No county building inspection program is shown for Floyd County: the state’s contact sheet for the county, updated September 8, 2026, leaves the local building inspector line empty. Outside Prestonsburg, every project except a house, duplex or townhouse therefore goes to the state’s Division of Building Code Enforcement (502-573-0373) for approval before work starts, and the published sources show no local building permit for houses. Inside Prestonsburg, the city’s building department at 200 North Lake Drive (606-886-2335) takes plan review and building permit applications.
What requires a building permit in Floyd County?
Floyd County splits into two cases. In Prestonsburg, the county seat, the city publishes its own permit rules, in a building brochure last revised in January 2018 and in its current forms. In the unincorporated county and the smaller cities, where the state sheet shows no local inspector, the state’s rule for jurisdictions without a local program governs: construction of anything other than a house, duplex or townhouse, including additions, alterations, renovations and changes of use, needs the Division of Building Code Enforcement’s approval before it starts.
Prestonsburg: city building permit
- New buildings, additions and significant remodels
- Residential portable buildings of 200 sq ft or more, site-built garages and outbuildings
- Pools over 24 inches deep or 250 sq ft, with a 48-inch barrier
- Fences, signs and roofing
- Demolition
- Electrical work, on the city’s electrical permit
Elsewhere in Floyd County
- State plan approval for commercial, three-plus-unit apartment and other non-house buildings
- State HVAC and plumbing permits, including for houses
- Electrical permit and inspection through the local electrical inspector
- Septic permit from the health department where there is no sewer
- KYTC permit for an entrance on a state route
Prestonsburg leaves a few small items out: a commercial portable building under 120 sq ft, left on its runners and not attached to a pad or foundation, needs no permit, and the city asks owners to check with the building department before building a deck. Outside the city, a house, duplex or townhouse must still be built to the Kentucky Residential Code; the state confirms that, with no local program, it gets no building inspections, only HVAC inspection by the state and wiring inspection by the local county electrical inspector, plus the state plumbing inspection on its permit.
What the county decides and what the state holds
At county level the local pieces are the electrical inspection, reached through the County Judge/Executive’s office, the county’s place in the federal flood insurance program and septic permits at the Floyd County Health Department. Prestonsburg adds its own zoning, building and electrical permits inside the city. The state reviews and inspects non-house buildings outside Prestonsburg, issues all HVAC and plumbing permits, regulates manufactured home installation and licenses the trades.
Short on time to read all of this?
Get a free quote →Who handles Floyd County building permits?
The state contact sheet for Floyd County lists only state inspectors (building, manufactured housing, electrical, elevator, HVAC, plumbing and boiler) and directs local electrical inspection to the County Judge/Executive’s office or the city office where the work is done. Prestonsburg’s permit forms carry a “Jurisdiction: State / Local” box, so the city also records which projects fall to the state.
| Office | Contact |
|---|---|
| State Division of Building Code Enforcement (plan review outside Prestonsburg) | 502-573-0373; applications through the state SmartGov portal |
| City of Prestonsburg, Code Enforcement Division / Department of Building & Construction | 200 North Lake Drive, Prestonsburg, KY 41653; 606-886-2335; fax 606-886-1044 |
| Local electrical inspection outside a city | Floyd County Judge/Executive’s office |
| Floyd County Health Department (septic; plumbing plan approval; state plumbing desk) | 238 Goble Street, Prestonsburg, KY 41653; 606-886-2788 (plumbing ext. 2, Tuesdays 8:00–9:30 a.m. Eastern) |
| State manufactured housing section | 502-573-1795 |
| Kentucky Transportation Cabinet, District 12 permits | 109 Loraine Street, Pikeville, KY 41501; 606-433-7791 |
Cities in Floyd County
| City | Building permits |
|---|---|
| Prestonsburg (3,618), county seat | City building department: plan review, building, electrical, roofing, sign and demolition permits; city zoning ordinance |
| Wheelwright (1,048) | No local inspector on the state sheet; state approval for non-house buildings |
| Martin (480) | No local inspector on the state sheet; state approval for non-house buildings |
| Wayland (359) | No local inspector on the state sheet; state approval for non-house buildings |
| Allen (168) | No local inspector on the state sheet; state approval for non-house buildings |
For Wheelwright, Martin, Wayland and Allen, the published sources show no city building permit; each city office can say whether it has its own zoning or other local rules, and it is the contact for electrical inspection inside its limits.
Floyd County permit types and supporting documents
Outside Prestonsburg, building code, HVAC, manufactured housing and plumbing filings go to the state through SmartGov, which first has the applicant settle whether a project is under local, expanded or state jurisdiction. Inside Prestonsburg the city posts separate application forms for new construction, additions and accessory structures over 400 sq ft; demolition and accessory structures under 400 sq ft; remodels; roofing; signs; electrical work; and zone changes.
Not sure this scope needs a permit?
Get a free quote →Residential permits
For a Prestonsburg house or addition, the new construction form asks for a copy of the recorded plat from the Floyd County Clerk’s office (or the recorded deed if there is no plat), a site plan to scale with property lines, easements, rights-of-way, building dimensions and distances to the lines and off-street parking, wall sections, floor and roof plans or truss diagrams, a window schedule with brand, model and size, a list of contractors and subcontractors with their Prestonsburg occupational licenses, workers’ compensation and unemployment information, and the receipt for tap fees. Elsewhere in the county a house has no building permit file; its permits are the state HVAC permit, the state plumbing permit (a homeowner may take one for their own residence, with an affidavit, before work starts), the electrical permit and the septic permit. Manufactured homes go through the state manufactured housing section.
Building or remodeling a home here? Alliance handles residential permit applications, so the crew isn't waiting on the counter.
Commercial permits
A commercial building outside Prestonsburg is filed with the Division of Building Code Enforcement with its construction documents and waits for state approval. In Prestonsburg, the city requires the plumbing plans for regulated structures to be approved by the Floyd County Health Department first, and evidence of that approval must be in the file before the city issues the building permit. Every city application for plan review and a building permit comes with two complete sets of construction plans, a site plan and the fees.
For tenant improvements and new commercial builds, Alliance handles commercial building permits through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning (Prestonsburg). The site and use must comply with the city’s zoning and subdivision ordinances; the brochure sends zoning questions to the Department of Planning and Engineering, and a zone change has its own form.
- Site work (Prestonsburg). The building department approves preconstruction work that affects street access, culverts, drainage and utility locations.
- Taps. Gas, water and sewer taps in Prestonsburg need a separate application to the municipal utilities (606-886-6871), and the tap fee receipt goes with the permit file.
- Land disturbance (Prestonsburg). The city has a Stormwater Conveyance and Erosion Control Ordinance; contact the Department of Building & Construction before any land disturbance, and keep mud and gravel off city streets.
- Septic. Where no sewer is available, the health department on Goble Street.
- State highway access. A Kentucky Transportation Cabinet permit, through the District 12 office in Pikeville, for an entrance or other work in a state right-of-way; Prestonsburg’s brochure also reminds applicants to get an encroachment permit for new street access.
Rather talk it over?
Call 1-855-478-4290 →Floyd County building-permit costs and fees
Floyd County publishes no building permit fees because it issues no building permits. Prestonsburg does not print its building fees either: its brochure tells applicants to contact the Office of Building and Construction for permit pricing, and its electrical application asks for the full cost of the electrical work (labor, material and fixtures), with payment due at application. The fees that are published are the state plumbing fees, in effect since March 1, 2022:
| Permit | Fee |
|---|---|
| One- and two-family residential | $50 + $14 per opening |
| Water heater only | $50 |
| Commercial | $50 + $20 per opening |
| Medical gas piping | $50 + $20 per opening |
Worked example. A house with 9 plumbing openings: $50 + (9 × $14) = $176 for the state plumbing permit; a commercial job with 15 openings: $50 + (15 × $20) = $350. HVAC permits are priced in the state portal, the electrical fee by the inspector or the city, and septic fees by the health department (606-886-2788).
Trade permits and who may pull them
- Electrical. Outside a city, the electrical permit and inspection are arranged through the County Judge/Executive’s office; the state portal does not issue electrical permits for private property. In Prestonsburg, wiring must meet the National Electrical Code and is inspected by the certified electrical inspector the city appoints; the electrical contractor applies with a scaled electrical plan, the contractor’s and master electrician’s license numbers, copies of both licenses and payment.
- HVAC. State permit, required for all new construction since January 1, 2011 and sold only to licensed or authorized applicants; neither Floyd County nor Prestonsburg is on the state’s list of local HVAC jurisdictions (updated May 13, 2025). Prestonsburg’s brochure states that every new building permit in the city requires the state HVAC permit.
- Plumbing. State permit and state inspection, needed for new plumbing, relocated fixtures, a new or replaced sewer or water service, a backflow device or a water heater. The state plumbing inspector’s desk is at the health department on Tuesdays from 8:00 to 9:30 a.m. Eastern (606-886-2788, ext. 2). Connections to municipal water or sewer mains are inspected by the utility.
- Contractors. Trades are licensed by the state. Prestonsburg requires contractors and subcontractors to hold a city occupational license and to show workers’ compensation; its roofing form includes a workers’ compensation affidavit.
Rather not deal with the Floyd County building department?
Get a free quote →How to apply for permits in Floyd County
Inside Prestonsburg, the city building department; elsewhere, the state and the trade offices.
Get the recorded plat or deed from the County Clerk and draw a site plan to scale.
Apply for taps in Prestonsburg, or for a septic permit at 238 Goble Street.
For a regulated structure in Prestonsburg, get the health department’s plumbing plan approval first.
City forms at 200 North Lake Drive, or state plan review in SmartGov for non-house buildings outside the city.
State HVAC and plumbing permits; electrical through the city or the Judge/Executive’s office.
Review, corrections and what causes delay
In Prestonsburg, the plans must be approved before the permit is issued, and the permit cannot issue without the health department’s plumbing approval for a regulated structure, the tap fee receipt and the contractor list with occupational licenses. Starting construction before the permit is issued is prohibited, and changes from the approved plans need the approving office’s authorization, sometimes with revised plans. Outside the city, the state’s approval is the gate for any non-house building.
Floyd County building inspections and final approval
In Prestonsburg the house number is assigned when the permit is issued, the city’s appointed electrical inspector inspects wiring, and for certain use groups no one may use the building until the building official issues a certificate of occupancy; which buildings need one is decided when the permit is issued. Outside the city, non-house buildings are inspected by the state building inspector assigned to Floyd County. A house there has no building inspection, but its HVAC system is inspected by the state HVAC inspector, its wiring by the local electrical inspector, and its plumbing by the state plumbing inspector. Elevators, boilers and manufactured home installations have their own state inspectors.
Want this handled start to finish?
Get a free quote →Kentucky building code in Floyd County
FEMA’s Community Status Book lists Floyd County as participating in the National Flood Insurance Program, on a flood map effective September 16, 2015. Prestonsburg’s brochure notes that buildings must comply with the Kentucky Building Code and its referenced standards in force when the permit is issued.
Kentucky has one mandatory statewide building code that local governments may not add to. Cities and counties enforce it and run zoning. The state reviews plans for larger and higher-risk buildings, and the local program reviews smaller ones. Kentucky rules
Permit search and official resources
Prestonsburg posts open records and public records request forms on its forms page for city permit files. State filings for the rest of the county are tracked in SmartGov, and plats and deeds are recorded at the Floyd County Clerk’s office.
- City of Prestonsburg Code Enforcement
- Prestonsburg guide to building and construction requirements
- Prestonsburg permit and records request forms
- Zoning Ordinance of Prestonsburg
- State contact sheet for Floyd County inspectors (Sept. 8, 2026)
- State building codes: places without a local program
- State Division of Building Code Enforcement
- State SmartGov permit portal
- State plumbing permits and fees
- State plumbing FAQ: homeowner permits
- State HVAC permits
- State list of local HVAC jurisdictions
- Kentucky Transportation Cabinet permit offices
- Kentucky highway districts by county
- FEMA Community Status Book, Kentucky
Inspections are where schedules slip.
Get a free quote →Floyd County building permit FAQ
Does Floyd County issue building permits?
No county program is shown. The state contact sheet updated September 8, 2026 leaves the county’s local building inspector line blank, and Prestonsburg permits inside the city.
Who issues building permits in Prestonsburg?
The city’s Department of Building & Construction (Code Enforcement Division), 200 North Lake Drive; 606-886-2335.
Do I need a permit for a house outside Prestonsburg?
No local building permit is shown, but the house needs state HVAC and plumbing permits, an electrical inspection and, off sewer, a septic permit.
Does a fence need a permit in Prestonsburg?
Yes. The city requires a building permit for fences, and they must meet the zoning rules.
Does a pool need a permit in Prestonsburg?
Yes, for pools over 24 inches deep or 250 sq ft; they go in the rear yard behind a barrier at least 48 inches high.
Where is the plumbing inspector?
At the Floyd County Health Department, 238 Goble Street, on Tuesdays from 8:00 to 9:30 a.m. Eastern; 606-886-2788, ext. 2.
Who handles driveway permits on state roads?
The Kentucky Transportation Cabinet’s District 12 permits office in Pikeville, 606-433-7791.
Simplify Floyd County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Kentucky. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Floyd County sooner?
Let Alliance prepare, file, and track your Floyd County permits while your crew stays on the job.
More Kentucky permitting guides
Pike County
Read guide →Knott County
Read guide →Johnson County
Read guide →Fort Thomas Building Permit Guide
Read guide →Frankfort Building Permit Guide
Read guide →Franklin County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Floyd County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.