Inside the City of La Porte, the Engineering & Building Department at City Hall, 801 Michigan Avenue ((219) 362-2327), issues building permits and performs the required inspections; LaPorte County’s building department covers land outside the city. Applications and contractor registrations are filed on the city’s online Citizen Service Portal. Fees follow Ordinance 10-2017: a $25 base fee for work up to $2,000, then $9, $5 or $3 per $1,000 of project cost, with roofing, water heater and HVAC jobs priced separately.
What requires a building permit in La Porte?
The Building Department issues permits for construction projects inside the city limits and enforces the Indiana building and fire codes together with the city’s own ordinances. Its fee schedule shows the work the city permits, including several jobs that are permitted on their own rather than as part of a larger project:
Building permit by project cost
- New houses and commercial buildings
- Additions, garages and accessory buildings
- Remodeling and alterations
- Class 1 buildings, which also get a certificate of occupancy inspection
Permitted separately
- Residential re-roofing
- Electrical service upgrades (to 200 amps, or larger)
- Water heaters and water softeners
- HVAC replacements and rooftop heating or cooling units
- Moving an existing structure
- Dumpsters in the right-of-way and street or utility excavation
The city does not post a list of exempt work, and its code is kept on an outside code library. Before skipping a permit for a small job such as a shed or deck, ask Engineering at (219) 362-2327. Tree trimming and removal requests are a separate application to the department.
What La Porte decides and what the state holds
La Porte sets its permit fees by ordinance, runs zoning through the La Porte Joint Zoning Ordinance, reviews site plans, historic districts and floodplain compliance, and inspects the work. A shop, office, church or apartment building used by the public, by three or more tenants or by employees is a Class 1 structure; before construction starts it needs the Indiana Department of Homeland Security’s Construction Design Release, unless 675 IAC 12-6-4 exempts the work. The city’s own fee schedule then prices the occupancy inspection for Class 1 buildings by size.
La Porte building department: who handles permitting
Building permits come from the Building Department within Engineering & Building, which reviews projects for code and zoning compliance, issues permits, inspects construction and monitors floodplain compliance. Land use, rezoning and historic review sit with Community Development and Planning, and sewer and water connections with La Porte Utilities. Property outside the city limits is covered by LaPorte County (see the LaPorte County guide).
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Building permits | Engineering & Building, City Hall, 801 Michigan Ave., La Porte, IN 46350; (219) 362-2327; fax (219) 362-1325 |
| Planning, zoning, site review | Community Development and Planning, City Hall; (219) 362-8260 |
| Online filing | Citizen Service Portal (online): permits, contractor registration, site review, historic certificates, utility taps |
| Sewer taps | Wastewater Division, 2101 Boyd Blvd.; (219) 362-2354 |
| Water taps | Water Plant, (219) 326-9540 |
| City Hall main line | (219) 362-0151 |
La Porte permit types
All building permit applications must be submitted online: the portal lists a General Building Permit along with contractor registration, site review, tree work and water and sewer tap applications. The city’s building permit checklist asks for whichever plans are relevant to the job (site plan, foundation plan, elevations, floor plans, roof plans, mechanical, plumbing and landscape plans) and is uploaded with the request.
Residential permits
- New houses and additions give the existing and new height, bedrooms, bathrooms, property size, finished and unfinished floor areas by level, garage size and proposed front, side and rear setbacks on the checklist.
- Roofs, water heaters, softeners, HVAC and service upgrades are separate flat-fee permits, so a furnace or roof replacement needs only that permit.
- Utility connections for a new house are applied for online as a water/wastewater tap.
Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
New and change-of-use developments go to the city’s Site Review Committee before work begins. Every city department sits on the committee and regional utilities are invited; the developer presents for 30 minutes on a scheduled Wednesday and leaves with a list of issues to resolve. Site review applications go in through the portal at least 10 working days before the meeting, and a site review expires one year after the presentation. Class 1 buildings then add the state design release, and development plans, plats and zone changes go to the Plan Commission.
For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Zoning. The La Porte Joint Zoning Ordinance (Ordinance 13-2017, 361 pages) was written for unincorporated LaPorte County and the cities of La Porte and Michigan City; the city posts its own revised copy and an interactive zoning map. Its scope section also extends the ordinance to the parts of the Airport Overlay District outside the city.
- Board of Zoning Appeals. Variances, special exceptions, use variances, use classifications and appeals are heard at 6 p.m. on the second Tuesday at City Hall. Meet the administrator at least a week before filing and file by appointment. The packet asks for a notarized application, an electronic copy of every item, vicinity and aerial maps, a list of adjoining owners from the County Real Estate Office at 555 Michigan Avenue, a site plan, a project summary and the legal description as shown on Beacon.
- Plan Commission. Zone map changes, plats and development plans are also heard on the second Tuesday at 6 p.m.; plats and development plans need proof of sewer and water service.
- Historic districts. Certificates of appropriateness for the Downtown La Porte and Indiana and Michigan Avenues historic districts and locally designated properties go to the Historic Preservation Commission, which meets at 5:30 p.m. on the third Tuesday.
- Floodplain. The department checks floodplain compliance and has posted a map of proposed floodplain changes.
La Porte permit costs and fees
Fees are assessed under Ordinance 10-2017, codified at Municipal Code Chapter 10, Article II, Section 10-33, as posted on the city’s Building Permits page. Building permit fees are based on project cost, rounded up to the nearest $1,000.
| Work | Fee |
|---|---|
| Base fee, project cost $0.01 to $2,000 | $25 |
| Per $1,000 of cost, $0.01 to $50,000 | $9 |
| Per $1,000 of cost, $50,000.01 to $100,000 | $5 |
| Per $1,000 of cost, over $100,000 | $3 |
| Residential roofing | $50 |
| Electrical upgrade to 200 amps / over 200 amps | $40 / $80 |
| Water heater and water softener | $25 |
| HVAC / rooftop heating or cooling unit | $40 / $40 per unit |
| Moving an existing structure | $50 |
| Dumpster in right-of-way | $15 for 1 to 15 days; $25 for 16 to 30 days |
| Excavation without pavement cut / with pavement cut | $50 / $100 per transverse cut or per 100 feet of parallel cut |
| Certificate of occupancy | $50 single-family; $100 two-family; $100 plus $25 per unit multi-family; Class 1 $100 under 12,000 sq ft, $200 over |
| Gas or electric reconnect inspection | $25 first inspection; $20 each additional |
| Missed required inspection | $50 |
Rather talk it over?
Call 1-855-478-4290 →The posted schedule does not say whether the per-$1,000 rates are charged on top of the $25 base fee or band by band, so ask Engineering to calculate the fee for a larger project before you budget. Zoning filings are separate: the 2021 BZA packet lists $80 for a variance or use variance, and the Plan Commission packet $80 for a zone map change and $80 per waiver, with other filing fees quoted by Engineering.
New buildings connecting to city sewer pay a $50 sewer tap fee plus a system development fee by water meter size: $1,100 for a 5/8-inch or 3/4-inch meter, $2,750 for 1-inch, $6,380 for 1½-inch and $11,000 for 2-inch. Once the building permit is issued, Engineering asks the Wastewater Division to issue the tap invoice.
Trade permits and who may pull them
Electrical, plumbing and HVAC work is permitted by the same Building Department. Service upgrades, water heaters, softeners and HVAC change-outs each have their own flat fee, and gas and electric reconnects are inspected for a fee. Contractors register with the city through the Citizen Service Portal, which also holds the city’s other license applications.
- Plumbing and sewer taps. Plumbers hold the state plumbing license, and every sewer tap must be made by a licensed contractor and inspected by the city.
- Contractor registration. The registration application is on the portal; the city’s pages do not post its fee or bond terms, so check them there before the first permit.
- Owners. The city’s pages do not describe a homeowner permit route; a property owner can create a portal account and apply, and Engineering can say whether a registered contractor is needed for the trade involved.
Moving a building, placing a dumpster in the street and cutting pavement for utility work each need their own permit, so a contractor planning street work should apply for the right-of-way permit with the building permit. Street and alley work in or next to city rights-of-way follows the city’s Public Works Construction Standards.
Rather not deal with the building department?
Get a free quote →How to apply for a La Porte building permit
Check the city zoning map; addresses outside the limits go to LaPorte County.
Book site review for new or change-of-use development and file any BZA or Plan Commission petition first.
Contractor registration is filed on the same online portal.
Fill in the building permit checklist and gather the plans that apply.
Choose the permit on the Citizen Service Portal and upload the checklist and plans; the checklist can also be emailed with the application.
Pay the fee, apply for the water and sewer tap, and schedule inspections.
Review, corrections and what causes delay
Engineering reviews each project for code and zoning compliance and, where it applies, floodplain compliance. New or change-of-use development cannot begin work until it has met the Site Review Committee, and the committee’s list of issues has to be resolved. Zoning petitions filed after a posted deadline move to the next monthly cycle, and the packets require a meeting with the administrator at least a week before filing.
Inspections and certificates in La Porte
The Building Department performs the required inspections on every permitted project inside the city. Missing a required inspection costs $50, and gas and electric reconnects are inspected at $25 for the first visit and $20 for each one after that. The certificate of occupancy is issued after the final inspection, at $50 for a single-family house, $100 for a two-family house, $100 plus $25 per unit for multi-family buildings and $100 or $200 for Class 1 buildings depending on whether they are under or over 12,000 square feet.
Sewer taps are inspected by the city. Property maintenance problems are handled by the city’s Code Enforcement Department (219-362-0149), which usually gives owners 10 days to correct a violation before a case goes to the Administrative Law Judge, where civil penalties can reach $1,000.
Indiana building code in La Porte
La Porte’s Building Department enforces the Indiana building and fire codes adopted by the Fire Prevention and Building Safety Commission, plus local ordinances in the city code and the La Porte Joint Zoning Ordinance. FEMA’s Community Status Book lists the City of La Porte (community 180490) as participating in the National Flood Insurance Program, with current flood maps effective November 6, 2013.
Want this handled start to finish?
Get a free quote →Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana
La Porte permit search and official resources
Applicants track their own permits in the Citizen Service Portal. For other permit, inspection or certificate of occupancy records, contact Engineering at (219) 362-2327; questions about the municipal code go to the Clerk-Treasurer’s office at 219-362-9512. Historic Preservation Commission decisions are summarized in annual certificate of appropriateness reports posted on its page.
- Building permits and fee schedule (Ordinance 10-2017)
- Citizen Service Portal (permits and contractor registration)
- Engineering & Building Department
- Building permit checklist
- La Porte Joint Zoning Ordinance (Ordinance 13-2017)
- Site Review Committee
- Board of Zoning Appeals application packet
- Plan Commission application packet
- Historic Preservation Commission
- Sewer tap and system development fees
- City code and construction standards
- FEMA Community Status Book, Indiana
Inspections are where schedules slip.
Get a free quote →La Porte building permit FAQs
Do I need a permit to replace my roof in La Porte?
Yes. Residential roofing is permitted separately for a flat $50.
How much is a permit for a new water heater or furnace?
A water heater or water softener permit is $25, and an HVAC permit is $40.
Can I apply on paper?
The city says building permit applications must be submitted online through the Citizen Service Portal; the checklist can also be emailed with the application.
Does the city issue permits for property outside the city limits?
No. The Building Department covers projects within the city limits; LaPorte County’s building department handles unincorporated land.
What does a sewer connection cost for a new house?
A $50 tap fee plus a system development fee, which is $1,100 for a 5/8- or 3/4-inch water meter, and the tap must be made by a licensed contractor.
Do I need site review for a new business?
Yes. New and change-of-use developments must meet the Site Review Committee before beginning work, and the review is good for one year.
Is the City of La Porte the same as LaPorte County?
No. The city, spelled La Porte, has its own building department at 801 Michigan Avenue; LaPorte County’s building department at the County Complex, 809 State Street, permits unincorporated areas.
When do the Plan Commission and BZA meet?
Both meet at 6 p.m. on the second Tuesday of the month at City Hall, 801 Michigan Avenue.
Simplify La Porte permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in La Porte sooner?
Let Alliance prepare, file, and track your La Porte permits while your crew stays on the job.
More Indiana permitting guides
LaPorte County
Read guide →Michigan City
Read guide →Porter County
Read guide →Lafayette Building Permit Guide
Read guide →LaGrange County Building Permit Guide
Read guide →Lake County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about La Porte permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.