DeLand, Florida Building Permit Guide

To get a building permit in DeLand, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

How to get a building permit in DeLand, FL - local filing, fees, trade permits, inspections and official municipal resources.

Authority: City of DeLand Building DivisionCode: Florida Building Code, 8th Edition (2023)Phone: 386-626-7007
Authority
City of DeLand Building Division120 S Florida Avenue, DeLand, FL 32720
Apply
Accela Citizen Portal / ePermitHubApplications, payments, status and inspections
Inspections
Online, SelecTXT or automated phone lineAutomated inspection line 386-626-7035
Code
FBC, 8th Ed. (2023)Effective Dec. 31, 2023

In DeLand, the City’s Building Division at 120 S Florida Avenue issues building and trade permits, and applications go through the online Citizen Portal. Under the fee schedule effective October 9, 2026, a new home is charged $1.10 per sq ft under roof plus $0.10 per sq ft for plan review and $100 per inspection, and every application starts with a $100 residential or $200 commercial submittal fee.

What requires a building permit in DeLand?

The Building Division processes all building permits for projects inside DeLand city limits. The Citizen Portal sorts work into these permit types:

Building permits

  • New buildings, additions and renovations
  • Accessory structures: fences, retaining walls, pools, screen enclosures, decks, gazebos, pergolas, sheds, detached garages, carports, patios and driveways
  • Demolition, including interior exploratory demolition
  • Re-roofs, roof-overs, sheathing and underlayment
  • Signs and solar (photovoltaic, pool and water heaters)

Stand-alone trade permits

  • Electrical: service and panel changes, weather heads, service upgrades
  • Mechanical: A/C units, duct work and hood systems
  • Plumbing: piping, fixtures and utility connections
  • Gas

The City’s fee schedule notes that the owner of a single-family home, or the owner’s contractor, does not need a building permit for work valued under $7,500 unless the work is of a type state law still requires a permit for.

DeLand building department: who handles permitting

DeLand permitting contact
DetailInformation
Local office120 S Florida Avenue, DeLand, FL 32720
Phone386-626-7007 (option 1, Permitting); Building@deland.org
HoursMonday-Friday, 8:00 a.m.-5:00 p.m.
Phone options386-626-7007: 1 permitting, 2 fire plan review and inspections, 3 plan review and inspections, 5 zoning
Chief Building OfficialLarry Hites
ApplyCitizen Portal (Accela)

Short on time to read all of this?

Get a free quote →

Front counter staff take applications, check contractor licences, issue permits and keep records; plans examiners and inspectors handle review and site inspections. Fire plan review and inspections sit with the Fire Prevention Division (Office of the Fire Marshal).

DeLand permit types and online filing

Every application starts in the Citizen Portal: log in, choose Start a New Application and pick the record type. The City publishes a step-by-step guide for each type (new building, addition, renovation, accessory structure, demolition, re-roof, electrical, mechanical, plumbing, sign and solar) and a Florida Product Approval specification sheet. Digitally sealed plans are uploaded in the portal.

  • Contractors must be registered with Volusia County to receive a City permit; the general contractor is entered first, then any subcontractors.
  • Owner-builders answer the owner-builder questions online and then sign a notarized paper copy at the office.
  • New buildings go through a pre-check before formal review; pre-checked applications do not pay the separate submittal fee.
  • Private providers must be registered with the City (required from January 1, 2026) and file a Notice to Building Official with every new permit. City inspectors do not inspect jobs whose plans were reviewed by a private provider, and early start permits are not allowed.

DeLand building permit cost

A new building fee schedule takes effect on October 9, 2026, in response to HB 803. Applications already in review by September 30, 2026 keep the old fees; incomplete packages not accepted by then are charged the new ones. Building inspection fees and City impact fees are collected when the permit is issued.

Not sure this scope needs a permit?

Get a free quote →
DeLand building permit fees (effective October 9, 2026)
ProjectFee
Submittal fee$100 residential; $200 commercial
New home, addition or alteration (sq ft under roof)$1.10 per sq ft
Residential plan review$0.10 per sq ft ($100 minimum)
Commercial permit$1.20 to $2.75 per sq ft by occupancy tier
Inspection$100 per required inspection
Re-roof or roof re-cover$350
Exterior doors and windows$250
Residential generator$200
Residential solar$350
In-ground pool / above-ground pool$800 / $250
Pool enclosure (screen cage)$500
Decks, docks and ramps$300
Demolition$300
Stand-alone building or trade permit$150
Technology fee5% of the permit fee

For example, a 2,000 sq ft house under roof has a $2,200 permit fee, $200 plan review and a $110 technology fee, plus $100 for each required inspection, the submittal fee, any trade base fees, the $5 inspector training surcharge and state surcharges.

Re-inspections cost $100 for the first and second and $300 from the third for the same item. Other charges include $30 per page for plan revisions, $100 to change contractor, $100 for an extension, $100 for a Certificate of Occupancy and $150 for each 30 days of a temporary CO. Work without a permit is charged double. A private provider cuts plan review and inspection fees by 25% each. Card payments in the portal carry a 3% fee.

Rather talk it over?

Call 1-855-478-4290 →

New impact, development and connection fees under Ordinance 2026-22 took effect on October 1, 2026; ask the Building Division for the figures that apply to your parcel, and call Volusia County (386-736-5924 ext. 12097) about county impact fees.

Trade permits in DeLand

The Building Division issues electrical, mechanical, plumbing and gas permits through the same portal. On a home, each trade has a $150 base fee. On commercial work, mechanical is $75 plus $10 per ton, plumbing $75 plus $6 per fixture, gas $50 plus $6 per outlet, backflow $50, and electrical $0.50 per amp single-phase or $0.75 to $1.00 per amp three-phase. Temporary power poles are $150. Fire plan review and fire inspections are handled through option 2 of the main number.

How to get a building permit in DeLand

1. Confirm the city and the permit type

Check the parcel is inside DeLand city limits and match the job to a Citizen Portal record type.

2. Check contractor registration

Make sure every contractor is registered with Volusia County, or prepare the owner-builder questions and notarized form.

3. Gather the attachments

Certificate of insurance, digitally sealed plans, survey, product approvals and a recorded Notice of Commencement for jobs over $5,000.

4. Apply and pay the submittal fee

Start the application in the Citizen Portal using the City’s step-by-step guide for that permit type.

5. Pre-check and plan review

New buildings go through a pre-check first; upload corrections when the reviewers ask.

6. Pay, inspect and close out

Pay the permit and impact fees at issuance, then book inspections online, by SelecTXT or on the automated line.

Rather not deal with the building department?

Get a free quote →

Inspections in DeLand

Book inspections in the Citizen Portal, by text through SelecTXT, or on the automated line at 386-626-7035, which runs 24 hours a day to schedule or cancel inspections, give results and take inspection-fee payments. You need the permit number and the inspection code.

Each required inspection is $100. After-hours inspections cost $100 an hour with a 3-hour minimum. Plan review and inspection questions go to option 3 on 386-626-7007.

Florida building code

The Florida Building Code, 8th Edition (2023), has applied statewide since 31 December 2023; the Florida Building Commission has proposed the 9th Edition (2026) to take effect on 31 December 2026. Florida permit rules

DeLand permit search and official resources

These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.

Want this handled start to finish?

Get a free quote →

DeLand permit FAQ

Who issues building permits in DeLand?

The City of DeLand Building Division processes building permits for projects inside city limits. Larry Hites is the Chief Building Official.

Can DeLand permits be filed online?

Yes. The Citizen Portal accepts applications, digitally sealed plans, payments, project tracking and inspection requests.

How much is a building permit for a new house in DeLand?

From October 9, 2026: $1.10 per sq ft under roof, plus $0.10 per sq ft plan review, a 5% technology fee, $100 per inspection and the $100 submittal fee. A 2,000 sq ft house starts at $2,200 plus $200 plan review.

How much is a re-roof permit in DeLand?

$350 for a re-roof or roof re-cover, plus $100 for each required inspection.

Do I need a permit for a fence or shed?

Fences and sheds are accessory structure permits in the portal. Owners of single-family homes may be exempt for work under $7,500 that state law does not require a permit for; check with the Building Division before you start.

Inspections are where schedules slip.

Get a free quote →

Can my contractor pull the permit?

Yes, if the contractor is registered with Volusia County. Owner-builders apply online and sign a notarized form at the office.

Are building fees changing?

Yes. A new building fee schedule starts on October 9, 2026, and new impact, development and connection fees started on October 1, 2026.

Simplify DeLand permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Florida. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in DeLand sooner?

Let Alliance prepare, file, and track your DeLand permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about DeLand permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.