Cicero, Illinois Building Permit Guide

Cicero’s Building Department at Town Hall sends full architectural plans to SAFEbuilt for review, charges a percentage of construction cost, and pairs 2024 I-codes with the 2009 mechanical code.

Authority: Town of Cicero Building DepartmentPlan review: SAFEbuiltCodes: 2024 I-codes, 2009 IMC
Building Department
708-656-3600 ext. 452Mon - Thurs 8 am - 8 pm
Permit fee
2% / 3%Residential / commercial construction cost
SAFEbuilt review
2-3 weeks1 week for revisions
Homeowner allowance
$1,500Per year, own repairs

The Town of Cicero issues building permits through its Building Department at Town Hall, 4949 W. Cermak Road. Projects with full architectural plans are reviewed by SAFEbuilt for the Town, and every contractor and subcontractor on an application must hold a Town of Cicero Business License.

This guide covers Cicero’s Building Department, what needs a permit, SAFEbuilt plan review, fees, codes and inspections.

What requires a building permit in Cicero?

Cicero requires permits for replacing kitchen cabinets or countertops, replacing windows, replacing existing plumbing fixtures, and soffits, fascias and siding. New shingle or flat roof work must be done by a licensed contractor.

Typically exempt: painting, flooring, tuck-pointing, gutter replacement, hot water heater installation, and replacing storm, screen or overhead garage doors in existing openings. A backwater valve install needs a follow-up inspection by the town’s water department.

New construction on non-standard lots goes first to the Architectural Review Committee, with an application, specification sheet and stamped blueprints.

Short on time to read all of this?

Get a free quote →

Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline

Who handles permitting in Cicero?

Cicero Building Department lines
OfficeHandlesContact
Building DepartmentPermits and code questions, Town Hall, 4949 W. Cermak Road; open Mon - Thurs 8 am - 8 pm708-656-3600 ext. 452
Electrical permitsElectrical permit questions708-656-3600 ext. 240
Building permits, property transfers, vacant propertyPermit status and transfers708-656-3600 ext. 469

Inspectors and a building official are in the office from 8 am to 8:45 am for code questions and approximate inspection times, and most inspectors return calls at 5 pm.

Plan review by SAFEbuilt and contractor licensing in Cicero

For projects with full architectural plans, send the plans, calculations and the Cicero permit application through the Town’s Plan Submittal form; SAFEbuilt handles the review. Typical turnaround is 2-3 weeks for the initial review and 1 week for revisions.

Not sure this scope needs a permit?

Get a free quote →

All contractors and subcontractors must hold a valid Town of Cicero Business License; applications naming an unlicensed contractor or subcontractor are not processed.

Illinois licenses plumbers through the Department of Public Health and roofing contractors through the Department of Financial and Professional Regulation; there is no state general contractor or electrician licence, and many jurisdictions require local registration. Contractor credentials in Illinois

Cicero permit costs and fees

The permit and inspection fee is 2% of construction cost for residential structures and 3% for commercial and mixed-use structures, subject to minimum fees. Residential applications need a notarized affidavit and a copy of the contract.

  • Trade minimums: $55 each for air conditioning, electrical, fencing, heating, masonry, plumbing, roofing, siding, windows and similar work.
  • Storm windows: $30. Demolition and wrecking: $200, with proof of ownership or a notarized affidavit from the owner.
  • Homeowner allowance: homeowners doing their own repairs get $1,500 a year; a permit is still required but is free up to that amount. It does not apply to contractor work.

SAFEbuilt review fees are based on square footage or the number of sprinkler heads. All SAFEbuilt and Cicero fees are paid to the Town of Cicero when the permit is picked up, not to SAFEbuilt.

Rather talk it over?

Call 1-855-478-4290 →

How to get a building permit in Cicero

1. Non-standard lot?

Get Architectural Review Committee review first.

2. Check licenses

Every contractor and subcontractor needs a Town of Cicero Business License.

3. Submit plans for SAFEbuilt review

Plans, calculations and the Cicero application through the Plan Submittal form.

4. Bring the approved set

3 printed copies of the stamped approved plans, a completed permit application, separate fire suppression and fire alarm applications with contracts, applications for any extra trades, and an electrical permit application with contracts.

5. Pay and post

All fees are paid before the Building Commissioner issues the permit; the permit and approved plans are displayed at the site.

A building permit carries a validity period set by Cicero; confirm the expiry on phased or delayed work before it passes. Permit validity in Illinois

Rather not deal with the building department?

Get a free quote →

Building codes in Cicero

Cicero has adopted the 2024 IRC, IBC, IEBC, IPC, IPMC, IFC and IECC and the 2023 NEC, with local amendments to the IRC, IPC, IFC and NEC, but still uses the 2009 International Mechanical Code. Local amendments are available from the Town Clerk’s Office.

Inspections in Cicero

Requests for next-business-day inspections are accepted until 4 pm, subject to inspector availability. Inspectors are in the office from 8 am to 8:45 am to give approximate inspection times.

Official Cicero permitting resources

These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.

Want this handled start to finish?

Get a free quote →

Frequently asked questions

Do I need a permit to replace kitchen cabinets in Cicero?

Yes. Cicero requires permits for replacing kitchen cabinets or countertops, windows and existing plumbing fixtures.

Who reviews plans for the Town of Cicero?

SAFEbuilt, for projects with full architectural plans; its fees are paid to the Town of Cicero when the permit is picked up.

Which mechanical code applies in Cicero?

The 2009 International Mechanical Code, although the Town has adopted the 2024 editions of the other I-codes.

Simplify Cicero permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Inspections are where schedules slip.

Get a free quote →
  • Check what the village or city needs for the project: permit, contractor registration, plans and outside approvals
  • Prepare and file the application in the right portal, inbox or counter
  • Track review, book the inspections and close out the permit

Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Cicero sooner?

Let Alliance prepare, file, and track your Cicero permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Cicero permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.