Skip to main content
Municipal GuideGeorgiaLilburn · Gwinnett County

Lilburn, Georgia Building Permit Guide

To get a building permit in Lilburn, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

How building permits work in Lilburn: who issues them, the online portal, trade permits, fees and inspection requests.

Authority: City of Lilburn Business Services DepartmentCode: Georgia State Minimum Standard Codes (2024)Phone: 770-921-2210
Authority
City of Lilburn Business Services DepartmentBuilding and trade permits
Apply / Intake
Permit Submittal PortalApplications, plans and payments online
Inspections
City inspection request formBefore 3:00 p.m. for the next business day

In Lilburn, building and trade permits are issued by the City’s Business Services Department at 340 Main Street, and applications, plans and payments go through the City’s online Permit Submittal Portal. Under the FY2026–2027 fee schedule most building and trade permits cost $7 per $1,000 of valuation plus a 2% art fee, and inspection requests made before 3:00 p.m. are scheduled for the next business day.

What requires a permit in Lilburn?

Lilburn’s Building & Trade Permits page lists the common projects that need a permit:

Building

  • New buildings and additions such as garages, bedrooms, bathrooms and sunrooms
  • Renovations such as garage conversions, basement finishing and kitchen expansions
  • Accessory structures, including sheds over 120 sq ft
  • Retaining walls over 4 feet
  • Fences over 4 feet high
  • Swimming pools, decks and fireplaces
  • Demolition of a whole structure or interior work

Trades and site

  • Mechanical (HVAC)
  • Electrical, including service upgrades, rewiring and generators
  • Plumbing, including water heaters
  • Temporary power poles, utility connections and roof repair (trade permit fee)
  • Land disturbance, clearing and grubbing
  • Wall, ground and temporary signs
  • Temporary uses such as tents and events

The City asks applicants to call Business Services at 770-921-2210 before starting a project to find out whether a permit is required. A certificate of occupancy or approval is needed for a new tenant, a new use or a change of business name or ownership.

Lilburn building department: who handles permitting

Business Services issues building and trade permits and certificates of occupancy, and building inspections are coordinated by SAFEbuilt for the City. The Planning Department handles land disturbance, site development, zoning and the BMP, site, stormwater and post-demolition inspections. Gwinnett County approvals (Fire Marshal, water and sewer, and Environmental Health for septic) are collected on the City’s Project Route Sheet before the City permit is issued.

Short on time to read all of this?

Get a free quote →
Lilburn permitting contact
DetailInformation
Office340 Main Street, Lilburn, GA 30047
Phone770-921-2210 (Business Services)
HoursMonday–Friday, 8:30 a.m.–5:00 p.m.
FilingLilburn Permit Submittal Portal
InspectionsOnline Inspection Request form; SAFEbuilt Inspection Coordinator

Lilburn permit types and filing

The City’s Permit Application Guide is a flow chart that sends each project to the right checklist: new buildings and trades, alterations and renovations, interior finish, demolition, certificate of occupancy or compliance, land disturbance and site development, signs and temporary uses. A licensed contractor or the owner must apply, unless a notarized permit authorization is provided.

Forms the City publishes:

  • Building Permit/Compliance Inspection Application, with the parcel number, zoning, setbacks, use, estimated construction cost and owner and contractor details.
  • Subcontractor Affidavit, one for each trade, filed by the general contractor.
  • Homeowner Affidavit, for an owner building on a home they live in or will live in. The owner may not sell or lease it for 12 months, must not have used an owner affidavit elsewhere in the past 6 months or sold a self-built building in the past 24 months, and must still use licensed contractors for HVAC, electrical and plumbing work.
  • Building Demolition Inspection Application with its checklist, and the Project Route Sheet for Gwinnett County sign-offs.
  • Land Disturbance and Site Development Application and Erosion Control Affidavit for site work.

Permit costs and fees in Lilburn

Fees come from the City’s FY2026–2027 Fee Schedule. A 2% art fee is added to most permit fees unless the schedule says otherwise, and a certificate of occupancy or approval fee is charged on top of the building permit.

Lilburn building permit fees (FY2026–2027)
ProjectFee
New construction or addition$7 per $1,000 of valuation
New shell building20% of the $7 per $1,000 rate
Alteration of an existing structure40% of the $7 per $1,000 rate
Interior finish80% of the $7 per $1,000 rate
Accessory structure, pool or retaining wall$7 per $1,000 of valuation
Minimum building permit$100 residential, $200 commercial
Trade permit (mechanical, electrical, plumbing, utility connection, temporary power pole, roof repair)$7 per $1,000 of valuation; the schedule’s total column shows $51 residential and $129 commercial
Demolition of an entire structure5% of the $7 per $1,000 rate
Interior demolition$100 residential, $175 commercial
Certificate of occupancy or approval$50 residential or temporary, $100 commercial

Not sure this scope needs a permit?

Get a free quote →

Building plan review for a new building or addition is $300 up to 20,000 sq ft, $500 up to 100,000 sq ft and $1,000 above that; reviews of shells, interior finishes, renovations and alterations are $100 per trade, and an engineered retaining wall review is $400. Re-inspections cost $50, then $100, then $150, and a same-day special inspection is $65. Work started before the permit is issued carries a 100% penalty.

For example, an addition valued at $100,000 has a permit fee of $700 plus a $14 art fee, before plan review and the certificate fee.

Electrical, plumbing, mechanical and gas work

Lilburn requires a separate permit for subcontractors such as plumbers and electricians. The subcontractor affidavit must be submitted before work begins and at least 24 hours before an inspection is requested.

For each trade permit, the City requires proof of a current occupational tax certificate or business licence, state trade licence, $100,000 property-damage liability insurance, and a driver’s licence or other photo ID. Even under a Homeowner Affidavit, HVAC, electrical and plumbing work must be done by licensed trade contractors.

Plumbing design must meet the City’s own plumbing and water efficiency code adopted in 2024 (Chapter 105), and food service businesses need a safe waste system and Gwinnett County grease trap details.

Rather talk it over?

Call 1-855-478-4290 →

Application documents and plan review

Every building application gives the scope of work, total square footage and cost, with copies of the contractor’s business licence, trade licence, insurance and photo ID.

New building or addition

  • Building Permit/Compliance Inspection Application
  • Gwinnett water meter number with receipt, and sewer tap receipt if on sewer
  • Plans (House Location Plan or Residential Drainage Plan) stamped by Gwinnett County
  • Environmental Health approval if on septic
  • Georgia Department of Agriculture stamp for restaurants and grocery stores
  • Subcontractor affidavits from the general contractor

Commercial plan set

  • Route Sheet with Gwinnett fire, water, sewer, DOT, planning and health approvals first
  • 2 bound sets of stamped construction documents
  • Cover sheet with parcel number, zoning, scope, sheet index and Gwinnett permit number
  • Egress, fire design and structural details
  • Mechanical, electrical and plumbing plans with ComCheck or ResCheck
  • Survey or site plan if the footprint grows or more than 250 sq ft is disturbed

A Georgia architect must seal plans for non-residential assembly, educational and institutional buildings and for R-1 and R-2 buildings over 5,000 sq ft or more than one floor. A Georgia engineer must seal plans for projects costing $100,000 or more, residential buildings of 3 or more floors and walls 4 feet or taller. One approved set stays on site, and a revised PDF set goes to the City Planner before a certificate is requested.

For site work, a pre-submittal conference with planning staff is recommended, and a Site Development review costs $950.

Rather not deal with the building department?

Get a free quote →

How to apply: 6-step Lilburn process

1. Confirm City jurisdiction and zoning

Check the parcel is inside Lilburn city limits and find its setbacks in the zoning ordinance; on new development sites no building permit is issued before the plat.

2. Collect Gwinnett approvals

Use the Project Route Sheet to get Gwinnett fire, water, sewer or Environmental Health sign-offs and the water meter and sewer tap receipts.

3. Use the matching checklist

Follow the Permit Application Guide and the checklist for a new building, an alteration, interior finish or demolition.

4. Submit through the portal

Upload the application, plans and contractor documents to the Permit Submittal Portal and pay the fees there.

5. File affidavits and inspect

File each subcontractor affidavit at least 24 hours before requesting an inspection, then request inspections before 3:00 p.m. for the next business day.

6. Apply for the CO or CA

After all construction inspections pass, apply for the certificate of occupancy or certificate of approval.

Lilburn inspections

Request each building inspection with the City’s online Inspection Request form, using the permit number issued by Business Services. Requests made before 3:00 p.m. go on the next business day’s schedule; you can name a preferred weekday and ask for a call ahead. Questions and rescheduling go to the Inspection Coordinator at SAFEbuilt, named on the form.

BMP, site, stormwater and post-demolition inspections are requested from the Planning Department directly. Sites disturbing more than 240 sq ft must show erosion control BMPs, and larger or stream-side sites need stamped erosion control plans.

A failed inspection that has to be repeated costs $50 the first time, rising to $100 and then $150.

Georgia building code

Georgia's State Minimum Standard Codes apply statewide: the 2024 International Building, Residential, Plumbing, Mechanical, Fuel Gas, and Swimming Pool and Spa Codes and the 2023 National Electrical Code, with Georgia Amendments, in force since 1 January 2026; the energy code is still the 2015 IECC with Georgia supplements. The Georgia State Minimum Standard Codes

Lilburn permit search and official resources

These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.

Want this handled start to finish?

Get a free quote →

Lilburn permit FAQs

How much is a building permit in Lilburn?

$7 per $1,000 of valuation for new construction and additions, plus a 2% art fee, with a $100 residential or $200 commercial minimum. Plan review and the certificate of occupancy are charged separately.

How are Lilburn permit applications submitted?

The City accepts applications, plans and payments digitally through its Permit Submittal Portal.

Inspections are where schedules slip.

Get a free quote →

Do I need a permit for a fence or shed in Lilburn?

Fences over 4 feet high and sheds over 120 sq ft are on the City’s list of work that needs a permit.

Can a homeowner pull a permit?

Yes, with the Homeowner Affidavit for a home you live in or will live in, but HVAC, electrical and plumbing work must still be done by licensed trade contractors.

What is Lilburn’s inspection cutoff?

Building inspection requests must be submitted before 3:00 p.m. to be placed on the next business day’s schedule.

What does Lilburn require for a trade permit?

The subcontractor affidavit, plus proof of a business licence, state trade licence, $100,000 property-damage liability insurance and photo ID.

What happens if I start work without a permit?

The fee schedule adds a 100% penalty for construction or installation started before the permit is issued.

Simplify Lilburn permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Georgia. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Lilburn sooner?

Let Alliance prepare, file, and track your Lilburn permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Lilburn permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.