Skip to main content
Municipal GuideIdahoBenewah County

Benewah County, Idaho Building Permit Guide

Benewah County’s Building Department in St. Maries issues building permits for the unincorporated county on a paper application; trade permits come from the State and septic permits from Panhandle Health District.

Authority: Benewah County Building DepartmentCode: State-adopted editions (County Code 8-1-1)Phone: 208-245-4122
Authority
Benewah County Building Department701 W College Ave, Suite 101, St. Maries
Apply / Intake
Paper form at the courthouseHand-drawn plans accepted
Inspections
County: footing to finalTrades inspected by the State

Benewah County’s Building Department, in the courthouse at 701 W College Avenue in St. Maries, issues building permits for land outside the cities on a paper application; hand-drawn plans are accepted if they show enough detail. The fee comes from a valuation table (a $200,000 project is $1,553.75 plus 10% residential plan review), and electrical, plumbing and HVAC permits are separate state permits.

When does Benewah County require a permit?

The county enforces the building codes adopted by the State of Idaho (County Code 8-1-1), and its one-page permit form covers six classes of work: new construction, additions, alterations, repairs, moving a building and removing one. Anything built for people to live in, or that needs sewage disposal, cannot get a building permit until the health district has approved a septic permit (County Code 8-1-4).

County permits

  • Building permit for new buildings, additions, alterations, repairs, moves and removals
  • Site permit for an exempt agricultural building
  • Site disturbance permit for a new driveway or road and for excavation for a structure, unless an exemption applies
  • Floodplain development permit for building, filling or placing a manufactured home in a mapped floodplain
  • Approach permit for a driveway onto a county road
  • Address application for a new site address

Agricultural buildings

  • Barns, stables, livestock and poultry shelters, grain silos, sheds, production greenhouses and storage for farm machinery are exempt from the building codes under County Code 8-1-3
  • The exemption applies only on land the County Assessor has classed as actively devoted to agriculture
  • The building may not be lived in, opened to the public or used as a workplace for processing or packaging farm products
  • It still needs a site permit from the Building Department and must meet zoning placement standards

Small earthwork is exempt from the site disturbance permit: less than 50 cubic yards of cut or fill in 12 months, or grading on a slope under 10% that is more than 500 feet from surface water and disturbs less than one-third of the parcel. The second exemption does not cover commercial or industrial projects.

Who issues building permits in Benewah County?

The county Building Department permits the unincorporated county. The three incorporated cities are handled as follows:

  • St. Maries runs its own Building Department. Applications go to City Hall, 602 College Avenue (208-245-2577), in person or by email, and the city values projects with the ICC building valuation data.
  • Plummer requires building permits and issues them through City Hall, 880 C Street (208-686-1641). The city has its own building inspector.
  • Tensed publishes no permit information of its own; ask the county Building Department whether it covers a Tensed address before you draw plans.

Short on time to read all of this?

Get a free quote →

Part of the county lies inside the Coeur d’Alene Indian Reservation, and the county’s site disturbance rules list the Coeur d’Alene Tribe as a permitting authority for earthwork within the reservation boundary.

Benewah County permitting contacts
OfficeDetails
Building Department701 W College Ave, Suite 101, St. Maries, ID 83861; 208-245-4122; Monday to Friday, 9:00 a.m.–5:00 p.m.
Planning & Zoning40 Airport Road, St. Maries; 208-967-4232; floodplain, subdivision, approach and county sewer applications
Septic permitsPanhandle Health District, St. Maries office, 208-245-4556
Electrical, plumbing, HVACIdaho Division of Occupational and Professional Licenses (state permits and inspections)

Benewah County applications and forms

There is no online portal. The Building Department posts its forms as PDFs and takes them at the courthouse counter:

  • Building Permit (form revised March 2025) — the applicant fills in spaces 1 to 11: job address and tax parcel number, lot and block, owner, contractor and licence number, designer or engineer, use of the building, IBC or IRC, class of work, a description of the work, its valuation in labor and materials, and the building data.
  • Address Application — $150. An assigned address does not replace the building permit or the approach permit.
  • Application and Permit to Use Public Right-of-Way for Approach — $250 to Benewah County Public Works, valid for 180 days, with a sketch of the work and photos of the site.
  • Floodplain Development Permit application — asks for the market value of the existing structure and the cost of the work, because work costing 50% or more of that value is treated as a substantial improvement.
  • Sewer Connection Permit application — for parcels served by a county sewer system.

The owner signs the building permit as owner-builder when no contractor is used.

Benewah County permit fees and valuation

County Code 8-1-2 has the building official set the valuation under the county’s current fee resolution, and the permit fee is then read from the table below. This is the table the county published as its current schedule in September 2025; after a public hearing on September 19, 2025 the commissioners voted to keep it with no changes, turning down a proposal for higher fees and a 40% plan review charge.

Not sure this scope needs a permit?

Get a free quote →
Benewah County building permit fee by valuation
Total valuationPermit fee
$1 to $500$23.50
$501 to $2,000$23.50 for the first $500, plus $3.05 for each additional $100 or fraction
$2,001 to $25,000$69 for the first $2,000, plus $14 for each additional $1,000 or fraction
$25,001 to $50,000$391.25 for the first $25,000, plus $10.10 for each additional $1,000 or fraction
$50,001 to $100,000$643.75 for the first $50,000, plus $7 for each additional $1,000 or fraction
$100,001 to $500,000$993.75 for the first $100,000, plus $5.60 for each additional $1,000 or fraction
$500,001 to $1,000,000$3,233.75 for the first $500,000, plus $4.72 for each additional $1,000 or fraction
Over $1,000,000$5,608.75 for the first $1,000,000, plus $3.65 for each additional $1,000 or fraction
Other Benewah County charges
ItemFee
Plan review, residential10% of the permit fee
Plan review, commercial15% of the permit fee
Reinspection after a failed inspection$47
Temporary certificate of occupancy$200
Lifting a notice of title$300
Address application$150
Approach permit (county road)$250
County sewer connection$1,000 hook-up fee plus $489 capitalization fee

For a project valued at $200,000 the permit fee is $993.75 plus 100 × $5.60, or $1,553.75, and residential plan review adds about $155.

⚠️ Fees may have changed on October 1, 2026. The commissioners held a hearing on September 9, 2026 on fee changes that include a Building & Planning schedule effective October 1, 2026, and Resolution 2026-29, adopting a revised county fee schedule, was on their September 14 agenda. The county has posted neither the resolution nor the minutes, so the figures above are the last schedule it published; the Building Department, 208-245-4122, has the fee now in force.

Electrical, plumbing, HVAC and septic permits

The county permit covers the structure only. Its form states that separate permits are required for electrical, plumbing, HVAC and sewer, and the state’s permit map assigns all three trades in Benewah County to the Idaho Division of Occupational and Professional Licenses (DOPL). Trade inspections are booked with the state, not with the county inspector.

Rather talk it over?

Call 1-855-478-4290 →
Who issues what in unincorporated Benewah County
PermitIssued by
Building, site, agricultural site permitBenewah County Building Department
ElectricalIdaho DOPL
PlumbingIdaho DOPL
HVAC / mechanicalIdaho DOPL
Septic systemPanhandle Health District
County sewer connectionBenewah County Public Works, with a tank-only permit from Panhandle Health District
Approach onto a county roadBenewah County Public Works

On a county sewer system a licensed installer sets the septic tank to Panhandle Health District standards and connects it to the county main, and Public Works inspects the connection before it is covered.

What to submit with the application

The county asks for three things with every building permit, and it does not require drafted plans for simple work.

Required submittal

  • Completed building permit application
  • Site plan showing the property boundaries and dimensions, existing structures and utilities
  • Construction plans with dimensions, materials, spacing and insulation R-values; they may be hand drawn but must show detail
  • Foundation plan with dimensions, spacing and materials
  • Engineered trusses, which are required for all structures

Approvals the county checks off

  • Survey or pin locate
  • Water and sewer
  • Elevation certificate, in a floodplain
  • Highway encroachment
  • Fire department
  • Dike district

Design values printed on the form and in County Code 8-1-2: seismic design category C, 24-inch minimum frost depth, 90 mph wind (3-second gust), a minimum roof snow load of 50 psf, an assumed soil bearing pressure of 1,500 psf and ice shield underlayment.

Rather not deal with the Benewah County building department?

Get a free quote →

How to apply for a Benewah County permit: 6 steps

1. Sort out septic or sewer first

Get the septic permit approved by Panhandle Health District, or apply to connect to a county sewer system. The county will not issue a permit for a dwelling without it.

2. Get an address and an approach

File the $150 Address Application, and the $250 approach permit if the driveway meets a county road.

3. Check floodplain and earthwork

Ask Planning & Zoning whether the site needs a floodplain development permit or a site disturbance permit.

4. Fill in the building permit form

Complete spaces 1 to 11 and attach the site plan, construction plans, foundation plan and truss engineering.

5. File at the courthouse and pay

Take the packet to Suite 101, 701 W College Avenue. The county checks the plans and works out the permit and plan check fees from the valuation.

6. Post the permit and call for inspections

The validated permit and approved plans must be posted on the job site. Buy the state electrical, plumbing and HVAC permits separately.

Inspections and permit completion in Benewah County

The county requires progressive inspections, recorded on the permit itself: footing, foundation or stem wall (or poles); framing; insulation; drywall; and final. Plumbing, electrical and HVAC inspections fall between framing and insulation and are arranged with the state. A sewer or septic permit must be in hand before the final inspection.

A permit lapses if work does not start within 180 days of issue, or stops for 180 days. The building official can reinstate an expired permit on a written request that shows good cause, for a fee equal to the reinspection fee, as long as the codes in force when it was issued still apply.

No building may be occupied until the county issues a certificate of occupancy or completion. Before it does, the applicant has to hand in final approvals from every other agency involved, such as the fire district, the highway district or Idaho Transportation Department, Panhandle Health District, the sewer district and the state electrical and plumbing inspectors.

Local Benewah County filing considerations

Two counters: Building is in the courthouse on College Avenue; Planning & Zoning (40 Airport Road) and Public Works (130 Airport Road) are at the airport. Subdivision and county sewer paperwork goes to Airport Road.

Paved county roads: an approach onto a paved county road has to be paved too, with a 20-foot radius. If a culvert is needed it must be corrugated metal pipe, 12 inches unless Public Works specifies otherwise. Call the road district at least 72 hours before starting.

Want this handled start to finish?

Get a free quote →

Floodplain and dikes: the building permit form has its own sign-off lines for an elevation certificate and for the dike district. Planning & Zoning keeps the flood maps and the county’s flood control code.

Timber and slopes: a design professional must prepare the site disturbance plan for any commercial or industrial project and for sites the county rates high risk after its site inspection.

Idaho building code

Idaho’s building codes are set statewide and enforced by the cities and counties that run a building program: the 2018 International Building Code and the Idaho Residential Code (based on the 2018 IRC), the 2018 Idaho Energy Conservation Code, the 2023 National Electrical Code, and a state plumbing code based on the 2015 Uniform Plumbing Code rather than the International Plumbing Code. Idaho’s adopted codes

Official Benewah County permitting resources

These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.

Inspections are where schedules slip.

Get a free quote →

Benewah County building permit FAQs

How much is a building permit in Benewah County?

It is based on valuation. A $100,000 project is $993.75 and a $200,000 project is $1,553.75, plus plan review at 10% of the permit fee for residential work or 15% for commercial work.

Do I need drafted plans?

No. The county accepts hand-drawn construction plans that show dimensions, materials, spacing and insulation values. Engineered trusses are required for every structure.

Does a barn need a building permit in Benewah County?

An agricultural building on land the assessor classes as actively devoted to agriculture is exempt from the building codes, but the owner still needs a site permit from the Building Department.

Who issues electrical and plumbing permits?

The State of Idaho, through the Division of Occupational and Professional Licenses. The county does not issue or inspect trade permits.

Who issues septic permits?

Panhandle Health District. Its approval has to come before the county building permit for any dwelling.

Does the county issue permits inside St. Maries or Plummer?

No. St. Maries has its own Building Department at 602 College Avenue, and Plummer issues permits through its City Hall.

How long is a Benewah County building permit valid?

Work has to start within 180 days, and the permit is void if work then stops for 180 days.

Simplify Benewah County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Idaho. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Benewah County sooner?

Let Alliance prepare, file, and track your Benewah County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Benewah County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.