Skip to main content
Municipal GuideConnecticutCity of Norwich · New London County

Norwich, Connecticut Building Permit Guide

To get a building permit in Norwich, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Norwich’s Building Department at 23 Union Street issues building and trade permits through the City’s OpenGov online portal, which also takes inspection requests.

Authority: Norwich Building DepartmentCode: 2022 Connecticut State Building CodePhone: 860-823-3745
Authority
Norwich Building Department23 Union Street, 1st floor
Fee
$40 for the first $1,000Then $20 per $1,000 (Ord. No. 1870)
Filing
OpenGov online portalThe City’s chosen channel
Inspections
9:30 a.m. to 3 p.m.Booked online first; may run 14+ days out

In the City of Norwich, the Building Department in Planning and Neighborhood Services issues building, electrical, plumbing, mechanical, roofing and demolition permits, and the City takes applications through its OpenGov portal. Under Ordinance No. 1870, in force since July 1, 2025, the building permit costs $40 for the first $1,000 of construction value and $20 for each further $1,000, plus the state education fee.

The department is on the first floor at 23 Union Street, open 8:30 a.m. to 4:30 p.m. on weekdays, with inspectors in the field from 9:30 a.m. to 3 p.m.; Christopher Burger is the Building Official. Norwich is a consolidated city and town of about 40,000 people (Census estimate for 2025), so one building office covers all of it, both the City Consolidation District and the Town Consolidation District.

💻

File through the portal. In the City’s words, “We no longer accept paper or emailed applications”: the department takes applications through OpenGov, with every document uploaded as a PDF (the tutorial notes that image files and pictures are not accepted). State law, section 29-263(a), lets an applicant file in person, by mail or by email in the manner the building official sets, so call 860-823-3745 if you cannot use the portal.

What requires a building permit in Norwich?

The portal’s building permit page lists the common jobs, and it adds that no trade work can be done under a building permit: electrical, plumbing, mechanical, roofing and fire protection work each has its own permit type.

Permit required

  • New homes, mobile homes, additions and sunrooms
  • Sheds, garages and carports over 200 sq ft; finishing an attic, garage or basement
  • New or widened window and door openings, and replacement windows or doors
  • Moving or removing walls, beams, stairs and decks
  • Retaining walls over 3 feet; fences over 7 feet, and any pool, hot tub or spa barrier (the portal’s list says over 6 feet; the code exemption the City reprints allows up to 7 feet)
  • Pools, siding, insulation, foundations, slabs and ramps
  • Commercial tenant fit-outs and any change of use
  • Re-roofing, except a one- or two-family home repairing up to 25% of its roof

No building permit

  • A shed under 200 sq ft with no utilities, though it must still be anchored
  • Roof and siding repairs limited to 25% within a calendar year
  • Painting, papering, tiling, carpeting, cabinets and countertops
  • Prefabricated pools 24 inches deep or less

The City’s permit tutorial says a deck needs a building permit whatever its size, while the code exemption list that the City reprints in its 2023 handout excuses a detached deck of 200 sq ft or less, no more than 30 inches above grade, that needs no guards and does not serve the required exit door; the code list is the adopted rule.

Short on time to read all of this?

Get a free quote →

What the city decides and what the state holds

Norwich sets the fee ordinance in chapter 4 of its code, the portal filing system, the inspection booking system and the demolition notice periods. The code, the list of exempt work and every trade license come from the state.

Connecticut has one State Building Code: the code itself sets which work needs a permit and which is exempt, every town’s building official is licensed by the State Building Inspector, and there is no county government. Connecticut rules

Norwich building department: who handles permitting

The Building Department administers the State Building Code: it takes applications, reviews plans, inspects construction, issues certificates of occupancy and demolition permits, and coordinates projects with Norwich Public Utilities, which issues its own permits for water and sewer service lines. Zoning permits, the Commission on the City Plan, the Inland Wetlands, Watercourses and Conservation Commission and coastal site plan review sit in the same Planning and Neighborhood Services office. The Uncas Health District handles septic systems, and the Fire Marshal reviews the plans of permits that need its sign-off, though it does not inspect one- and two-family homes for life safety.

Norwich permitting contacts
DetailInformation
Building Department23 Union Street, 1st floor, Norwich, CT 06360
Phone and fax860-823-3745; fax 860-823-3741; scheduling 860-823-3766 or 860-823-3739
HoursMonday to Friday, 8:30 a.m. to 4:30 p.m.; inspections 9:30 a.m. to 3 p.m.
Online portalNorwich OpenGov (ViewPoint Cloud) portal: building, trade, zoning, fire marshal and NPU permits
Planning and wetlandsCity Planner and wetlands agent, 860-823-3745 ext. 3773
Uncas Health District401 West Thames Street, Suite 106; 860-823-1189
Norwich Public Utilities173 North Main Street; 860-887-2555 (water and sewer service permits)

Permit types

Residential permits

For a house project the City asks for a specific description: an application that only says “build garage” or “fence” will not be approved. The tutorial explains how to print the lot from the City’s GIS at a scale of 40 and draw the site plan on it with setbacks and dimensions, and engineered plans are needed for larger work such as a new home. Handouts cover finished basements, pools, decks for one- and two-family homes and when architectural plans are required. Roofing has a quick form that needs photographs of the sheathing, ice barrier, seam tape, underlayment, drip edge, step flashing and finished roof, and an overlay must show that the existing roof does not have too many layers and is not waterlogged.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

Commercial fit-outs, changes of use and new commercial buildings file on the same building permit, with fire alarms, sprinklers and kitchen hoods on a separate fire protection systems permit. The Fire Marshal wants plans in full-size paper form and will not approve a final certificate of occupancy for a project whose plans it did not review before work began. A new or changed business first gets a zoning verification, and tents, construction trailers and events take a temporary installation permit.

What comes before the building permit

The zoning enforcement officer must issue a zoning permit before the building inspector can issue a building permit for new buildings, additions, pools, fences, sheds, garages, driveways and changes of use. Special permits, site plans, wetlands, subdivision, coastal area management and variance applications are still filed on paper, with the portal used to hold the documents. Any activity within 100 feet of a wetland or watercourse needs the wetlands agent’s review, and the zoning regulations were amended by Ordinance No. 1881 in January 2026. On a septic lot the Uncas Health District reviews additions, decks and pools under the Public Health Code’s B100a rule.

Norwich permit costs and fees

Fees are set in sections 4-3 and 4-5 of the Code of Ordinances, rewritten by Ordinance No. 1870 of April 21, 2025 and in force since July 1, 2025. The fee is first paid on the estimated cost; under section 4-6, when the finished work cost more than $500 the applicant files a declaration of the actual cost and pays the difference, and a lower actual cost is refunded.

Rather talk it over?

Call 1-855-478-4290 →
Norwich building fees (Code of Ordinances sections 4-3 and 4-5, Ordinance No. 1870)
ItemFee or rule
Building permit$40 for the first $1,000 of construction value, $20 for each further $1,000
Expedited review and inspections100% of the standard permit fee, $100 minimum and $2,500 maximum, non-refundable
Initial plan review; each later review$125; $100
Certificate of occupancy$75 per dwelling or sleeping unit (one- and two-family, R-2, R-3, R-4); $150 per unit for other uses; $50 temporary
Inspections$50 for required initial inspections; $100 for each subsequent, missed or failed one; $125 an hour after hours, three-hour minimum
Demolition$100 accessory structure; $200 single-family home; $300 up to 10 units; $500 over 10 units; $600 or $1,000 commercial
Mobile home; annual maintenance permit$900; $300 plus the permit fees
Permit extension; code modification request; board of appeals$50; $30; $200
State education fee26 cents per $1,000, collected on top of the City fees

Worked example. A $20,000 bathroom and kitchen renovation pays $40 for the first $1,000 and 19 × $20 ($380) for the rest, $420, plus $5.20 in state education fee: $425.20, before any plan review or certificate fees. Expedited handling of the same permit would add another $420.

The City’s Building Fees web page, which it calls a courtesy, still shows several older figures: a $35 minimum, $150 for an initial plan review, $250 for an annual maintenance permit, $950 for a mobile home and a $250 charge for work done without permits. It describes the $50 and $100 inspection charges as re-inspection fees. The ordinance figures are the adopted ones, and the page’s refund rules still apply: requests in writing within 30 days of approval, a $50 administrative charge, and no refund once a review or inspection has been done.

Trade permits and who may pull them

Each trade files its own permit in the portal. The electrical permit covers new circuits, solar with or without batteries, EV chargers, mini-split circuits, low-voltage systems and pool bonding; the mechanical permit covers boilers and furnaces (like-for-like replacements included), wood and pellet stoves, chimney liners, gas piping, heat pumps and vented fans; the plumbing permit covers water heaters, fixtures and gas piping, with pressure tests done with the appliances disconnected.

Norwich rules

  • A homeowner in an owner-occupied single-family home can do most trade work without the trade license, but still needs the permit
  • Contractors upload a license copy and workers’ compensation proof, and an owner’s authorization form when they apply for the owner
  • Water and sewer lines from the street are permitted by Norwich Public Utilities, not the Building Department
  • A new sewer connection is approved only after the Sewer Capital Connection Fee is paid

Fire protection permit

  • Fire alarm systems
  • Sprinklers and suppression
  • Commercial kitchen hoods

Rather not deal with the building department?

Get a free quote →

The Department of Consumer Protection issues the trade licenses and registers home improvement and new home construction contractors.

How to apply for a Norwich building permit

1. Get the zoning permit

File the zoning permit in the portal with a GIS-based site plan and elevations; add the wetlands agent’s review if the work is within 100 feet of a wetland or stream.

2. Check the health and utility side

On septic, ask the Uncas Health District about a B100a review; on city sewer or water, file the NPU permit and pay any connection fee.

3. File the building permit online

Choose the right record type (building, roofing, electrical, mechanical, plumbing, fire protection or demolition) and describe the job precisely.

4. Upload PDFs

Plans, the owner’s authorization form, the contractor’s license and workers’ compensation proof, all as PDF files.

5. Pay and answer review comments

Pay on the estimated cost, or choose expedited review for an extra 100% of the fee.

6. Inspect and settle the final cost

Request inspections online and file the affidavit of final cost when the work is finished.

Review, corrections and what causes delay

The usual hold-ups are a vague project description, image files instead of PDFs, a missing owner’s authorization and a building permit filed before the zoning permit. Expedited review moves a file ahead of the queue but, as the ordinance says, depends on staff availability and does not guarantee approval. Section 4-8 bars a permit or certificate of occupancy while property taxes are delinquent, unless the Building Official finds a safety risk or the City Manager approves. Demolition of a building of 500 sq ft or more needs a newspaper notice at least 30 days before the permit (60 days for historic district or National Register buildings), mailed notice to abutters and a 2 by 3 foot sign posted for 30 days.

Inspections in Norwich

Request inspections through the portal, which the City prioritizes, or by phone on 860-823-3766 or 860-823-3739, giving the inspection type, address and permit number. In busy periods inspections may be booked 14 days or more ahead. Permits from the City’s older computer system are handled through the office staff.

Want this handled start to finish?

Get a free quote →

The City’s required inspections handout lists footings (with all property corners located and marked so setbacks can be checked), foundation walls, framing and masonry, rough plumbing, electrical and mechanical with pressure tests, wallboard, and the final, for which house numbers, sidewalks and final grading must be done. Floodplain inspections, checked against the FEMA flood maps that took effect on August 1, 2023 (the City posts the panels on its maps page), and insulation, fire-rated construction and radon or vapor barrier inspections can be added. The Fire Marshal does not do residential life safety inspections of one- and two-family homes.

Norwich permit search and official resources

Records in the OpenGov portal can be searched online; for permits from the older system, call the department’s office staff.

Inspections are where schedules slip.

Get a free quote →

Norwich building permit FAQ

Who issues building permits in Norwich?

The City’s Building Department at 23 Union Street, first floor, through the OpenGov portal. Call 860-823-3745.

How much is a building permit in Norwich?

$40 for the first $1,000 of construction value and $20 for each further $1,000, plus 26 cents per $1,000 for the state. A $20,000 job pays $425.20.

Can I drop off a paper application?

The department says it no longer accepts paper or emailed applications and takes them through the OpenGov portal as PDF files; call 860-823-3745 if the portal is not an option.

Can I pay for faster review?

Yes. Expedited review and inspections cost 100% of the standard permit fee extra, at least $100 and at most $2,500, and depend on staff availability.

Can a homeowner do their own electrical or plumbing work?

The City says an owner living in a single-family home can do most trade work without holding the trade license, but a permit is still required.

Do I need a permit for a new roof?

Yes, on the roofing quick form with photographs, unless it is a one- or two-family home repairing no more than 25% of the roof.

How far ahead are inspections booked?

Inspectors work 9:30 a.m. to 3 p.m., and in busy periods inspections may be booked 14 days or more ahead; online requests are handled first.

Simplify Norwich permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Connecticut. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Norwich sooner?

Let Alliance prepare, file, and track your Norwich permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Norwich permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.