Fairview Borough, New Jersey Building Permit Guide

To get a building permit in Fairview Borough, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Fairview’s Building Department on the third floor of the Municipal Building, 59 Anderson Avenue, issues construction, zoning and dumpster permits and the certificates of occupancy needed for every sale, rental and business opening.

Authority: Fairview Building DepartmentPayment: Cash, check or money order (no cards)Phone: 201-943-5485
Authority
Building Department59 Anderson Ave., 3rd floor
Hours
8:30–1 and 2–4:30Monday to Friday
Resale CCO
$125Ordinance 11-4; notarized
Street dumpster
$50 for 3 days$25 a day after; 7-day max

In the Borough of Fairview, construction permits are issued by the Building Department on the third floor of the Municipal Building, 59 Anderson Avenue (201-943-5485), where Richard Bolan is Construction Official and Zoning Officer. The office is open weekdays from 8:30 a.m. to 1 p.m. and 2 to 4:30 p.m. and takes cash (exact change), checks or money orders, but no credit cards. A permit is valid for one year, and a certificate of occupancy is required for every resale, every rental and every business opening.

What requires a building permit in Fairview?

The Building Department handles construction permits for new buildings, alterations, demolitions and interior and exterior renovations, as well as zoning permits and street dumpster permits. Its own list of examples is a guideline rather than a full catalog, and the department’s standing advice is to call before starting any work.

Residential examples

  • Fences, walkways, driveways, sidewalks, patios and pavers
  • Pools and hot tubs or Jacuzzis
  • Decks and sheds
  • Building additions

Commercial examples

  • Signs
  • A new business, a change of tenancy or a change of ownership
  • A change of use
  • Building additions and lot alterations

Under the state Uniform Construction Code, ordinary maintenance such as painting or a like-for-like faucet swap needs no permit, and minor work can begin after the office is notified. Fairview’s list mixes construction-code work with items such as walkways, pavers and patios, which come to the same office because it also issues the borough’s zoning permits.

Working without a required permit is costly. The department says a notice of violation and order to pay a penalty goes to the property owner, starting at $2,000 and adding $2,000 for each week the violation stays open, and final inspections are required on all work or penalties follow.

What Fairview decides and what the state holds

The technical code is the state’s, and Fairview cannot alter it. The borough decides the enforcing agency, the fee ordinance in the Borough Code, zoning through its Land Use and Development Ordinance, dumpster permits, and the certificates of occupancy it requires under Ordinance 11-4 on resales, refinances and rentals, along with the business and rental certificates that every new or transferred business needs.

Fairview building department: who handles permitting

Fairview runs its own construction office. On DCA’s Local Construction Contacts roster (as of September 2, 2026) the construction official also holds the building subcode post, and borough officials hold the electrical, fire protection and plumbing posts; the roster leaves the elevator line blank, while the department’s own page names the private agency Municipal Inspection Corp. (201-437-6327) for elevators. The department page also lists a single official for both electrical and plumbing, where the roster shows two people, so confirm who will inspect your trade work when you file.

Short on time to read all of this?

Get a free quote →
Fairview Building Department contacts
DetailInformation
OfficeMunicipal Building, 59 Anderson Avenue, 3rd floor, Fairview, NJ 07022
Phone / fax201-943-5485 / 201-943-4057 (fax per DCA roster)
HoursMonday to Friday, 8:30 a.m. to 1 p.m. and 2 to 4:30 p.m.
Construction Official and Zoning OfficerRichard Bolan
Elevator inspectionsMunicipal Inspection Corp., 201-437-6327
Health Department201-943-3687

Fairview permit types

Fairview’s applications page carries the building jacket and building application, the electrical, plumbing and fire applications, a chimney verification form, the residential and commercial zoning applications, dumpster permits, the business certificate application and the resale, rental and refinance packets.

Residential permits

  • Additions, garages and an added level: the zoning application needs a current survey showing the work and building plans showing the building height.
  • Fences: the zoning application must state the fence height.
  • Generators, condensers and other ground equipment: must be drawn on the survey.
  • Retaining walls: show the top-of-wall height measured from the bottom of the wall.
  • Dumpsters: a permit is needed only when the container sits on the street; one kept in your driveway needs none.

The borough does not keep copies of residents’ surveys. The one from your closing papers, insurance or mortgage file may lack details a permit needs, so a new survey is sometimes necessary.

Commercial permits

Every new business, change of ownership and change of name starts with the same three steps. First, a zoning review package: a letter of intent giving the owner’s name and phone, the address, hours, number of employees, services, the prior use of the space and, for food service, the approved and proposed number of seats, plus an architect’s site plan with any off-street parking and an architect’s layout of the store. An incomplete package is returned on the spot. Second, the Zoning Officer decides whether the case needs variances from one of the boards. Third, the business completes the $250 business certificate application and the landlord completes and pays for a $75 rental certificate. Construction for the new business also needs one set of signed and sealed drawings.

The borough’s instructions continue from there. Interior renovations need every permit before work starts, sometimes with architect’s designs, and the instructions say all contractors must be licensed and that a business owner may not do the construction unless licensed. After the construction inspections, you schedule a rental certificate inspection through the office, and it must pass before the business opens. Food businesses must also satisfy the Health Department (201-943-3687) and hand in its satisfactory certificate before the business and rental certificates are released. A new store sign always needs its own permit: zoning review first, with before-and-after photos, a drawing showing all colors and dimensions (and the projection of an awning sign), mounting details and the measurements of the building front, then the permit application with two extra sets of the approved drawings. Opening without a valid business certificate brings fines or summonses.

Not sure this scope needs a permit?

Get a free quote →

What comes before the construction permit

  • Zoning permit. Issued by the same office, with the residential or commercial zoning application.
  • Planning Board. Adopts and amends the master plan and approves conditional uses; it meets in person at 7 p.m. in the Council Chambers on the second floor of Borough Hall unless posted otherwise.
  • Zoning Board of Adjustment. Hears variances from the zoning ordinance, which governs uses, conditional uses, parking, setbacks, signs and parcel size (its page calls it the board of “non-permitted uses”); meetings are scheduled for November 19 and December 17, 2026 at 7 p.m.
  • County and soil. County Planning Board reviews go through Bergen County’s GeoCivix portal, a dig in a county road needs a county road opening permit (201-336-7678), and more than 5,000 square feet of disturbance needs a certified soil erosion and sediment control plan.

Fairview permit costs and fees

Construction permit fees are set by the borough’s fee ordinance in the Borough Code (posted on eCode360); the Building Department page does not list them, so call 201-943-5485 for the amount on a given job. The fees the borough prints on its pages and forms are:

Fairview fees on borough pages and forms
ItemFee
Residential resale or refinance certificate of continued occupancy$125
Business certificate (paid by the business)$250
Rental certificate for a business tenancy (paid by the landlord)$75
Street dumpster permit$50 for the first three days, then $25 a day, up to 7 days
Work without a required permitPenalty from $2,000, plus $2,000 for each week the violation stays open
State training fee surcharge on construction permitsAdded to the borough fee

Rather talk it over?

Call 1-855-478-4290 →

A seven-day street dumpster costs $50 for days one to three plus 4 × $25 for days four to seven, or $150 in total. Fairview takes cash (exact change only), checks payable to the Borough of Fairview or money orders, and does not accept credit cards. Under the state rules the plan review fee is paid with the application, credited against the permit fee and not refunded.

Trade permits and who may pull them

Electrical, plumbing and fire work each has its own Fairview application, filed with the building jacket so that all parts of the job sit under one construction permit; a chimney verification form goes with any replacement of fuel-fired equipment. Each trade is inspected by the borough’s subcode official for that trade, and elevator work by Municipal Inspection Corp.

  • Electrical: a state-licensed electrical contractor signs the electrical application.
  • Plumbing and gas: a state-licensed master plumber files the plumbing application.
  • Fire protection: sprinkler, alarm and suppression work on the fire application.

Fairview treats obtaining a permit as a joint duty of owner and contractor: the contract should say who files the paperwork, picks up the permit and calls for inspections, but the owner is ultimately responsible for what happens on the property. New Jersey has no general contractor license; home improvement contractors register with the Division of Consumer Affairs, new-home builders with DCA, and owners doing their own work on their own homes are exempt from registration.

How to apply for a Fairview building permit

1. Call first

Phone 201-943-5485 to confirm whether the job needs a permit, a zoning permit or both.

2. Get a usable survey

Exterior work needs a current survey showing the proposed work, and additions need plans showing building height.

3. File the zoning application

The Zoning Officer reviews it and refers any variance to the Planning Board or Zoning Board of Adjustment.

4. Agree who files

Put in the contract whether you or the contractor submits the paperwork, collects the permit and calls for inspections.

5. Submit the jacket and applications

Bring the building jacket and the building, electrical, plumbing or fire applications to the third floor, avoiding the 1 to 2 p.m. lunch closure.

6. Pay without a card

Pay by exact cash, check or money order, then keep the permit on site.

Review, corrections and what causes delay

Incomplete zoning applications slow the review and may be refused, and an incomplete business package is handed straight back. The Uniform Construction Code gives the construction official 20 business days to act on a complete application, with zoning approval counted as part of a complete file. Two avoidable setbacks are arriving with only a card, since cards are refused, and relying on an old closing survey that lacks the detail the zoning review needs.

Rather not deal with the Fairview Borough building department?

Get a free quote →

Inspections and certificates in Fairview

Inspections cannot be booked for a specific time; the department says the volume of inspections means it cannot promise one. State rules require the request in writing at least 24 hours ahead. Final inspections are required on every permit, and a certificate of approval is issued once the work passes, showing it was done to code and inspected by a licensed subcode official. A permit lasts one year from issue and expires if the work is abandoned for more than six months.

Resales, refinances and rentals. Under Borough Ordinance 11-4, a certificate of continued occupancy is required whenever a property is sold or a new tenant moves in, and Fairview’s residential packet also covers refinances. The $125 application must be complete, with original notarized signatures and every page returned printed one-sided, plus a copy of the survey on a sale. It asks about solar panels or a generator, earlier board approvals, abandoned wells or septic tanks, smoke and CO detectors (which must be UL 217 approved), open permits and, in a tank affidavit, any oil tank and how it was removed or abandoned. If tenants stay after the sale, the seller must also buy rental certificates for every current tenant. Inspections take place on weekdays between 10 a.m. and noon once the paperwork and payment are in.

New Jersey building code in Fairview

Fairview enforces the statewide Uniform Construction Code with its own officials. The 2024 I-codes, 2024 National Standard Plumbing Code and 2023 NEC have applied since August 17, 2026; until February 17, 2027 a complete application with all prior approvals may still use the 2021 editions. FEMA’s Community Status Book lists Fairview (community 340034) as a participating National Flood Insurance Program community, with maps effective August 28, 2019.

New Jersey has one Uniform Construction Code for every municipality; the town supplies the enforcing agency, the fee ordinance and the zoning approvals. New Jersey rules

Fairview permit search and official resources

The Borough Clerk furnishes documents requested under the Open Public Records Act and posts an OPRA request form on the clerk’s page; use it to ask for copies of past permits, certificates or plans. The clerk also keeps the original ordinances and resolutions. Boundary disputes with a neighbor are a private legal matter for the county courts in Hackensack, not the Building Department. The applications page also carries the 2026 zoning map and an abandoned property registration form, and the clerk’s forms include a landlord identity registration form. The Fairview Health Department (201-943-3687) works with the nurses and health officials of the Bergen County Department of Health Services.

Want this handled start to finish?

Get a free quote →

Inspections are where schedules slip.

Get a free quote →

Fairview building permit FAQs

Do I need a permit for a fence or pavers in Fairview?

Yes. Fences, walkways, driveways, patios and pavers are on the borough’s list of residential work needing a permit; a fence application must give the height.

Can I pay for a Fairview permit by credit card?

No. The Building Department takes exact cash, checks payable to the Borough of Fairview or money orders.

How long is a Fairview permit valid?

One year from issue, and it expires if work stops for more than six months.

Do I need a permit for a dumpster?

Only if it sits on the street: $50 for the first three days and $25 for each extra day, up to seven days.

What does a resale certificate cost?

$125 for a residential resale or refinance, with a notarized application and the property survey.

What happens if I work without a permit?

The owner receives a penalty starting at $2,000, plus $2,000 for every week the violation remains open.

Can I book an inspection for a set time?

No. The department cannot guarantee specific inspection times.

Simplify Fairview Borough permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in New Jersey. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Fairview Borough sooner?

Let Alliance prepare, file, and track your Fairview Borough permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Fairview Borough permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.