In Berkeley Heights Township, construction permits come from the Building Department at Town Hall, 29 Park Avenue; Joe Popolo is the Construction Official and Fire Official (908-464-2700 x2138). Most applications go to the Zoning Office first, which normally takes about 10 days, and to the Township Engineer when grading or drainage changes. The township wants one copy of each state form, collects half of any affordable housing development fee and the $7,318.03 sewer connection fee before a permit issues, and books inspections online in set time windows.
What requires a building permit in Berkeley Heights?
The township’s permit process page states that every project requires permits, and its project work matrix shows which offices each common job passes through. The state still draws the outer line: ordinary maintenance listed in N.J.A.C. 5:23-2.7 needs no permit, and minor work may begin once the office is notified.
Zoning and construction
- Additions and new buildings (zoning, engineering, all trades; certificate of occupancy)
- Decks, built patios and pergolas (paver or brick patios need zoning only)
- In-ground and above-ground pools (fence required)
- Sheds over 200 square feet
- Fences over 6 feet, and any fence that is a pool barrier
- Retaining walls over 4 feet (engineering too)
- Solar panels, with a letter confirming the homeowner’s contract
- Tenant fit-outs, with health review if food is served
Zoning or engineering only, or no permit
- Sheds of 100 square feet and under: zoning only
- Fences up to 6 feet: zoning only
- New or enlarged driveways: zoning and engineering
- Retaining walls under 4 feet: zoning and engineering
- Resurfacing a driveway: no permit
- Residential siding: no permit
- Dumpsters: no application, but never on the street
The matrix leaves sheds between 100 and 200 square feet unlisted; the state rule exempts garden sheds of 200 square feet or less, 10 feet or less in height and without utilities from the building permit, and the zoning permit applies at any size. The matrix also lists window and door work under the building subcode, while the state treats same-size window and door replacements as ordinary maintenance, so ask the department about your job.
What Berkeley Heights decides and what the state holds
The technical code is the state’s, and elevators are state-issued in the matrix, with DCA holding that subcode. The township decides its zoning (height, lot coverage, impervious surface, parking and setbacks), the Township Engineer’s grading and soil moving review, tree removal permits, the sewer connection fee and end user sewer agreements, the affordable housing development fee and its construction fee schedule.
Berkeley Heights building department: who handles permitting
The Building Department is the township’s enforcing agency; it reviews, processes, issues and inspects construction permits for every building in the community, and its inspectors are licensed by DCA in their disciplines. DCA’s Local Construction Contacts roster (as of September 2, 2026) lists Joseph Popolo as construction official and fire protection subcode official, other township officials for building, electrical and plumbing, and the Department of Community Affairs for elevators.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Building Department, Town Hall, 29 Park Avenue, Berkeley Heights, NJ 07922 |
| Construction Official and Fire Official | Joe Popolo, 908-464-2700 x2138 |
| Technical assistant | 908-464-2700 x2138 |
| Administrative assistant | 908-464-2700 x2120 |
| Zoning Officer (zoning and trees) | 908-464-2700 x2115; fax 908-464-3791 |
| Online services | SDL portal: permit search, payments, inspection scheduling and history |
| Board of Health | Town Hall; permits for food businesses and community pools |
Berkeley Heights permit types
Applications use the state construction permit jacket and whichever technical sections apply. DCA’s instructions ask for three copies; Berkeley Heights asks for one copy of each. A professional must complete the chimney verification form whenever a water heater or heating appliance is installed (the matrix requires it for any fuel-fired appliance in a one- or two-family home), and a homeowner who draws the plans or does their own plumbing or electrical work files the certification in lieu of oath.
Residential permits
- Additions and second floors. Zoning, engineering and every trade, plus the development fee: expanding the footprint or building up counts. Plans go to the Tax Assessor, and once the addition is assessed half of the estimated fee is paid before the permit is issued.
- Pools. Zoning and engineering approval, then building, electrical and plumbing sections; the Engineer may require a soil moving permit for an in-ground pool.
- Mechanical replacements. A replacement air conditioner or electric water heater needs the electrical and mechanical sections; a gas water heater needs the mechanical section and the chimney verification.
- Basements and kitchens. A finished basement needs zoning plus building and electrical sections; a kitchen remodel needs a building section and whichever trades the scope touches.
Building or remodeling a home here? Alliance handles home building permits, so the crew isn't waiting on the counter.
Commercial permits
Tenant fit-outs pass through zoning and take building, electrical, plumbing and fire sections, ending with a certificate of approval or continued occupancy; a food use adds Board of Health review. Commercial roofing and siding need building permits (with fire prevention review when hot tar or a torch is used on a roof), and rooftop HVAC replacements need electrical, plumbing and fire sections. Non-residential construction pays the 2.5% development fee unless exempt.
For tenant improvements and new commercial builds, Alliance handles commercial permit filing through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the construction permit
- Zoning. A current scaled survey showing existing conditions and every change, including grades, walls and paving, with plans or a manufacturer’s brochure; a homeowners’ association’s written permission or declaration of no jurisdiction where one exists. Variances go to the Zoning Board of Adjustment.
- Engineering. The Township Engineer approves grading and drainage plans before work starts; in-ground pools, detached garages and new homes may need soil moving permits, and landscape and retaining walls are reviewed for their effect on neighbors.
- Sewer. New connections pay $7,318.03 per EDU before the construction permit; large dischargers sign an end user sewer agreement first.
- Prior approval checklist. For new homes and larger jobs the department’s checklist runs through the soil district, any developer’s agreement and resolution compliance, a pre-construction lot grading plan under Ordinance 2025-35, septic design or well permit where used, the Union County road department on a county road, driveway plans, bonds and escrows, zoning or Board of Adjustment approval and NJDEP where needed, then the jacket and technical sections with copies of each contractor’s license, three sets of signed and sealed drawings, the energy compliance report, duct drawings, Manual S and J and the builder’s registration card.
- County and soil. The Union County Planning Board reviews site plans and subdivisions as they affect county roads and drainage (908-527-4268); see the Union County guide for county road openings. Disturbing more than 5,000 square feet needs certification from the Somerset-Union Soil Conservation District, 308 Milltown Road, Bridgewater (908-526-2701).
Berkeley Heights permit costs and fees
The construction fee schedule is in the township code, which the township publishes through an outside code library; ask the Building Department for the current schedule or the amount for your job before filing. The state permit surcharge is collected with it, and fees can be paid online through the SDL portal. The township does post these charges:
| Item | Fee |
|---|---|
| Zoning permit: shed | $40 |
| Zoning permit: fence | $50 up to 400 linear feet; $100 over 400 |
| Zoning permit: sign | $50 per sign |
| Tree removal (live trees) | $25 each for up to three a year; $75 each up to ten; $250 each after that |
| Sewer connection | $7,318.03 per EDU, before the construction permit |
| Tax map revision | $200 per lot (minor subdivision); $150 per lot up to $4,500 (major); $300 per encumbrance (site plans) |
| Development fee, residential | 1.5% of equalized assessed value; 6% bonus with a d(5) density variance |
| Development fee, non-residential | 2.5% of equalized assessed value |
Rather talk it over?
Call 1-855-478-4290 →Development fees after Ordinance 2026-04
The township’s building pages still describe the fee as Article 4.7, adopted November 6, 2017. Ordinance 2026-04, introduced February 17, 2026 and finally adopted March 3, 2026, repealed Article 4.7 and moved the development fee into Part 18 of the code at the same 1.5% residential, 6% bonus and 2.5% non-residential rates. The Tax Assessor estimates the equalized assessed value and confirms or adjusts it within 10 days of the final inspection; the additions page and project matrix say half is collected before the permit issues, and the balance is due at the certificate of occupancy. Removing a dead tree costs nothing once the township has inspected it.
Trade permits and who may pull them
Each trade is a technical section of the same application, reviewed before the project starts and inspected at set stages by its own subcode official. The Construction Official also holds the fire protection subcode, and elevators are issued by the state.
- Electrical. Service and panel work, transfer switches, car chargers and alterations need the electrical section from a state-licensed electrical contractor, unless a homeowner does the work on their own home and files the certification in lieu of oath.
- Plumbing. Licensed master plumbers file the plumbing section; lawn sprinklers need plumbing and engineering, and a new water softener needs plumbing.
- Mechanical. Residential furnace, boiler, A/C and water heater replacements use the mechanical inspection, with the chimney verification for fuel-fired units.
- Fire. Fire alarms (with an electrical section), suppression systems, new masonry and wood-burning fireplaces, and residential oil tank installation or removal involve the fire subcode; a wood-burning stove takes building and mechanical sections.
Home improvement contractors register with the Division of Consumer Affairs and new-home builders with DCA; a homeowner working on their own home is exempt from registration.
Rather not deal with the building department?
Get a free quote →How to apply for a Berkeley Heights building permit
See which offices your job needs: zoning, engineering, health, sewer and which construction sections.
File the zoning application with the survey and fee, on paper or online through SDL; review normally takes about 10 days.
Get grading and drainage approval, any soil moving permit, and pay the sewer connection fee on new connections.
The zoning form tells applicants to check with the Building Department after zoning approval.
Jacket, technical sections, chimney verification and plans; additions also go to the Tax Assessor for the development fee.
Pay half the development fee and the permit fee, then book inspections through SDL.
Review, corrections and what causes delay
The Building Department has 20 business days to review the application, plans and specifications and either approve them or send comments, and most applications reach it only after zoning has signed off. On an addition, the Tax Assessor’s estimate and the first half of the development fee come before the permit, and grading plans need the Township Engineer’s approval before work starts.
Inspections and certificates in Berkeley Heights
Inspections are scheduled online through the SDL portal. Inspectors may arrive at any time in the window, and the department gives no appointments or arrival calls. The windows are: building Monday to Friday, 10 a.m. to 2 p.m.; electrical Tuesday to Thursday, 1 to 4 p.m.; plumbing Monday to Thursday, noon to 4 p.m., and Friday, 7 to 11 a.m.; mechanical Tuesday and Wednesday, 9 a.m. to 2 p.m.; and fire Tuesday and Wednesday, 4 to 7 p.m. New buildings and additions end with a certificate of occupancy and most other work with a certificate of approval; tenant fit-outs may need a certificate of continued occupancy. Before a certificate of occupancy or temporary certificate, the department’s checklist looks for every subcode final, an as-built survey under Ordinance 2025-35, final engineering and flood sign-off where needed, sewer, water and health approvals, the soil district’s compliance certificate, the home warranty, duct leakage and air barrier results, and proof that the certificate fee, development fees and taxes are paid.
Selling or renting a home
Fire and smoke inspections for a change of occupancy are requested through the township’s own online fire and smoke inspection form, not the SDL portal; the Construction Official is also the township’s Fire Official. Ask the Fire Official at x2138 for the inspection fee. The township’s pages list no separate resale certificate of occupancy for houses.
New Jersey building code in Berkeley Heights
The department enforces the codes as DCA adopted them: the 2024 I-codes, the National Standard Plumbing Code and the 2023 NEC from August 17, 2026, with the 2021 codes and 2020 NEC allowed until February 17, 2027 for complete applications that have all prior approvals. Most code books can be read at the Berkeley Heights Public Library reference desk. FEMA’s Community Status Book lists the township (community 340459) as a participating flood insurance community with maps effective September 20, 2006, enrolled in the Community Rating System at class 10, which carries no premium discount.
Want this handled start to finish?
Get a free quote →New Jersey has one Uniform Construction Code for every municipality; the town supplies the enforcing agency, the fee ordinance and the zoning approvals. New Jersey rules
Berkeley Heights permit search and official resources
With a free SDL account, anyone can search Berkeley Heights permits by address, owner or block and lot, see inspection history, pay online and view zoning and property maps. Older files are requested on the township’s Open Public Records Act request page.
- Building Department
- Permit process
- Application forms
- Project work matrix
- Instruction sheets and checklists
- Prior approval checklist
- CO/TCO checklist
- Inspection schedule
- Check permit status online
- SDL portal
- Construction code regulations and fees
- Development fees for additions
- Ordinance 2026-04
- Zoning and tree inspections
- Zoning application
- Board of Health
- NJ soil conservation district directory
- DCA Local Construction Contacts roster
- DCA construction permit forms
- FEMA Community Status Book, New Jersey
Inspections are where schedules slip.
Get a free quote →Berkeley Heights building permit FAQs
Does an addition in Berkeley Heights carry an extra fee?
Yes. Additions that expand the footprint or add a floor pay the affordable housing development fee, half of the estimate before the permit issues.
How long does zoning review take?
Normally about 10 days; most construction applications reach the Building Department only after zoning approval.
Do I need a permit for a fence?
A zoning permit ($50 up to 400 linear feet); a building permit only for fences over 6 feet or pool barriers.
How do I schedule an inspection?
Online through the SDL portal; inspectors arrive within the set window for each trade, without appointments or arrival calls.
How many copies of the application do I file?
One copy of each form, although DCA’s instructions mention three.
Do I need a permit to remove a tree?
Yes, for a live tree over six inches in diameter on private property: $25 each for up to three a year, with replacement rules.
What does a new sewer connection cost?
$7,318.03 per EDU, paid in full before the construction permit is issued.
Simplify Berkeley Heights Township permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in New Jersey. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Berkeley Heights Township sooner?
Let Alliance prepare, file, and track your Berkeley Heights Township permits while your crew stays on the job.
More New Jersey permitting guides
Union County
Read guide →Clark Township
Read guide →Cranford Township
Read guide →Berkeley Township Building Permit Guide
Read guide →Bernards Township Building Permit Guide
Read guide →Bloomfield Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Berkeley Heights Township permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.