Washington County's Division of Permits and Inspections, in the County Administration Annex at 80 West Baltimore Street in Hagerstown, permits and inspects construction across the Maryland county that runs from South Mountain to the West Virginia line — the Maryland Washington County, not the several others that share the name. Its arrangement with three of its towns is unusual and worth knowing before filing: residents within the limits of Boonsboro, Funkstown and Williamsport apply at the county's offices after receiving zoning approval from their town's zoning administrator, the town reviews and approves for local zoning, forwards the application and plans to the division for building code review, and the division returns the approved application to the town for issuance.
The county also enforces a state requirement most jurisdictions have yet to publicise. Under Maryland's public safety code, all new single-family detached houses, semi-detached houses, duplexes and townhouses subject to the residential code that include a garage, driveway or carport must have one electric vehicle supply equipment-installed parking space or one electric vehicle-ready parking space. All new one- and two-family dwellings and additions to them comply with the residential provisions of the 2021 energy code, with the energy efficiency form completed before building plan review approval.
This guide covers Washington County, Maryland. The City of Hagerstown issues its own building permits; Boonsboro, Funkstown and Williamsport share the process described here; and the Washington Counties of other states are unrelated jurisdictions.
Town zoning, county code, town issuance. For Boonsboro, Funkstown and Williamsport the sequence is fixed: zoning approval from the town's zoning administrator, then the county's building code review, then issuance by the town. The application travels; the applicant does not file twice. Elsewhere in the county the division both reviews and issues, and Hagerstown runs its own department entirely.
What requires a building permit in Washington County?
Maryland runs on one statewide instrument, the Maryland Building Performance Standards (COMAR 09.12.51), and enforces it locally. The state adopts each new edition of the International Building Code, the International Residential Code and the International Energy Conservation Code, with Maryland modifications, and every jurisdiction must adopt and enforce the same edition within twelve months — counties and the cities that keep their own permit offices may amend the building and residential codes to suit local conditions, but may make the energy code and the Maryland Accessibility Code only more stringent, never less. The 2021 editions, effective statewide on May 29, 2023 with local enforcement required by May 29, 2024, replaced the 2018 editions; the Maryland Building Rehabilitation Code carries the existing building code beside them. What is local in Washington County is the enforcing office, its amendments, its fee schedule, and the grading, stormwater, forest conservation and Critical Area approvals that run ahead of the building permit.
The codes draw the exemption line and the local amendments move it. The IRC's work-exempt-from-permit list — small accessory structures, low fences, minor repairs — applies as Washington County adopted it, and the jurisdiction's own ordinance may narrow it. Electrical, plumbing and gas work carry their own permits under the state licensing boards' rules, and zoning, grading and sediment control approvals are separate from all of them.
Typically permit required
- New single-family, semi-detached, duplex and townhouse dwellings with a garage, driveway or carport, which need an electric vehicle installed or ready parking space
- All new one- and two-family dwellings and additions, which file the energy efficiency form before building plan review approval
- Construction, grading or stream crossing within a mapped hundred-year floodplain, which needs a county floodplain permit and a state letter of authorisation before any disturbance
- New buildings, additions and any structural work on an existing building
- Interior alterations that reconfigure space, add plumbing fixtures or extend circuits, under the building or residential code and the Maryland Building Rehabilitation Code
- Decks, accessory structures above the local exemption threshold, retaining walls and swimming pools, including above-ground pools
Often exempt
- Work the adopted codes place outside the permit requirement; the division confirms it before work starts
- Painting, wallpapering, interior finishes, cabinets, flooring and trim
- Like-for-like replacement of windows and doors in the same opening
- Small detached accessory structures below the jurisdiction's exemption threshold and fences below its height limit — the zoning rules still apply
- Minor repairs that do not remove or alter structural members
What is actually local, and what is not
The code editions are the state's. Washington County's layer is the enforcing office and its amendments to the building and residential codes, its fee schedule, its grading and stormwater ordinances under the state's delegation, and the town-and-county sequence for Boonsboro, Funkstown and Williamsport, and the electric vehicle parking requirement on new houses.
Who handles permitting in Washington County?
The Division of Permits and Inspections is the enforcing office, and since July 2025 it also provides fire prevention services across the county through the Office of the Fire Marshal. The Washington County Health Department issues well and septic permits, which may be applied for concurrently with the building permit; the state highway administration approves residential driveway access onto state roads; and the county planning commission approves site plans, which may be reviewed concurrently with the building permit once the site plan has accepted status.
| Detail | Information |
|---|---|
| Department | Washington County Division of Permits and Inspections |
| Office | County Administration Annex, 80 West Baltimore Street, Hagerstown, MD 21740 |
| Phone | (240) 313-2460 |
| Office hours | Monday to Friday, 7:30 am to 4:30 pm |
| Permit processing | 7:30 am to 4:00 pm Monday, Tuesday, Thursday and Friday; to 3:00 pm Wednesday |
| Health department | (240) 313-3400 for well and septic permits, applied for concurrently |
Permit types
Residential permits
A Washington County house project files at the annex — or through the town first, in Boonsboro, Funkstown or Williamsport — with the energy efficiency form completed before plan review approval and the electric vehicle parking space designed in where the house has a garage, driveway or carport. Well and septic permits are taken concurrently with the building permit from the health department, and driveway access onto a state road goes to the state highway administration.
How Maryland contractor credentials work
Maryland has no state general contractor license for commercial work, but home improvement is licensed outright: the Maryland Home Improvement Commission licenses contractors who alter, repair or improve residential property, with an examination, proof of financial solvency and a guaranty fund that pays homeowners for a licensee's defective or incomplete work. New construction is different again: a home builder registers with the Home Builder Registration Unit of the Attorney General's Consumer Protection Division under the Maryland Home Builder Registration Act, and the registration number goes on the permit. Electricians, plumbers and gas fitters, and HVACR contractors are licensed statewide by their boards at the Department of Labor, and Washington County verifies those licenses at the permit counter. Owner-occupants may build on their own home without the home improvement license, and Washington County licenses no trades of its own beyond any local registration its ordinance keeps.
Commercial permits
Commercial work in Washington County files three sets of detailed architectural drawings, drawn to scale and carrying a Maryland-licensed design professional's wet seal with signature, date and professional certification — drawings marked preliminary or not for construction are refused. A building permit may be reviewed concurrently with the site plan where the site plan has been submitted and has accepted status with the plan review department, with three copies of the pending dimensioning plan filed alongside, and proof of paid water and sewer allocation fees is part of the checklist.
Prior approvals, plan review and the local clock
A Maryland building permit is one application reviewed by the local office's plan reviewers for the building, residential and energy codes, with the electrical, plumbing and mechanical trades permitted alongside it. The approvals that run ahead of it are the ones that decide the schedule: zoning certification, a grading permit with a sediment and erosion control plan approved by the soil conservation district, stormwater management under the Maryland Department of the Environment's delegation, forest conservation under the Forest Conservation Act where the site disturbs enough land, and Critical Area review within a thousand feet of tidal waters. In Washington County the Antietam and Conococheague creeks and the Potomac bring mapped floodplain into much of the county, where a county floodplain permit and a state letter of authorisation precede any disturbance, and the state highway administration controls access onto its roads. Unlike the states with a statutory review clock, Maryland leaves review times to each jurisdiction — Washington County publishes its own targets, and they are the number to plan against.
Washington County permit costs and fees
Fees follow the division's residential and commercial building fee schedules, with health department, water and sewer allocation and state approvals charged by their own offices.
| Item | Fee or rule |
|---|---|
| Building permit | The division's residential and commercial building fee schedules |
| Well and septic | Health department fees, applied for concurrently with the building permit |
| Water and sewer allocation | Proof of paid allocation fees required on the commercial checklist |
| Floodplain permit | County permit plus a state letter of authorisation before any disturbance in a mapped floodplain |
| Driveway access | State highway administration approval for access onto a state road |
| Town fees | Charged by Boonsboro, Funkstown or Williamsport where the town issues |
Processing hours are shorter than office hours. The division's office is open 7:30 am to 4:30 pm, but permit processing runs only to 4:00 pm on Monday, Tuesday, Thursday and Friday, and to 3:00 pm on Wednesday. An applicant arriving at four on a Wednesday finds the office open and the counter closed.
Trade permits and who may pull them
Trade work is permitted separately from the building permit in most Maryland jurisdictions and inspected by the office's trade inspectors, with the state boards' licenses verified at issuance.
Permit required
- Floodplain work — county floodplain permit and a state letter of authorisation before any disturbance
- Electrical — state-licensed master electrician; separate electrical permit
- Plumbing and gas — state-licensed master plumber or gas fitter; separate plumbing and gas permits
- HVACR — state-licensed HVACR contractor; mechanical permit
- Fire protection, alarms and sprinklers — fire marshal review, state or local, with the building permit
Typically exempt
- Like-for-like fixture, receptacle and switch replacement where the licensing boards' rules allow it
- Low-voltage and communications wiring below the local permit threshold
How to apply for a Washington County building permit
Zoning certification, grading and sediment control, stormwater, forest conservation and Critical Area review run ahead of the building permit.
The Maryland Home Improvement Commission license, or the home builder registration number, goes on the application.
The local application with the building, residential and energy code submittals the scope requires, and trade permits alongside.
Reviewers in the local office check the building, residential and energy codes as the jurisdiction amended them; corrections are answered in writing.
Fees follow the jurisdiction's ordinance and are due before issuance.
Footing to final by permit number, then the use and occupancy certificate that closes the permit.
Review, corrections and what actually causes delay
Washington County allows the building permit to be reviewed concurrently with the site plan once the site plan has accepted status, which is the county's own lever on schedule. What delays a file here is drawings marked preliminary, a town application filed directly with the county, and a floodplain disturbance begun before the state letter of authorisation.
Inspections in Washington County
Inspections follow the adopted codes' required sequence — footing, foundation, framing, rough trades, insulation and final — and are requested from the local office by permit number. Work that passes final receives a use and occupancy certificate for new buildings and changes of use, or a final approval on the permit for everything else. Washington County inspects through the division, which since July 2025 also carries fire prevention services for the county; health department inspections for wells and septic systems run on their own track beside the building inspections.
Washington County permit search and official resources
- Washington County Permits and Inspections — the division, its hours and the electric vehicle and energy requirements
- Homeowner permit procedures booklet — the town-and-county sequence and homeowner filing
- Commercial permit application checklist — sealed drawings, concurrent site plan review and allocation fees
- Maryland Building Performance Standards — the statewide code adoptions from the Department of Labor's Building Codes Administration
- Maryland Home Improvement Commission — home improvement contractor licensing and the guaranty fund
- Home Builder Registration Unit — new home builder registration with the Attorney General
Frequently asked questions
Is this the Maryland Washington County?
Yes — the county between South Mountain and the West Virginia line, with Hagerstown as its seat. Washington Counties in other states are unrelated jurisdictions.
How does permitting work in Boonsboro, Funkstown or Williamsport?
The town's zoning administrator approves for local zoning, then forwards the application and plans to the county division for building code review; the division returns it to the town, which issues the permit.
Do new houses need an electric vehicle space?
Under state law, all new single-family detached, semi-detached, duplex and townhouse dwellings subject to the residential code that include a garage, driveway or carport must have one electric vehicle installed or electric vehicle-ready parking space.
When is the energy efficiency form due?
Before building plan review approval, for all new one- and two-family dwellings and additions to existing ones, under the residential provisions of the 2021 energy code.
Can the building permit be reviewed with the site plan?
Yes, where the site plan has been submitted and has accepted status with the plan review department, with three copies of the pending dimensioning plan filed alongside the building permit application.
Which code edition applies?
The 2021 editions of the International Building Code, International Residential Code and International Energy Conservation Code with Maryland modifications, effective statewide on May 29, 2023 under the Maryland Building Performance Standards, with local enforcement required from May 29, 2024.
Simplify Washington County permitting with Alliance Permitting
Washington County will run reviews in parallel if the file is right and stop dead if it is not. We route town applications through the town, seal every drawing, and file the floodplain and highway approvals before the disturbance rather than after.
Ready to break ground in Washington County sooner?
Send us the scope and the parcel. We confirm the review path with the Washington County Division of Permits and Inspections, assemble the submittal, file it, and track it through issuance — corrections included.