Inside Meridian, the Building & Inspection Division of the Community Development Department issues building, electrical, plumbing, mechanical and gas permits, and no permit is issued until a Site Development Request has been approved. A building permit is priced on project value under Code section 7-18, with plan review included: a $200,000 job pays $912, and the City asks for 30 days of plan review.
Who issues building permits in Meridian?
The Community Development Department, led by Director Terrell Thompson, runs the City’s permit counter through its Building & Inspection Division. The division enforces the zoning, building, flood, sign and address rules, issues the building and trade permits, inspects the work and issues the Certificate of Occupancy. Its Planning Division handles zoning, subdivisions and historic preservation, and the Building & Inspection staff also serve the Electrical Examining Board, the Mechanical Examining Board and the Building Code Board of Adjustments and Appeals.
| Detail | Information |
|---|---|
| Office | Building & Inspection, 723 23rd Avenue, Meridian, MS 39301 |
| Phone / fax | 601-485-1900 / 601-485-1983 |
| building_inspection@meridianms.org | |
| Hours | Monday–Friday, 7:30 a.m.–4:30 p.m. |
| Planning Division | 601-485-1910 (zoning, historic districts) |
Unincorporated Lauderdale County outside the city limits is handled by the county Permit Office at 2525 14th Street (601-484-3992), not by the City.
Meridian permit types and the Site Development Request
Every building permit is preceded by a Site Development Request (SDR). It is free, and the City will not authorize work or issue any other permit until the SDR is approved and signed by the Building Official. Building & Inspection routes it to Engineering, Code Enforcement, Fire Prevention and Planning for a concurrent review, then either returns comments, calls a Site Plan Review Committee meeting or approves it.
Short on time to read all of this?
Get a free quote →Needs an SDR
- New buildings, additions and renovations
- Demolition
- Manufactured homes and accessory structures
- Driveways and parking lots
- Grading, clearing, grubbing and tree removal
- Fences and retaining walls
- Utility additions and a change of occupancy use
Permits that follow
- Building permit (application and valuation)
- Electrical, plumbing, mechanical and gas permits, each filed by the licensed trade contractor
- Sign permit for commercial signs
- House moving permit
- Demolition permit
- Floodplain development permit and elevation certificate in a flood zone
The City allows one accessory structure per lot, none on a vacant lot, and power for it must come from the main building; a second meter is not allowed. Manufactured homes are limited to particular zoning districts, and in a designated historic district only as temporary emergency dwellings. A house move needs sign-off from the Police Chief, the Public Works Director and the Building Official, with at least 48 hours’ notice.
Meridian building permit fees
Building permit fees are set in section 7-18 of the Code of Ordinances, last amended by Ordinance 4598 on August 5, 2025, and plan review is included in the permit fee. Council minutes and agendas from July to October 2026 show no change to these fees.
| Project value | Fee |
|---|---|
| $100 or less | No fee unless an inspection is needed ($5 per inspection) |
| $101–$1,000 | $14.80 |
| $1,000–$50,000 | $24 for the first $1,000 plus $6 per additional $1,000 |
| $50,000–$100,000 | $312 for the first $50,000 plus $4.80 per additional $1,000 |
| $100,000–$500,000 | $552 for the first $100,000 plus $3.60 per additional $1,000 |
| Over $500,000 | $1,992 for the first $500,000 plus $2.40 per additional $1,000 |
| Moving a building | $50 |
| Demolition | $30 |
| Temporary power pole | $50 for the first 200 amps |
The code’s wording for the first band reaches $318 at $50,000, while the next band starts at $312; the City’s own fee table in its Construction Guidelines booklet charges $24 at $2,000, $72 at $10,000 and $312 at $50,000, so ask the Building & Inspection Division which figure applies to a job under $50,000. For example, a $200,000 project pays $552 plus 100 × $3.60, or $912. Starting work before the permit doubles the fee, and repeat offenders also face fines of $50, then $100–$200, then $350–$500. Renovating an existing building in the Meridian Downtown Historic District worth more than $100,000 (the tax assessor’s total value) halves the building and inspection fees.
Not sure this scope needs a permit?
Get a free quote →Electrical, plumbing, mechanical and gas permits in Meridian
The building permit does not cover electrical, plumbing, heating or gas work. Each trade contractor files its own permit, and under Code sections 7-3, 7-31 and 7-136 every electrical, plumbing, HVAC and mechanical contractor must hold a Mississippi State Board of Contractors licence for any project amount, residential or commercial. On commercial projects every contractor and subcontractor needs an MSBOC licence regardless of value. Contractors also register with the City: the mechanical board and the electrical examining board approve licences, the application fee is $50 and the annual licence is $100 for master trades or $25 for residential plumbers and electricians, and a bond must be posted.
| Permit | Fee |
|---|---|
| Electrical (sec. 7-158) | $10 plus $1 per designed amp of service (new or added) |
| Plumbing (sec. 7-74) | $10 plus $5 per fixture, water heater, sewer or water service; re-inspection $10 |
| Mechanical (sec. 7-52) | $10 plus $7–$50 per unit by tonnage or BTU; re-inspection $15 |
| Gas (sec. 7-92) | $10 plus $5 per outlet up to five, $3 per outlet over five; re-inspection $15 |
| Electrical final, repeat visits | $50 for the first, $100 for each later visit |
The City’s printed trade forms add a $1 records fee to each permit, and the gas form still shows $5 for each outlet over five; the code figure of $3 is the adopted rate. On commercial work where the trade contractor’s direct contract exceeds $10,000, the permit is issued only with a copy of the contractor’s Material Purchase Certificate. An electrical permit expires if work has not started within 90 days or stops for 60 days.
What Meridian asks for with a building permit
The Construction Guidelines booklet, revised March 25, 2025, lists what the contractor must provide for new construction, additions and renovations:
- The approved Site Development Request with its scaled site plan
- The Building Permit Application, showing the costs of plumbing, electrical and HVAC work and the total project amount
- A copy of the contractor’s MSBOC licence
- A $10,000 contractor bond on the City of Meridian bond form
- A certificate of liability insurance
- A complete set of plans, delivered at least two weeks ahead
- Flood information and an elevation certificate when the lot is in a flood zone
- Historic Preservation Commission approval when the site is in a historic district
- A Material Purchase Certificate, or proof of applying for one, for self-contracted commercial jobs over $10,000
Rather talk it over?
Call 1-855-478-4290 →The City says to allow 30 days for plan review, longer for complex projects. Demolition needs the SDR, the bond, insurance of at least $1,000,000, utility disconnections and a rubber-sealed sewer cap within 5 feet of the property line, which Code Enforcement inspects before it is covered.
How to get a Meridian building permit, step by step
Land outside the city limits goes to the Lauderdale County Permit Office instead.
Submit the free SDR form and a dimensioned site plan to Building & Inspection at 723 23rd Avenue and wait for the departments’ sign-off.
Apply for a Certificate of Appropriateness in the downtown historic district, and for a floodplain development permit in a mapped flood zone.
Hand in the application, plans, licence copy, $10,000 bond and insurance certificate at least two weeks ahead and allow about 30 days.
Pay the valuation-based fee; each licensed electrical, plumbing, mechanical and gas contractor then files a separate permit.
Request each inspection at least 24 hours ahead; the Building Official issues the Certificate of Occupancy after all finals pass.
Inspections and occupancy in Meridian
The general contractor is responsible for calling in every inspection at least 24 hours ahead, at 601-485-1900. Wiring must be seen by the electrical inspector before it is covered, and no system may be energized until the inspector has approved it. Building permits are valid for 180 days and can be extended while work continues.
No new or structurally altered building may be occupied until all final inspections are approved and the Certificate of Occupancy is issued. Before the finals, temporary power, water or gas can be connected at the Building Official’s discretion, but only in the general contractor’s name, and the contractor pays the water deposit and the water used until the Certificate of Occupancy is issued.
Rather not deal with the building department?
Get a free quote →Local Meridian rules that shape a project
Historic district and landmarks: Meridian has one locally designated district, the Meridian Downtown Historic District; six residential National Register districts have not been adopted locally. The code also designates every landmark and landmark site listed on the National Register of Historic Places in the city, and the Jerry and Selena Burton House at 1417 29th Avenue. For all of them, no exterior part of a building, fence, sign or above-ground utility may be built, altered, moved or demolished until the Meridian Historic Preservation Commission approves a Certificate of Appropriateness, and the City issues no building permit before that approval. The COA is required even for work that needs no building permit. The review fee is $20, and the Commission meets on the fourth Tuesday of each month at 4:00 p.m. at 723 23rd Avenue. Ordinary maintenance that does not change the design, material, color or appearance can be cleared by the Commission’s secretary.
Flood zones: a development permit is required before any development in a special flood hazard area. Under Chapter 10 of the Code, new and substantially improved homes and commercial buildings must have the lowest floor at least 1 foot above the base flood elevation; non-residential buildings may be floodproofed instead. The Building Official administers the flood rules, keeps the Flood Insurance Rate Maps and requires an elevation certificate for improvements in the flood hazard area. Meridian takes part in the Community Rating System, which the City says makes flood insurance 10% cheaper there.
Sprinklers in houses: the City has amended the code so that automatic sprinklers are not mandatory in one- and two-family dwellings.
Codes Meridian enforces
Meridian adopts its own codes in Chapter 7 of the Code of Ordinances. Ordinance 4595 of March 18, 2025 brought in the 2024 International Building, Mechanical and Plumbing Codes and the 2023 National Electrical Code, and the City lists the 2024 residential, existing building, fuel gas, property maintenance and fire codes as adopted. Section 7-91 names the fuel gas code as a “2025 edition”, while the City’s booklet lists the 2024 edition.
Want this handled start to finish?
Get a free quote →Some work is exempt statewide: farm structures once the owner files an affidavit (Mississippi Code §17-2-7), and manufactured housing built to federal standards, certain industrial and utility facilities, buildings on non-public fairgrounds and hunting or fishing camps with an owner’s affidavit (§17-2-9). None of these exemptions reaches floodplain rules. The state minimum codes are the Mississippi Building Code and Mississippi Residential Code, the residential code drawn from the 2021 International Residential Code. How building codes apply in Mississippi
Meridian permit FAQs
How much is a building permit in Meridian, MS?
It depends on project value: $312 at $50,000, $552 at $100,000 and $912 at $200,000, with plan review included. Trade permits are charged separately.
What is a Site Development Request?
A free City form, with a site plan, that Engineering, Code Enforcement, Fire Prevention and Planning review before any permit is issued. It covers new buildings, additions, demolition, driveways, parking lots, grading, tree removal, fences and changes of use.
How long does plan review take?
The City asks for plans at least two weeks ahead and says to allow 30 days for review.
Does my electrician need a state licence for a small job?
Yes. Meridian requires electrical, plumbing, HVAC and mechanical contractors to hold an MSBOC licence for any project amount, and they file their own permits.
Do I need approval to work on a downtown building?
Yes. In the Meridian Downtown Historic District, and on any National Register-listed landmark in the city, the Historic Preservation Commission must approve a Certificate of Appropriateness ($20 review fee) before the City issues a permit for exterior work.
How high must a new house be built in a Meridian flood zone?
The lowest floor, including any basement, must be at least 1 foot above the base flood elevation.
How long is a Meridian building permit good for?
180 days, and it can be extended while work continues.
Inspections are where schedules slip.
Get a free quote →Official Meridian permit resources
- Mississippi Insurance Department: Mississippi Uniform Building Codes
- Meridian Building & Inspection Division
- Meridian Community Development Department
- Meridian Construction Guidelines booklet (March 25, 2025)
- Meridian Site Development Request form
- Meridian building permit application
- Meridian electrical permit application
- Meridian plumbing permit application
- Meridian mechanical permit application
- Meridian gas permit application
- Meridian sign permit application
- Meridian flood protection information
- Meridian boards and commissions (Historic Preservation Commission)
- Meridian Code of Ordinances (Municode)
- Meridian City Council minutes
Simplify Meridian permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Mississippi. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Meridian sooner?
Let Alliance prepare, file, and track your Meridian permits while your crew stays on the job.
More Mississippi permitting guides
This guide is provided by Alliance Permitting for general information about Meridian permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.