In Longmeadow, the Building Commissioner, part of the Building, Planning and Community Development office in the municipal offices at 231 Maple Road, issues building permits and enforces both the State Building Code and the Zoning Bylaws; part-time inspectors handle wiring, plumbing and gas. Applications go in on paper at the office or online through the town’s PermitLink portal. House additions and alterations are priced in steps by project cost, from $55 for work up to $5,000 to $500 plus $10 per $1,000 above $100,000, and starting work without a permit doubles the fee.
What work requires a building permit in Longmeadow?
The Building Department’s own “When Permits Are Required” sheet is short and broad. It lists new construction and additions, repairs and alterations to existing buildings, and changes of use, then names the smaller jobs that residents most often ask about. Separate permits are required for all electrical, all plumbing and all gas fitting work.
Building permit
- New buildings, additions, repairs and alterations
- Change of use of an existing building
- Decks and porches
- Roofing, siding and windows
- Demolition
- Wood, pellet and other solid-fuel appliances
- Solar collectors
- Swimming pools
- Signs and wireless communication facilities
- Tents over 400 square feet
Also on the town’s list
- Fences: a $25 fence permit
- Sheds, detached garages and barns, priced on the fee schedule even under 200 square feet
- Sheet metal (ductwork) permits
- Moving a one- or two-family house
- Electrical, plumbing and gas work of any size
Pools carry an extra local rule: Chapter 265 of the general bylaws requires every pool to be enclosed by a fence that meets the State Building Code. The town publishes diagrams for fence placement on standard and corner lots, pool placement and frontage and setbacks, which are the quickest way to see where a structure may go before you draw a plot plan.
What Longmeadow decides and what the state holds
The building code itself is 780 CMR, written by the state Board of Building Regulations and Standards, and Longmeadow enforces it without local changes. What the town controls is set by Town Meeting or the Select Board: the fee schedule (amended by the Select Board on December 28, 2016 and revised June 15, 2022), the Stretch energy code in Chapter 135, demolition delay in Chapter 138, the wetlands bylaw in Chapter 304, the wells bylaw in Chapter 300 and the Zoning Bylaw. The Building Commissioner must be state-certified and also serves as the town’s chief zoning enforcement officer.
Longmeadow building department: who handles permitting
Paul Healy is the Building Commissioner. His office sits within Building, Planning and Community Development, which also staffs the Planning Board, Zoning Board of Appeals and Conservation Commission. The plumbing and gas inspector and the electrical inspector each have an alternate, and both work mornings only. Questions go to the Building Commissioner or the department’s administrative assistant at building@longmeadowma.gov.
Short on time to read all of this?
Get a free quote →| Item | Details |
|---|---|
| Office | Municipal offices, 231 Maple Road, Longmeadow, MA 01106 |
| Phone | 413-565-4153 (Building Commissioner and office); Associate Planner 413-565-4100 ext. 1323 |
| Office hours | Monday to Thursday 8:15 a.m. to 4:30 p.m.; Friday 8:15 a.m. to noon |
| Trade inspectors | Part-time; plumbing and gas, and electrical, mornings only |
| Online filing | PermitLink (“Online Permit Link” on the permitting portal page) |
| building@longmeadowma.gov |
Longmeadow permit types and application documents
Residential permits
For houses and two-family homes the fee schedule sorts work into new dwellings, additions and alterations (priced by project cost), roofing and siding on their own, accessory buildings, pools, solid-fuel appliances, solar and demolition. A roof replacement alone is a $55 permit; any repairs beyond the roofing fall under the additions and alterations rate. Building applications go in on paper at the office or through PermitLink; call or email first if you are unsure which permits apply. Since July 1, 2025 every permit payment is final: nothing is refunded if a project is cancelled, changes scope, never starts or is denied because the application was wrong or incomplete.
Building or remodeling a home here? Alliance handles residential permit applications, so the crew isn't waiting on the counter.
Commercial permits
Business, assembly, mercantile and multifamily buildings, including elderly housing and condominiums, pay at least $650 or $0.55 per square foot per floor for new construction. Commercial alterations follow the same cost steps as houses at higher rates ($75, $150, $455, and $650 plus $10 per $1,000 above $100,000). Commercial roofing is $110 minimum or $0.08 per square foot, demolition $200 minimum or $150 per 10,000 square feet, and wireless communication facilities $200 minimum or $10 per $1,000.
For tenant improvements and new commercial builds, Alliance handles commercial building permits through issuance. More on this: commercial building permits explained.
What comes before the building permit
The town’s Permitting Due Diligence Guide is a nine-question screen for the boards a project may need. In summary:
- Zoning: the Building Commissioner decides whether a project needs relief from the Zoning Board of Appeals (height, open space and similar). ZBA special permits, variances and findings cost a $150 filing fee, plus $50 and postage for certified notices to abutters within 300 feet and the actual cost of the newspaper notice. The Planning Board reviews exterior changes to a site or building (solar panels excepted), new roads and utility connections, and signs. Planning Board and ZBA applications need the required paper copies plus one digital copy, on the forms updated December 11, 2023, and are time-stamped by the Town Clerk.
- Historic District: alterations visible from a public way in the district around the Longmeadow Green need a certificate of appropriateness first.
- Demolition: pre-1901 structures go through the demolition delay bylaw.
- Wetlands: work within 100 feet of a wetland or 200 feet of a brook, stream or river starts with the Conservation Commission.
- Health and fire: public pools, food, personal-service and tobacco businesses go to the Board of Health; propane or hazardous-material storage to the Fire Department.
- Street and trees: the town publishes a right-of-way and tree-belt sheet and a street list for work near the road.
Not sure this scope needs a permit?
Get a free quote →Staff recommend a free preliminary meeting before any formal filing: book it with the Building Commissioner for building, electrical or plumbing questions, or with the Associate Planner for Planning Board projects. No plans are needed and nothing said there binds either side.
Longmeadow building permit fees
Fees come from the Building Department Fee Schedule, amended by the Select Board on December 28, 2016 and revised June 15, 2022. Most residential work is priced in fixed steps by project cost rather than a straight rate per $1,000; new houses and large accessory buildings are priced by floor area.
| Work | 1 & 2 family | Commercial |
|---|---|---|
| New dwelling (house) | $500 minimum or $0.55 per sq ft per floor | Business, assembly, multifamily: $650 minimum or $0.55 per sq ft per floor |
| Additions, repairs, alterations up to $5,000 | $55 | $75 |
| Over $5,000 | $110 | $150 |
| Over $35,000 | $350 | $455 |
| Over $100,000 | $500 for the first $100,000 plus $10 per $1,000 | $650 for the first $100,000 plus $10 per $1,000 |
| Accessory buildings (sheds, garages, barns) up to 600 sq ft; structures under 200 sq ft | $55 | $75 |
| Accessory buildings over 600 sq ft | $0.55 per sq ft per floor (as new construction) | Same |
| Swimming pools, in-ground or above-ground | $110 | $150 |
| Solar collectors | $110 | $150 |
| Roof replacement only; new siding only | $55; $55 | $110 minimum or $0.08 per sq ft; $75 |
| Solid-fuel appliances | $55 | $75 |
| Demolition | $55 | $200 minimum or $150 per 10,000 sq ft |
| Sheet metal | $55 | $55 minimum plus $5 per $1,000 |
| Tents of 400 sq ft and over | $55 | $100 |
| Signs; moving a 1 or 2 family home; fence permit | –; $100; $25 | $75; –; $25 |
| Large ground-mounted solar; wireless facilities | – | $10 per $1,000 of job value; $200 minimum or $10 per $1,000 |
Rather talk it over?
Call 1-855-478-4290 →Worked example. A $150,000 addition to a house is in the “over $100,000” step: $500 for the first $100,000, plus 50 × $10 for the remaining $50,000, or $1,000. A $20,000 bathroom remodel falls in the “over $5,000” step and costs a flat $110. Starting either job before the permit is issued doubles the fee.
Trade permits and who may pull them
Every electrical, plumbing and gas job needs its own permit from Longmeadow’s part-time inspectors, who administer the state electrical, plumbing and gas codes. Licensed electricians, plumbers and gas fitters file them; building work on houses needs a licensed construction supervisor and, on existing owner-occupied homes, a registered home improvement contractor, unless the owner uses the homeowner exemption. The trade fees sit on the same 2022 schedule:
| Permit | Fee |
|---|---|
| Electrical: new dwelling or condominium, per unit | $165 |
| Electrical: additions, repairs, alterations with a service change; without one | $165; $110 |
| Electrical: service change, temporary service or any one-inspection job | $55 |
| Electrical: solar panels | $110 residential; $165 commercial |
| Electrical or plumbing: multifamily and elderly housing | $165, plus $55 per inspection after the first 3 |
| Plumbing: new dwelling or condominium, per unit | $165 |
| Plumbing: additions and alterations | $110 residential; $165 commercial |
| Plumbing: repairs, replacement septic tanks, one-inspection work | $55 |
| Gas water heater or boiler, like for like or new upgrade (plumbing and gas together) | $110 ($55 each) |
| Gas: one-inspection work | $55 |
| Gas: fireplace, generator, grill; pool heater | $110 each |
Rather not deal with the building department?
Get a free quote →How to apply for a Longmeadow building permit
Answer the town’s nine questions on the historic district, pre-1901 buildings, wetlands, zoning relief, health, fire, roads and signs.
Optional and free; the Building Commissioner covers building and trade questions, the Associate Planner covers Planning Board review.
ZBA, Planning Board, Conservation Commission or Historic District Commission decisions come before the building permit where they apply.
Hand a paper copy to the office at 231 Maple Road or file through PermitLink, with plans and contractor license details.
Check the fee schedule first: since July 1, 2025 payments are final and are not refunded.
Your electrician, plumber and gas fitter each file a separate permit for their work.
Trade inspectors work mornings; call the office at 413-565-4153.
Review, corrections and what causes delay
780 CMR 105.3.1 gives the building official 30 days from the filing of an application to act on it. Applications in Longmeadow most often stall on approvals the permit depends on: a ZBA hearing with mailed and published notices, a Historic District Commission meeting (held monthly, with applications due 15 days ahead), a nine-month demolition delay, or a wetlands filing. Old Planning Board or ZBA forms are refused, so download them fresh.
Inspections in Longmeadow
Inspections are arranged through the Building, Planning and Community Development office at 413-565-4153. The gas and plumbing inspector and the electrical inspector are part-time and keep morning hours only, so trade inspections are booked into those mornings, and alternates cover both trades. Keep the permit card and approved plans on site for each visit. The Building Commissioner can order a building closed for non-compliance, and he is also the officer who answers written complaints about building or zoning violations: the town’s form goes to his office, he has 14 days to act and report back in writing, and either side may appeal his decision within 30 days.
Energy code and local bylaws in Longmeadow
Longmeadow is a Stretch energy code town. Chapter 135 of the general bylaws adopted the Stretch code at the May 7, 2013 Annual Town Meeting, and the October 25, 2022 Special Town Meeting rewrote the chapter, keeping the Stretch code “including future editions”. The Energy and Sustainability Committee’s page presents the Specialized opt-in code as a proposal for the May 2026 Town Meeting, but the posted May 12, 2026 warrant has no energy-code article, and no energy-code change appears among the 2026 bylaw amendments listed on eCode360. That meeting amended the demolition bylaw (Article 26). Under Chapter 138, a demolition permit application for a structure built before 1901 goes to the reviewing commission within five days; it holds a hearing within 30 days with notice to abutters within 300 feet, and if it finds the building significant and its loss detrimental, no demolition permit issues for nine months unless the commission shortens the delay. Demolishing 25% of a building’s volume or roof structure counts. The wetlands bylaw, Chapter 304, reaches 100 feet from wetlands, banks and ponds, 200 feet from perennial streams and 100 feet from the 100-year storm line. Under Chapter 300, drilling a well needs a DPW permit, a new well needs a Board of Health permit, and well water needs a certified lab analysis before household use. FEMA lists Longmeadow (community 250143) as participating in the National Flood Insurance Program, with current flood maps effective July 16, 2013.
Want this handled start to finish?
Get a free quote →Massachusetts has one State Building Code, 780 CMR, for every city and town; towns cannot rewrite it, though many opt into a stricter energy code. The trades run under their own state codes. Massachusetts rules
Longmeadow building permit FAQ
How much is a building permit for a renovation in Longmeadow?
It depends on the cost step: $55 up to $5,000, $110 over $5,000, $350 over $35,000, and $500 plus $10 per $1,000 above $100,000 for a house. A $150,000 addition costs $1,000.
Do I need a permit for a fence in Longmeadow?
Yes. Fences are on the town’s list of work needing a permit, and the fence permit is $25. Pool fences must also meet the State Building Code under Chapter 265.
Do small sheds need a permit?
The fee schedule prices accessory structures under 200 square feet at $55 for a home lot, and buildings up to 600 square feet also at $55; larger ones are charged $0.55 per square foot per floor.
Can I get a refund if I cancel my project?
No. Under the refund policy in effect since July 1, 2025, permit payments are final whatever the reason.
Which energy code applies to new homes in Longmeadow?
The Stretch code, under Chapter 135 of the general bylaws. A Specialized code proposal was discussed for May 2026, but it was not on the posted warrant.
Is my house in a historic district?
The Longmeadow Historic District covers the Longmeadow Green and surrounding areas, including Town Hall and the old part of the cemetery. Visible exterior changes there need a certificate of appropriateness, filed electronically 15 days before the commission’s monthly meeting.
When can the trade inspectors come out?
The electrical and the plumbing and gas inspectors are part-time and work mornings only; schedule through the office at 413-565-4153.
What does a ZBA application cost?
$150 to file, plus $50 and postage for certified notices to abutters and the cost of the newspaper notice.
Longmeadow permit search and official resources
Applications filed online can be followed in PermitLink. For older permit files, plans and inspection records, ask the Building, Planning and Community Development office by phone or at building@longmeadowma.gov; Planning Board and ZBA case files are posted in the town’s Active Case Files folder, and the assessor’s database shows parcel data.
Inspections are where schedules slip.
Get a free quote →- Building, Planning and Community Development
- Building and Community Development permitting portal page
- PermitLink online permits
- Building Department fee schedule (rev. June 15, 2022)
- When permits are required
- Permitting due diligence guide
- Building and zoning code enforcement
- Zoning Board of Appeals
- Historic District Commission
- Conservation Commission
- Health Department (Eastern Hampden Shared Public Health Services)
- General bylaws (eCode360)
- Zoning Bylaws (eCode360)
- Town Meeting warrants
- Specialized opt-in code information
- Assessor’s database
- Official 2020 municipal census
- Massachusetts municipal energy code list
- Massachusetts State Building Code
- FEMA Community Status Book, Massachusetts
Simplify Longmeadow permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Massachusetts. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Longmeadow sooner?
Let Alliance prepare, file, and track your Longmeadow permits while your crew stays on the job.
More Massachusetts permitting guides
Agawam
Read guide →Chicopee
Read guide →East Longmeadow
Read guide →Lowell Building Permit Guide
Read guide →Ludlow Building Permit Guide
Read guide →Lunenburg Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Longmeadow permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.