Jefferson County, Idaho Building Permit Guide

Jefferson County’s Planning, Zoning & Building Department issues building permits through its Cityworks portal for the unincorporated county and for Rigby, Menan, Lewisville and Mud Lake; Ririe and Roberts are handled separately.

Authority: Jefferson County Planning, Zoning & Building DepartmentCode: 2018 IBC, IRC, IMC and IFGCPhone: 208-745-9220
Apply
Cityworks public portalChrome or Firefox only; PDF attachments
Review time
About 15 business daysAbout 20 for commercial permits
Plan review fee
15% of the permit feePlus $30 GIS and $30 technology fees

The Jefferson County Planning, Zoning & Building Department in Rigby issues building permits for unincorporated Jefferson County and, by extension of its service, for the cities of Rigby, Menan and Lewisville; Mud Lake properties also use County permits. Applications are made in the County’s Cityworks portal. The 2026 fee schedule charges a valuation-based permit fee plus a 15% plan review fee, and the County allows about 15 business days for a non-commercial permit and about 20 for a commercial one. The County does not handle permits for Ririe or Roberts.

What needs a building permit in Jefferson County?

The County’s own sheet, Structures Requiring Building Permits, starts from the building code rule that an owner needs a permit to construct, enlarge, alter, repair, move, demolish or change the occupancy of a building, and then lists what is exempt. One local twist: a small structure that is exempt from the building permit still needs a County Zoning Certificate if it is in the unincorporated county.

Exempt at a house

  • One-story detached accessory structures up to 200 sq ft
  • Fences not over 7 ft high
  • Retaining walls not over 4 ft, unless supporting a surcharge
  • Sidewalks and driveways not more than 30 inches above grade
  • Painting, tiling, carpeting, cabinets and counter tops
  • Prefabricated pools not more than 4 ft deep
  • Detached decks up to 200 sq ft, not more than 30 inches above grade and not serving the required exit door
  • Swings, playground equipment and flag poles

Exempt on commercial property

  • One-story detached tool and storage sheds up to 120 sq ft
  • Fences not over 7 ft high
  • Retaining walls not over 4 ft
  • Water tanks on grade up to 5,000 gallons
  • Painting, papering, tiling, carpeting and similar finish work
  • Movable fixtures, racks, counters and partitions up to 5 ft 9 inches high

Everything else is applied for by type: single-family dwellings (including modular homes), additions, basement finishes and residential remodels, accessory dwelling units, detached accessory buildings such as pole barns, shops, sheds, conex boxes and greenhouses, manufactured or mobile homes, non-commercial solar arrays, commercial new construction and additions, and commercial signs and towers. An accessory dwelling unit is capped at 1,200 sq ft of living space and 2 bedrooms.

Building or moving a structure without a permit costs twice the permit fee, and the permit still has to be applied for and paid.

Who issues building permits in Jefferson County?

The department manages land use only in the unincorporated county, but its building permit service reaches further. It also issues building permits for three cities and holds every permit to the same state and local building codes. County code enforcement stops at the city limits.

Jefferson County permitting contact
DetailInformation
DepartmentJefferson County Planning, Zoning & Building Department
Address210 Courthouse Way, Suite 170, Rigby, ID 83442
Phone208-745-9220
HoursMonday to Friday, 9:00 a.m. to 5:00 p.m.
ApplyJefferson County Permit Application Portal (Cityworks)

Jurisdiction depends on where the parcel is, not on the mailing address. The County’s jurisdiction guide sorts the six incorporated cities this way.

Short on time to read all of this?

Get a free quote →
Building permits in Jefferson County’s cities
CityWho issues building permits
RigbyJefferson County, using the Rigby application types in the County portal. The City’s Planning and Zoning office at City Hall, 158 W. Fremont (208-745-8111), handles the zoning side and its own deck, fence, garage or shed, sidewalk, sign and solar permit forms, and the City issues the Certificate of Occupancy.
Menan and LewisvilleJefferson County. The County publishes separate help sheets for single-family and modular homes in each city, and the city issues the Certificate of Occupancy from the County’s inspection record.
Mud LakeJefferson County. The guide says properties in the City of Mud Lake use County permits.
Ririe (partly in Jefferson County)Not Jefferson County. The City of Ririe posts its own Application for a Building Permit together with the Idaho state building permit application and submittal standards; the City office is on 208-538-5548.
RobertsNot Jefferson County. The City of Roberts takes its own Building Permit Application, which staff review and the City Council approves; the Council generally meets on the second Tuesday of each month.

Jefferson County applications in the Cityworks portal

Building permit applications exist only in the County’s public portal, which works in Google Chrome or Mozilla Firefox; Edge and Safari are not supported. You register, validate the account, pick the jurisdiction (the County or one of the cities it serves), then choose a category by icon.

  • Commercial: New Construction / Addition, and Signs & Towers.
  • Noncommercial: Single Family Dwelling, Non-Commercial New Addition, Basement Finish or Residential Remodel, Accessory Dwelling Unit, Detached Accessory Building and Manufactured/Mobile Home. Duplexes and townhouses are application types in Rigby only.
  • AG Exempt Building Permit: for buildings that meet the County’s agricultural exemption policy, filed with its affidavit.
  • Solar: non-commercial arrays, roof or ground mounted.
  • Zoning Certificate: structures under 200 sq ft in the unincorporated county.
  • Demolition Permit and Conex Placement Permit.

The County writes a short help sheet for each application type, listing the fields and attachments it will ask for. Other forms sit on the Permits and Applications page: the Flood Plain Development Permit Application, the Building Permit Time Extension Application, the self-build exemption from state contractor registration, and the Road and Bridge Access Permit.

Jefferson County building permit fees

Fees are set by the Board of County Commissioners in the Jefferson County Fee Schedule 2026, adopted April 6, 2026. The Building Official sets the valuation, and the permit fee is read from this table.

Not sure this scope needs a permit?

Get a free quote →
Jefferson County building permit fee table (2026 schedule)
Total valuationBuilding permit fee
$1 to $500$26.46
$501 to $2,000$26.46 for the first $500 plus $3.30 per additional $100 or fraction
$2,001 to $40,000$75.96 for the first $2,000 plus $12.13 per additional $1,000 or fraction
$40,001 to $100,000$536.90 for the first $40,000 plus $9.92 per additional $1,000 or fraction
$100,001 to $500,000$1,132.10 for the first $100,000 plus $7.71 per additional $1,000 or fraction
$500,001 to $1,000,000$4,216.10 for the first $500,000 plus $5.52 per additional $1,000 or fraction
$1,000,001 to $5,000,000$6,976.10 for the first $1,000,000 plus $3.30 per additional $1,000 or fraction
$5,000,001 and over$20,176.10 for the first $5,000,000 plus $2.20 per additional $1,000 or fraction
Other Jefferson County building fees (2026 schedule)
ItemFee
Plan review15% of the building permit fee
GIS/mapping review$30, added to each application
Technology fee$30, added to each application
Agricultural exempt building permit$250
Zoning certificate (structure under 200 sq ft)$50
Demolition permit$100 minimum, plus the plan review fee
Conex placement permit, unoccupied storage conex$90 per structure
Manufactured home$250 single-wide, $500 double-wide, $750 triple-wide
Moving a structure$550, plus permit fees and required inspections
Inspection or re-inspection fee$90
Inspection outside normal business hours$250 per hour, 2-hour minimum
Additional plan review for changed plans$120 per hour, half-hour minimum
Change of occupancy$150
Permit extension$80
Working past a required inspection without passing it25% of the permit fee
Occupying a structure without a Certificate of OccupancyTwice the permit fee

The plan review, GIS and technology fees are added to the permit fee and are due when the application is submitted; no further review happens until they are paid. For example, on a valuation of $250,000 the permit fee is $2,288.60 and the plan review fee is $343.29, and with the two $30 fees the building total is $2,691.89 before mechanical and impact fees.

Impact fees for a new dwelling in the 2026 schedule are $720.90 for roads and bridges, $138.30 for parks and recreation and $46.80 for the Sheriff, plus $200 in the Central Fire District or $500 in the Roberts Fire District.

Rather talk it over?

Call 1-855-478-4290 →

Mechanical, electrical and plumbing permits in Jefferson County

Mechanical (HVAC) permits are County permits in the unincorporated county and in Rigby. The department says it handles mechanical permits for Jefferson County, and the 2026 fee schedule has its own mechanical table. DOPL’s permit map is narrower: it sends HVAC permits to the County for unincorporated land and Rigby, and to the state’s online services for Menan, Lewisville, Mud Lake, Ririe and Roberts. A residential mechanical permit is $200 for work valued up to $1,000, then $200 plus $6.50 per additional $1,000 up to $10,000, with further steps above that. Commercial mechanical permits start at $200 and add $12 per $1,000 up to $10,000. Modifying or replacing appliances, ducts or pipes on an existing system is a flat $100. An older County help sheet, dated January 2024, still tells applicants that mechanical systems are permitted by the state.

Electrical and plumbing permits are state permits, issued and inspected by the Idaho Division of Occupational and Professional Licenses. The County’s inspection sequence puts the trade rough-in inspections before framing and the state finals before its own final.

⚠️ Electrical and plumbing permits may be moving to the County. On September 28, 2026 the Commissioners held a public hearing on Resolution 2026-45, a 2026-2027 county-wide fee schedule that adds County electrical and plumbing permit tables (a residential permit would be $200 for work valued at up to $1,000, the same scale as mechanical) and a 15% plan review fee on mechanical, electrical and plumbing permits; its building permit table is the same as the April 2026 one. On August 3, 2026 they also approved a joint powers agreement to provide building, mechanical, plumbing and electrical inspection services for the City of Lewisville. The County has not posted an adopted resolution, and its department page still lists only mechanical permits, so ask the department (208-745-9220) whether an electrical or plumbing job now files with the County or the State.

Commercial building permits inside the Central Fire District also need a Fire Plan Review, applied for through the link on the County’s guidance page.

What to attach to a Jefferson County application

All attachments must be PDFs. For a single-family dwelling the County’s help sheet lists these.

Required attachments

  • Site plan with property lines, setbacks, easements, north arrow, all structures, driveway, canals, rivers and roads
  • Complete set of plans, with floor plans for each floor
  • Footing and foundation details with steel requirements
  • All four elevations, labeled by compass direction
  • Floor layout, truss layout and engineered truss design
  • Recorded warranty deed
  • Idaho contractor licence, or the completed contractor exemption form

Outside approvals

  • Approved septic permit from Eastern Idaho Public Health, or its letter authorizing connection to an existing or private sewer system
  • Approved access permit from Jefferson County Public Works for an approach onto a county road, or from the Idaho Transportation Department for a state highway
  • Flood Plain Development Permit Application and Elevation Certificate, if the property is in a flood plain

Rather not deal with the Jefferson County building department?

Get a free quote →

The application itself asks for the parcel number and size, zoning, each setback, building heights, the square footage of every kind of space, whether there are canals on the property and the distance from the canal’s high water mark, the sewer provider and permit number, the water source and the heating system.

How to apply for a Jefferson County building permit: 7 steps

1. Work out the jurisdiction

Unincorporated county, Rigby, Menan, Lewisville and Mud Lake use the County portal. Ririe and Roberts do not.

2. Read the help sheet for your permit type

It lists every field and attachment the portal will ask for.

3. Collect the septic and access permits

Both have to be approved before you apply.

4. Register and submit in the portal

Use Chrome or Firefox, validate the account and upload the PDFs.

5. Pay the first invoice

The plan review, GIS and technology fees come first; zoning, floodplain and plan review follow.

6. Pay the balance and post the sign

The permit is issued once it is approved and paid in full, and the permit sign must be visible on the property.

7. Inspect through to the certificate

Give at least 24 hours’ notice for each inspection.

Jefferson County inspections

Inspections need a minimum of 24 hours’ notice. The County lists the basic sequence for a building permit; a particular permit may need fewer or more.

Jefferson County inspection sequence
InspectionNote
1. LayoutFirst inspection on the County’s list
2. FootingBefore concrete is poured
3. FoundationBefore concrete is poured
4. SheathingThe building cannot be wrapped yet
5. Trade rough-in inspectionsThe County’s sheet lists electrical, plumbing and HVAC
6. Framing, then insulationAfter the rough-ins pass
7. DrywallSeams cannot be taped or mudded yet
8. State finals and health department finalWhere they apply
9. Final by the Building DepartmentLeads to the certificate

After the final, the County issues a Certificate of Occupancy or a Certificate of Completion. For property inside a city, the County sends its documentation to the city and the city issues the certificate. A re-inspection costs $90, and the County advises booking the final several days before a loan closing in case a correction is needed.

Local Jefferson County details that matter

Septic: Eastern Idaho Public Health issues septic permits. Its Jefferson County office is at 380 Community Lane, Rigby (208-745-7297).

Want this handled start to finish?

Get a free quote →

Canals: the application asks for the irrigation canal’s name and the distance from its high water mark, and the County keeps a canal information sheet, updated in June 2026, with the forms.

Floodplain: every application gets a floodplain review. A property in a flood plain needs the County’s Flood Plain Development Permit Application and an Elevation Certificate.

Agricultural buildings: County Code 104-1 exempts agricultural buildings from the building codes and from impact fees when they stand on an agricultural unit of land of 5 acres or more and are used only for a qualifying farm use. The building still needs a zoning permit, must meet setbacks and gets a layout and a final inspection, and it cannot be converted to another use without a conversion permit that brings it up to the current building code. The AG Exempt Building Permit costs $250 and requires the County’s signed affidavit on its exemption policy.

County design values: County Code 104-25 sets a 35 psf live snow load, a 45 psf ground snow load, 90 mph wind speed, seismic design category D1 and a 30-inch frost line for houses.

Stale applications: an application with no permit issued within 180 days expires, and reviving it means resubmitting plans and paying a new plan review fee.

Conex boxes: an unoccupied storage conex needs a $90 Conex Placement Permit.

Owner-builders: an owner building without a registered contractor files the County’s Exemptions from State Registration Form.

Extensions: a Building Permit Time Extension Application is available, at $80.

Idaho building code

Idaho’s building codes are set statewide and enforced by the cities and counties that run a building program: the 2018 International Building Code and the Idaho Residential Code (based on the 2018 IRC), the 2018 Idaho Energy Conservation Code, the 2023 National Electrical Code, and a state plumbing code based on the 2015 Uniform Plumbing Code rather than the International Plumbing Code. Idaho’s adopted codes

Official Jefferson County permitting resources

These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.

Inspections are where schedules slip.

Get a free quote →

Jefferson County building permit FAQs

Does Jefferson County issue building permits inside Rigby?

Yes. The County’s building permit service covers Rigby, Menan and Lewisville, and Mud Lake properties also use County permits. The city issues the Certificate of Occupancy.

Who issues building permits in Ririe and Roberts?

Not the County. Each of those cities takes its own building permit application.

How much is a building permit in Jefferson County?

The fee is based on valuation, plus a 15% plan review fee and two $30 fees. On a $250,000 valuation the building total is $2,691.89 before mechanical and impact fees.

How long does a Jefferson County building permit take?

About 15 business days for a non-commercial application and about 20 for a commercial one.

Do I need a permit for a shed in Jefferson County?

A one-story detached accessory structure of 200 sq ft or less is exempt from the building permit, but in the unincorporated county it needs a $50 Zoning Certificate.

Who issues HVAC permits in Jefferson County?

The County, for unincorporated land and Rigby. The state’s permit map shows HVAC permits for Menan, Lewisville, Mud Lake, Ririe and Roberts as state permits. Electrical and plumbing permits come from the Idaho Division of Occupational and Professional Licenses everywhere.

Which browser works with the Jefferson County permit portal?

Google Chrome or Mozilla Firefox. The County says Edge and Safari are not supported.

How much notice does an inspection need?

At least 24 hours.

Simplify Jefferson County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Idaho. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Jefferson County sooner?

Let Alliance prepare, file, and track your Jefferson County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Jefferson County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.