Municipal GuideNew JerseyEdison Township · Middlesex County

Edison Building Permit — Filed & Tracked For You

Edison requires a continued certificate of occupancy before any building changes hands or changes occupancy — issued only after an inspection finds no open violations — and puts site plan approval in front of every building permit that is not a one- or two-family house.

Scope: Edison TownshipCode route: New Jersey Uniform Construction Code (N.J.A.C. 5:23)Trades: State licensed
Authority
Division of Construction Code EnforcementDepartment of Planning and Engineering
Counter
100 Municipal BoulevardEdison, NJ 08817
On sale
Continued certificate of occupancyChange of ownership or occupancy
Engineering
Inspection escrowFive percent of cost or five hundred dollars

Edison Township's Division of Construction Code Enforcement, in the Department of Planning and Engineering, is the enforcing agency for one of New Jersey's largest townships, and Chapter 14 of the township code adds a certificate the state code does not require: no building may be occupied or used in whole or part after a change in ownership or a change of occupancy until a continued certificate of occupancy has been issued, and the enforcing agency issues it only after an inspection finds no violations of any applicable law, ordinance or order pending.

The zoning code adds the second gate. Under Section 17.08.100, no building permit issues for a building, use or enlargement unless a site plan has first been submitted and approved — single-family and two-family dwellings and their accessory uses excepted — and no change of occupancy permit for a nonresidential use is authorised until the planning board committee has approved it, with landscaping, paving, fencing, lighting and facade work available as conditions.

This guide covers Edison Township. Woodbridge, Piscataway, Old Bridge and New Brunswick are separate Middlesex County municipalities with their own enforcing agencies, and Middlesex County issues no construction permits.

📜

Sales and changes of tenant have a certificate. Chapter 14 provides that a continued certificate of occupancy shall be applied for and obtained prior to the use or occupancy of the whole or any part of any building undergoing a change in ownership or a change of occupancy. For a turnkey business with no construction and no change of business category, the Building Division may accept the CCO application in place of the fuller certificate of occupancy — but it is inspected, and open violations block it.

What requires a building permit in Edison?

New Jersey runs on a single statewide instrument, the Uniform Construction Code (N.J.A.C. 5:23), in force since January 1977 and administered by the Department of Community Affairs. Rather than writing its own code, the state adopts the national model codes as subcodes with New Jersey amendments: the International Building Code (building subcode), the International Residential Code for one- and two-family dwellings, the National Standard Plumbing Code — not the International Plumbing Code used in neighbouring states — the National Electrical Code, and the mechanical, fuel gas and energy codes. The 2024 editions of the I-codes and the NSPC, with the 2023 NEC, took effect on August 17, 2026 and replace the 2021 editions and the 2020 NEC; the usual six-month grace period lets an applicant file under either edition until roughly mid-February 2027. Under N.J.S.A. 52:27D-119 et seq. no municipality, Edison included, may adopt different technical standards — what is local is the enforcing agency, the fee ordinance, the zoning approvals that precede the permit, and the certificates that follow it.

The UCC itself draws the exemption line. Ordinary maintenance under N.J.A.C. 5:23-2.7 needs no permit, no notice and no inspection; minor work under 5:23-2.17A needs a permit but may begin once the enforcing agency has been notified, with the application filed and inspected afterwards. Everything else waits for the issued permit.

Typically permit required

  • Any building, use or enlargement other than a one- or two-family house, which needs site plan approval under Section 17.08.100 before the building permit
  • Site work — parking, drainage, grading, landscaping — which needs a Site Improvement Permit from the Engineering Division with an inspection escrow posted
  • A new single-family house, reconstruction, or change or expansion of use, which files a sanitary sewer connection application with Engineering
  • New buildings, additions and any structural work on an existing building
  • Interior alterations that reconfigure space, add plumbing fixtures or extend circuits — renovation, alteration and reconstruction under the rehabilitation subcode
  • Decks, and sheds over 200 square feet, over ten feet tall or with any utility connection

Often exempt

  • Ordinary maintenance under N.J.A.C. 5:23-2.7 — though a change of ownership still triggers the continued certificate
  • Painting, wallpapering and interior finishes on less than a quarter of the wall area of a house
  • Like-for-like replacement of windows and doors in the same opening, and glass in any window or door
  • Roofing and siding replacement on a one- or two-family dwelling
  • Garden sheds up to 200 square feet and ten feet high with no utilities, and fences up to six feet — the zoning permit still applies to both

What is actually local, and what is not

Technical standards are the state's. Edison's layer is the local enforcing agency — the construction official and the building, electrical, plumbing and fire subcode officials, each licensed by the state under N.J.A.C. 5:23-5 — plus the municipal fee ordinance, the zoning officer's sign-off, and the continued certificate of occupancy that Chapter 14 attaches to every change of ownership and occupancy.

Who handles permitting in Edison?

The Division of Construction Code Enforcement is the enforcing agency, with the Construction Official and the building, electrical, plumbing and fire subcode officials reviewing their sections. The Engineering Division in the same department issues Site Improvement Permits, tree permits, soil import and export approvals and sanitary sewer connections, and inspects site work on two business days' notice. The Planning Board and its committee approve site plans and nonresidential changes of occupancy under Chapter 17.

Edison permitting contact
DetailInformation
DepartmentEdison Township Division of Construction Code Enforcement — Department of Planning and Engineering
OfficeMunicipal Complex, 100 Municipal Boulevard, Edison, NJ 08817
Phone(732) 248-7257
Engineering inspections(732) 248-7242, at least two business days ahead; inspections typically 8 am to 2 pm
On saleContinued certificate of occupancy before occupancy after a change of ownership or occupancy
Site planRequired before a building permit for anything other than a one- or two-family house

Permit types

Residential permits

A house project in Edison files the state UCC jacket in three signed copies with the subcode sections at 100 Municipal Boulevard, with zoning sign-off attached; single-family and two-family dwellings and their accessory structures are exempt from the site plan requirement. A new house, a reconstruction or an expansion of use also files the sanitary sewer connection application with Engineering, and a house that is sold needs the continued certificate of occupancy before the buyer occupies it.

How New Jersey contractor credentials work

New Jersey has no state general contractor license. What it has instead is a registration that doubles as a permit gate: a home improvement contractor business must be registered with the Division of Consumer Affairs under the Contractors' Registration Act (N.J.S.A. 56:8-136 et seq.), and N.J.A.C. 5:23-2.15(b)8 requires the registration number on the construction permit application — an enforcing agency may not issue a home improvement permit to an unregistered contractor. Registration now carries commercial general liability insurance of at least five hundred thousand dollars per occurrence, workers' compensation cover and a tiered compliance bond, and the 2024 Home Improvement and Home Elevation Contractor Licensing Act is phasing in individual licensing through a new state board. New construction is different: a new-home builder registers with the Department of Community Affairs under the New Home Warranty and Builders' Registration Act and shows the builder registration card at permit. Electrical contractors, master plumbers and HVACR contractors hold separate state licenses from Consumer Affairs boards. Owners working on their own home are exempt from registration, and Edison licenses no trades of its own.

Commercial permits

Commercial work in Edison starts with site plan approval under Section 17.08.100, then files for construction review; a nonresidential change of occupancy needs the planning board committee's approval before the certificate, and a turnkey tenant with no construction may be routed to the continued certificate instead. Site work carries a Site Improvement Permit with an engineering inspection escrow of five percent of the construction cost or five hundred dollars, whichever is greater, drawn down for plan revisions and inspection time.

Prior approvals, subcode review and the twenty-day clock

A New Jersey construction permit is one application with technical sections — the state's UCC F100 jacket with building, electrical, plumbing, fire and mechanical subcode forms — and each subcode official reviews their own section. The permit cannot issue until the prior approvals are in hand: zoning or planning board approval under the Municipal Land Use Law is a separate track that precedes the construction permit, and where a project touches a county road or county drainage the county planning board signs off as well. Sites disturbing 5,000 square feet or more need soil erosion certification from the regional soil conservation district, and DEP approvals apply in flood hazard, wetland and coastal areas. In Edison the Engineering Division's site improvement, tree, soil import and export and sewer connection approvals are prior approvals in their own right, and the Middlesex County planning board reviews frontage on county roads. Once complete, N.J.A.C. 5:23-2.16 gives the enforcing agency twenty business days to approve or reject a complete application, with a written list of deficiencies on any rejection.

Edison permit costs and fees

Construction fees follow the township's fee ordinance — by volume for new construction and additions, by estimated cost for alterations — plus the state training fee, with Engineering fees and escrows charged separately.

Edison fee reference points
ItemFee or rule
Construction permitBy cubic foot for new construction and additions, by thousand dollars of cost for alterations, plus the state training fee
Continued certificate of occupancyApplication and inspection fee on any change of ownership or occupancy
Certificate of occupancyFee on new buildings and changes of use, after all subcode finals
Engineering inspection escrowFive percent of the overall construction cost or five hundred dollars, whichever is greater
Site Improvement PermitEngineering Division fee, with plan revision and inspection time charged against the escrow
Sanitary sewer connectionApplication for new single-family homes, reconstructions and changes or expansions of use
⚠️

The escrow is a running account. Edison's engineering escrow is not a flat fee. It is posted at five percent of the overall cost of construction, or five hundred dollars, whichever is greater, and the Engineering Division charges plan revisions and inspection time against it — a project that revises its site plan twice will be asked to replenish before the final.

Rather not deal with the building department?

We prepare, file and track the application through to issuance — including the fees above, the submittal package, and every correction the department comes back with.

Get a fixed quote →

Trade permits and who may pull them

Trade work is permitted through the same application under the electrical, plumbing, fire and mechanical subcode sections, and inspected by the subcode official for each.

Permit required

  • Site improvements, grading and drainage — Engineering Division Site Improvement Permit with escrow
  • Electrical — state-licensed electrical contractor; electrical subcode section
  • Plumbing and gas piping — state-licensed master plumber; plumbing subcode section under the NSPC
  • HVAC and fuel-fired equipment — licensed HVACR contractor; mechanical or fire subcode section
  • Fire protection, alarms and sprinklers — fire subcode section, with fire official review

Typically exempt

  • Like-for-like fixture, receptacle, switch and light fixture replacement in the same location
  • Communications and low-voltage wiring in a house that does not penetrate a fire-rated assembly

How to apply for a Edison building permit

1. Settle zoning first

A zoning permit or planning board approval under the Municipal Land Use Law precedes the construction permit.

2. Confirm the credential the permit needs

The home improvement registration number, or the new-home builder registration card, goes on the application.

3. Assemble the UCC jacket and subcode forms

One F100 application with the building, electrical, plumbing, fire and mechanical sections the scope requires, plus sealed plans where the UCC demands them.

4. Clear prior approvals

Soil conservation, county planning board, DEP or overlay agency sign-offs are attached before the permit can issue.

5. Pay on the municipal fee ordinance

Fees follow the local ordinance plus the state training fee surcharge, and are due before issuance.

6. Call inspections in sequence and close out

Footing to final under 5:23-2.18, then the certificate of occupancy or approval that closes the permit.

Review, corrections and what actually causes delay

Edison reviews on the state's twenty-business-day clock and routes each application through Building, Planning and Engineering for completeness. What delays an Edison application is a site plan not yet approved where Section 17.08.100 requires one, a Site Improvement Permit filed after the building permit rather than before, and a nonresidential change of occupancy filed without the planning board committee's approval.

Inspections in Edison

N.J.A.C. 5:23-2.18 sets the inspection sequence statewide — bottom of footing trenches, foundation and backfill, rough framing, electrical and plumbing, insulation, and final — and the enforcing agency must inspect within three business days of the request. Work that passes final receives a certificate of occupancy for new buildings or changes of use, or a certificate of approval for everything else. Edison books construction inspections through the Division of Construction Code Enforcement and engineering inspections separately, by phone or in person at least two business days ahead, typically performed between 8 am and 2 pm; a continued certificate of occupancy carries its own inspection for open violations, and a certificate of occupancy is required before occupancy wherever site plan or subdivision approval was given.

Edison permit search and official resources

Frequently asked questions

Does Edison require a certificate when a house is sold?

Yes. Chapter 14 requires a continued certificate of occupancy before any building is used or occupied after a change in ownership or a change of occupancy, issued only after an inspection finds no pending violations.

Do I need site plan approval for a house?

No. Section 17.08.100 exempts single-family and two-family dwellings and their accessory uses; every other building, use or enlargement needs an approved site plan before the building permit.

What is the engineering escrow?

An inspection escrow posted with the Engineering Division at five percent of the overall construction cost or five hundred dollars, whichever is greater, charged for plan revisions and inspection time.

How do I book an engineering inspection?

Call (732) 248-7242 and leave a message, or come in person, at least two business days ahead; inspections are typically performed between 8 am and 2 pm.

Does a new business need a full certificate of occupancy?

Not always. A turnkey operation with no construction and no change of business category may be routed to a continued certificate of occupancy application instead; a nonresidential change of occupancy needs the planning board committee's approval.

Which code edition applies?

The New Jersey editions of the 2024 I-codes with the 2023 National Electrical Code and the 2024 National Standard Plumbing Code, effective August 17, 2026, with a six-month grace period during which the 2021 editions may still be used.

Simplify Edison permitting with Alliance Permitting

Edison layers three approvals most applicants meet one at a time: site plan, Site Improvement Permit with escrow, and the construction permit itself, with a continued certificate waiting at the end of any sale. We sequence them, post the escrow once, and track every inspection to the certificate.

Ready to break ground in Edison sooner?

Send us the scope and the parcel. We confirm the review path with the Edison Township Division of Construction Code Enforcement, assemble the submittal, file it, and track it through issuance — corrections included.