidewalk and road-opening permits, a Business Certificate of Occupancy for new or changed businesses, and the Certificate of Compliance that the Fire Prevention Bureau issues on sales and rentals.
Short on time to read all of this?
Get a free quote →Fort Lee building department: who handles permitting
The Borough of Fort Lee is its own enforcing agency. DCA’s Local Construction Contacts roster (as of September 2, 2026) shows the borough filling the construction official post and all five subcode posts (building, electrical, elevator, fire protection and plumbing) with its own officials, with no post held by the state or a private inspection agency. The department’s staff list adds separate electrical, fire, plumbing and elevator inspectors and two code enforcement officers.
| Detail | Information |
|---|---|
| Office | Building Department, 1365 Inwood Terrace, Fort Lee, NJ 07024 |
| Phone / fax | 201-592-3500 x1503 / 201-585-1563 |
| Hours | Monday to Friday, 8:30 a.m. to 4:00 p.m. |
| Construction Official and Zoning Officer | Brian Ribarro, 201-592-3500 x1025 |
| State roster listing | 309 Main Street (Borough Hall), 201-592-3500, fax 201-585-0621 |
| Borough Hall | 309 Main Street, Fort Lee, NJ 07024 |
The state roster still lists the Borough Hall address and an older fax number for the office; the borough’s own department page and its 2026 business occupancy form both give 1365 Inwood Terrace, so take plans there.
Fort Lee permit types
Fort Lee works from the state’s construction permit packet. The borough asks first-time applicants to watch its short instructional video and then download the packet from DCA’s construction permit forms page; the borough also posts its own copies of the construction permit jacket and the building, electrical, plumbing, fire protection and chimney verification technical sections, plus the application for a certificate.
Residential permits
- Alterations, additions and new homes go in on the jacket with each technical section the job needs. Framing is checked against the state framing checklist (UCC F390), which the builder fills in before the inspector signs off.
- Fuel-fired equipment replacements need the chimney verification form with the plumbing or fire section.
- Demolition follows the borough’s 2021 demolition requirements and the state demolition section, N.J.A.C. 5:23-2.34, both posted on the department page.
- Tree removal needs a borough permit at $75 per tree, with a survey marking each tree and its distance from the buildings, the tree expert’s details and a final inspection.
Building or remodeling a home here? Alliance handles residential permit filing, so the crew isn't waiting on the counter.
Commercial permits
A new business, a change of use or a change of owner needs a Business Certificate of Occupancy: the Zoning Officer first approves the use, then building, electrical and fire inspections follow, with Health Department approval where it applies; the fee is $250. Signs need a sign application ($150 per sign plus a $500 escrow for a single sign or $750 for a double sign), filed as a PDF on a disc or thumb drive or by e-mail, with renderings and photos of every side of the building and the neighboring storefronts. Capital letters may be no taller than 10 inches, lower-case letters 8 inches and logos 12 inches, and both the Sign Committee and the Construction Code Official sign the form. Outdoor cafés and sidewalk work have their own applications.
Not sure this scope needs a permit?
Get a free quote →For tenant improvements and new commercial builds, Alliance handles commercial permit expediting through issuance. More on this: commercial building permits explained.
What comes before the construction permit
- Zoning. The Construction Official is also the Zoning Officer, so zoning review happens in the same office; variances and site plans go to the Planning or Zoning Board, whose application forms are posted in the borough’s document center.
- County approvals. Site plans and subdivisions that need Bergen County Planning Board approval, and residential driveway permits on county roads, are filed through the county’s GeoCivix portal; any excavation between the curbs of a county road needs a county road opening permit from the Operations Division (201-336-7678).
- Soil erosion. Construction that disturbs more than 5,000 square feet needs a soil erosion and sediment control plan certified by the Bergen County Soil Conservation District.
- Borough street work. Sidewalk and road opening permits are separate borough forms.
Fort Lee permit costs and fees
Fort Lee’s construction (UCC) permit fees are set in the Borough Code, which is published on eCode360; the Building Department pages do not reprint the fee table, so the office at 201-592-3500 x1503 prices each application. Fees the borough does print on its own forms are below.
| Item | Fee |
|---|---|
| Sale Certificate of Compliance (Fire Prevention Bureau, form as of May 20, 2025) | $100; failed inspections cost extra |
| Annual registration of a non-owner-occupied rental unit (Ordinance 216-72) | $100 a year; an owner living in one unit of a two-family home is exempt |
| Business Certificate of Occupancy | $250 |
| Sign permit | $150 per sign, plus $500 escrow (single sign) or $750 (double sign) |
| Tree removal permit | $75 per tree |
| State training fee surcharge (N.J.A.C. 5:23-4.19) | Collected by the department on top of the borough fee |
Under the state rules, the plan review fee is a share of the permit fee paid when you apply and credited against the permit fee at issuance, and it is not refunded; the state surcharge is based on the cubic volume of new buildings and additions and on the cost of other work. The Certificate of Compliance form accepts credit cards (with a fee) or checks payable to the Borough of Fort Lee.
Rather talk it over?
Call 1-855-478-4290 →Trade permits and who may pull them
Trade work rides on the same construction permit as the building work: the electrical, plumbing and fire protection technical sections are attached to the jacket and each trade is inspected by Fort Lee’s own subcode staff. Fort Lee posts each of those sections separately on its Building Department page.
- Electrical: the electrical technical section, signed by a state-licensed electrical contractor; the borough has its own electrical subcode official and an electrical inspector.
- Plumbing and gas: the plumbing technical section from a state-licensed master plumber, with the chimney verification form when a boiler, furnace or water heater is replaced.
- Fire protection: sprinklers, alarms and suppression systems go on the fire protection section, reviewed by the fire subcode official.
- Elevators: the borough holds the elevator subcode post itself and lists an elevator inspector on staff.
New Jersey has no general contractor license. A home improvement contractor must be registered with the Division of Consumer Affairs and put that number on the application; a builder of new homes registers with DCA instead, and HVACR contractors hold a state license. An owner doing work on their own home does not need the contractor registration.
How to apply for a Fort Lee building permit
Compare the job with the ordinary maintenance list on the borough’s Permit Requirements page, and call x1503 if it is not clearly on it.
The borough’s instructional video walks through the forms; then download the construction permit packet from DCA’s site.
Get the Zoning Officer’s sign-off, any Planning or Zoning Board approval, county approvals for work on a county road and the soil district certification where land is disturbed.
Complete the construction permit jacket with the building, electrical, plumbing or fire sections, contractor registration or license numbers and the drawings the job calls for.
Bring the package to 1365 Inwood Terrace during office hours and pay the plan review fee the office assesses.
Pay the balance when the permit is released, keep the approved plans on site and do not cover any work before it is inspected.
Rather not deal with the building department?
Get a free quote →Review, corrections and what causes delay
The most common hold-ups are a missing prior approval (zoning, county or soil district), a technical section left off the jacket, and an unregistered contractor. Under the Uniform Construction Code the construction official, or the subcode official on a single-trade job, must grant or deny a complete application within 20 business days. Sign applications also need the Sign Committee’s signature before the Construction Code Official signs.
Inspections and certificates in Fort Lee
Inspections are arranged with the Building Department, which has its own building, electrical, plumbing, fire and elevator inspectors. State rules call for a written request at least 24 hours before the inspection is wanted. On framing jobs the builder completes the framing checklist (UCC F390) and the inspector initials and dates it. When the final inspections pass, the department issues a certificate of approval for alterations or a certificate of occupancy for a new building.
Selling or renting a home. Fort Lee requires a Certificate of Compliance from the Fire Prevention Bureau under Borough Ordinance 182-1 and N.J.A.C. 5:70-2.3 when a home is sold, and a rental version before a new tenant moves in. The fee is $100, the inspector arrives without a call or a fixed time, and no one may occupy the unit until the bureau approves it. The certificate is issued only after all open building permits are closed and borough taxes and fees are paid. Smoke alarm rules depend on the year the building was built (10-year sealed batteries for battery units, interconnected 110-volt alarms in newer homes), and CO alarms are required on every level, within 10 feet of sleeping areas, outside rooms with fuel-burning appliances and near an attached garage door; CO alarms over 5 years old must be replaced unless the maker allows longer.
The 2025 form says fire extinguishers are not required in one- and two-family homes, while apartments need an ABC unit within 10 feet of the kitchen unless the building has common-area extinguishers within 75 feet. The Building Department’s older housing inspection hints still list a mounted 5- to 10-pound ABC extinguisher, so a seller should ask which list the inspector will use. Tenants’ units must also be registered with the Rent Leveling Board within 60 days of the tenancy starting (Ordinance 324-14).
New Jersey building code in Fort Lee
Fort Lee enforces the statewide Uniform Construction Code through its own licensed officials. Since August 17, 2026 that means the 2024 I-codes, the 2024 National Standard Plumbing Code and the 2023 NEC; a complete application with all prior approvals may still be filed under the 2021 codes until February 17, 2027. FEMA’s Community Status Book lists Fort Lee (community 340035) as participating in the National Flood Insurance Program, with flood maps dated August 28, 2019.
New Jersey has one Uniform Construction Code for every municipality; the town supplies the enforcing agency, the fee ordinance and the zoning approvals. New Jersey rules
Want this handled start to finish?
Get a free quote →Fort Lee permit search and official resources
Past permits, certificates and plans are public records. Fort Lee takes Open Public Records Act requests through an online form on the borough website or on its printable OPRA form, both handled by the Borough Clerk at 309 Main Street. Construction appeals go to the Bergen County Construction Board of Appeals in Hackensack.
- Fort Lee Building Department
- Permit requirements and ordinary maintenance list
- DCA construction permit forms
- Framing checklist (UCC F390)
- Sign application
- Tree removal permit application
- Business Certificate of Occupancy application
- Certificate of Compliance application, sales
- Certificate of Compliance application, rentals
- Housing inspection helpful hints
- Planning and Zoning Board applications
- Borough forms
- OPRA request form
- Borough Code of Fort Lee (eCode360)
- DCA Local Construction Contacts roster
- DCA adopted codes
- Bergen County Planning & Engineering
- Bergen County Construction Board of Appeals
- NJ soil erosion and sediment control program
- FEMA Community Status Book, New Jersey
Inspections are where schedules slip.
Get a free quote →Fort Lee building permit FAQs
Where is the Fort Lee Building Department?
At 1365 Inwood Terrace, open Monday to Friday from 8:30 a.m. to 4:00 p.m.; call 201-592-3500 x1503.
Do I need a permit to replace windows in Fort Lee?
Not if each window or door goes into the same opening without changing the framing; that is ordinary maintenance under the state list the borough publishes.
What does it cost to sell a house in Fort Lee?
The Fire Prevention Bureau’s sale Certificate of Compliance costs $100, and it is issued only after every open building permit on the property is closed.
How much is a tree removal permit?
$75 per tree, with a survey showing each tree and where it sits in relation to the buildings.
What happens if I build without a permit?
The borough warns of penalties up to $2,000 per violation, and the work may have to be removed or redone.
What does a new business need before opening?
A $250 Business Certificate of Occupancy: zoning approval of the use, then building, electrical and fire inspections, and health approval where it applies.
Can I file a sign permit by e-mail?
Yes. The sign application may be e-mailed or delivered as a PDF on a disc or thumb drive, with photos of every side of the building.
Simplify Fort Lee permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in New Jersey. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Fort Lee sooner?
Let Alliance prepare, file, and track your Fort Lee permits while your crew stays on the job.
More New Jersey permitting guides
Bergen County
Read guide →Franklin Lakes Borough
Read guide →Garfield
Read guide →Franklin Township (Gloucester County) Building Permit Guide
Read guide →Franklin Township (Somerset) Building Permit Guide
Read guide →Freehold Township Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Fort Lee permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.