The Town of Newington’s Building Department, at Town Hall on Garfield Street, issues building, electrical, plumbing and heating permits. You can apply online through the Online Permit Center, by mail or at the counter. Since July 1, 2025 the fee has been $15 for each $1,000 of value or part of $1,000, with a $50 minimum for work up to $3,000, and inspections must be booked 24 hours ahead on 860-665-8580.
What requires a building permit in Newington?
The residential application form puts it briefly: additions, alterations, decks, pools, porches, garages, sheds, gazebos, pergolas and new houses need permits. On the commercial side, additions, alterations, changes of use and new construction do. Newington also keeps separate permit forms for each kind of work:
Permits the Town lists
- Residential and commercial building permits
- Electrical, plumbing, and heating and air conditioning
- Roofing and siding
- Swimming pools
- Demolition
- Fuel storage tanks
- Sprinkler and fire suppression systems
- Signs
- Solid fuel stoves
No building permit (zoning still applies)
- Sheds under 200 sq ft
- Freestanding decks under 200 sq ft and less than 30 in. off the ground
- Both still need a zoning permit and a plot plan
- Fences up to 7 ft that are not pool barriers; they may sit on the property line but must meet the Zoning Officer’s height and front-yard limits
Anything that changes the footprint of the property needs zoning review as well, and the Town counts air conditioning units, sheds, generators and tanks as footprint changes.
What the town decides and what the state holds
The building code, the exemptions in it and the licensing of trades are the state’s. The Town sets its fee schedule, which it raised from July 1, 2025, decides how applications are taken (Newington still accepts paper by mail or at the counter alongside the online portal), and runs its own land use approvals: zoning review by the Town Planner’s office, the Town Plan and Zoning Commission, the Conservation Commission and the Inland Wetlands Commission, flood permits and a Building Code Board of Appeals. Septic and well permits come from the Central Connecticut Health District, which Newington joined in 2006.
Newington building department: who handles permitting
The Building Department reviews plans, issues building and trade permits, inspects the work and issues certificates of occupancy. Douglas Jourdan is the Building Official. The Town Planner’s office handles zoning review, the Zoning Enforcement Officer and the land use commissions; the Fire Marshal’s Office does fire code plan review and inspections. All three are in Town Hall.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Building Department | Town Hall, 200 Garfield Street, Newington, CT 06111 |
| Phone and fax | 860-665-8580; fax 860-665-8577 |
| Hours | Monday, Wednesday and Thursday 8:30 a.m. to 4:30 p.m.; Tuesday 8:30 a.m. to 6:00 p.m.; Friday 8:30 a.m. to noon |
| Online Permit Center | newingtonct.viewpointcloud.com (portal help line 617-577-9000 ext. 2) |
| Town Planner and zoning | Town Hall, 860-665-8575 |
| Fire Marshal | Town Hall, 860-667-5910, Monday to Friday 8:30 a.m. to 4:30 p.m. |
| Septic and wells | Central Connecticut Health District, 2080 Silas Deane Highway, Rocky Hill, (860) 785-8380 |
Newington permit types and application documents
There are three ways in. Online, the Online Permit Center lets homeowners and licensed contractors apply, pay and track the permit once they have an account. By mail, print the right form from the Town’s permit forms page and send it with the documents and a check payable to the Town of Newington. In person, bring the same to the Building Department counter. Whatever the route, the Town lists the same required items:
- The completed permit application, plus the Application for Zoning Review ($15) and a plot plan where zoning review is needed
- The contractor’s name, address and phone, and a copy of the contractor’s Connecticut license or registration
- Proof of workers’ compensation insurance (state forms 7A and 7B are posted for exemptions)
- Construction plans: 2 sets for a one- or two-family house, 3 sets for anything else
- Approvals from the health district, Conservation Commission, Inland Wetlands Commission, Town Plan and Zoning or the flood permit, where they apply
Residential permits
Plans must show the work with dimensions and a cross section in enough detail to check the code; for a pre-built shed a photo or brochure will do. The plot plan must be the official one, drawn to scale, with the new structure marked in ink, the changes initialed and dated, and the distances to the property lines shown. The Planning and Zoning office can email a plot plan, and paper copies cost $1. Sheds must sit on the rear half of the lot, at least 5 ft from the property line, with an average roof height of no more than 15 ft. A detached accessory building of up to 600 sq ft with an eave height of 10 ft or less needs no frost-protected footing, but must still rest on undisturbed soil or engineered fill and be anchored against wind uplift.
Building or remodeling a home here? Alliance handles home building permits, so the crew isn't waiting on the counter.
Not sure this scope needs a permit?
Get a free quote →Commercial permits
The commercial, industrial and multi-family application asks for 3 sets of plans and a completed zoning permit application, and the Town’s form says buildings of 500 sq ft or more need a design professional. The application records any Town Plan and Zoning or Zoning Board of Appeals approval and its date, and separate forms cover sprinkler and fire suppression systems, fuel storage tanks and signs. A certificate of occupancy fee of $50 applies to new construction and whenever a new tenant moves in.
For tenant improvements and new commercial builds, Alliance handles commercial permit filing through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning review: the Assistant Town Planner, who is the Zoning Enforcement Officer, approves or denies each Application for Zoning Review against the plot plan, and staff check whether the parcel is in the 100- or 500-year flood zone, a wetland, an upland review area or a conservation easement.
- Erosion bond: since January 1, 2018, zoning review for an addition, an in-ground pool or a new building needs a $500 erosion and sedimentation control bond, paid by check and held until the project is complete.
- Wetlands and commissions: wetlands permits go through the Inland Wetlands application packet, and larger projects to the Town Plan and Zoning Commission, which offers a pre-application form.
- Septic and wells: on lots not served by sewer, the Central Connecticut Health District witnesses the deep test pits and percolation tests, approves the septic plan and inspects the installation.
Newington permit costs and fees
Newington raised its building permit fee from July 1, 2025; the increase first appeared in the Town Council’s budget discussion of March 11, 2025 as a proposal expected to add $150,000 in revenue. The rule is $15 for each $1,000 of value or fraction of $1,000, and work valued at $3,000 or less pays a flat $50. Above $3,000, round the value up to the next thousand and multiply by $15, without adding the $50.
| Item | Fee |
|---|---|
| Work valued up to $3,000 | $50 |
| Work over $3,000 | $15 per $1,000 or fraction (for example $60 for $3,200, rounded up to $4,000) |
| Application for Zoning Review | $15 |
| Certificate of occupancy, new single-family house | $25 |
| Certificate of occupancy, commercial new construction or new tenant | $50 |
| Erosion and sedimentation control bond (additions, in-ground pools, new buildings) | $500, held until the project is complete |
| Plot plan copy | $1 |
Rather talk it over?
Call 1-855-478-4290 →For example, a $50,000 addition comes to $750 on the Town’s table, plus $15 for zoning review and the $500 bond check, which the Town holds until the project is complete. Value is estimated with the Town’s value charge schedule, which sets base costs by type of work. The Permit Fees web page still shows the earlier rate ($11 per $1,000 above $4,000) beside the notice of the increase; the July 2025 schedule is the one in force. The Town’s schedule does not list the state education fee separately.
The health district charges separately under its schedule effective July 1, 2025: $455 for plan review and the permit to install a new septic system, $230 for soil testing on a new lot and $85 for a Public Health Code section 19-13-B100a review, the check made before adding to or changing the use of a building served by a septic system.
Trade permits and who may pull them
Electrical, plumbing, and heating and air conditioning work each have their own Town permit form, and the same forms are available in the Online Permit Center. The building permit application shows the trades together: its fee box lists building, heating and air conditioning, electrical and plumbing permits paid on the job. Fees follow the same $15 per $1,000 rule. Sprinkler and fire suppression systems and fuel storage tanks also have their own permit forms.
Who may pull trade permits
Newington’s commercial form states the local rule plainly: no license is needed for the general contractor on a building permit, but licenses are needed for the trades. Applications must carry a copy of the contractor’s Connecticut license or registration, and the home improvement registration applies to work on existing homes. The Online Permit Center is open to homeowners as well as licensed contractors. The Town’s pages do not set out a separate rule on homeowners doing their own electrical or plumbing work.
Rather not deal with the building department?
Get a free quote →How to apply for a Newington building permit
Ask Planning and Zoning for the official plot plan, mark the work on it and file the Application for Zoning Review with the $15 fee.
Health district on a septic or well lot, Conservation and Inland Wetlands commissions near wetlands, and a flood permit in a flood zone.
Online Permit Center account, mail-in forms with a check, or the Building Department counter.
Application, plans in the right number of sets, contractor license copy and workers’ compensation proof.
$15 per $1,000 of value, plus the $500 erosion bond for additions, in-ground pools and new buildings.
Call 860-665-8580 at least 24 hours before each inspection, through to the final or certificate of occupancy.
Review, corrections and what causes delay
The Building Department posts no review timetable. The residential form says an application cannot be processed until it has its plans, its zoning review where the footprint changes and its plot plan, so those three items come first. A missing health district, wetlands or flood approval stops the permit, and the Online Permit Center lets you follow the application’s status while it waits.
Newington inspections and closeout
Call 860-665-8580 at least 24 hours ahead; office staff, not the inspectors, keep the schedule. Most inspections need someone at the house, the owner or a representative over 21. Call Before You Dig (811) before any excavation.
A new house or addition is inspected at erosion controls where required, footing forms and rebar before concrete, foundation forms and hold-downs, footing drains or waterproofing before backfill, anchor bolts and sill plate, rough framing with the rough plumbing, electrical and HVAC, the electrical service, insulation before drywall, and the final or certificate of occupancy inspection. A deck is inspected at the piers before concrete, at framing and tension ties before the decking goes on (only for decks less than 4 ft above grade), and at final. When an alteration or addition needs a permit, smoke and carbon monoxide detectors are checked at the final inspection. Commercial work adds inspections of fire-rated gypsum assemblies, fire-resistant penetrations, energy efficiency and above-ceiling work, plus special inspections as the Building Official determines.
Want this handled start to finish?
Get a free quote →Building code and flood zones in Newington
Newington enforces the 2022 Connecticut State Building Code for applications filed from October 1, 2022, and the application date will decide when the delayed 2026 edition takes over. The Town is a participating community in the National Flood Insurance Program, with FEMA flood maps effective September 26, 2008; the Town Planner’s page links a FEMA flood hazard web map, and work in a flood zone needs a flood permit before the building permit.
Connecticut has one State Building Code: the code itself sets which work needs a permit and which is exempt, every town’s building official is licensed by the State Building Inspector, and there is no county government. Connecticut rules
Newington building permit FAQ
Who issues building permits in Newington?
The Town Building Department at Town Hall, 200 Garfield Street, 860-665-8580.
Can I still apply on paper?
Yes. Newington takes applications online, by mail with a check, or in person at the Building Department.
How much is a building permit in Newington?
$15 per $1,000 of value or fraction, with $50 covering work up to $3,000. A $50,000 project is $750.
Do I need a permit for a shed?
Not a building permit for a shed under 200 sq ft, but you still need zoning review and a plot plan, and the shed must be on the rear half of the lot at least 5 ft from the line.
Why do I need a $500 bond?
Since 2018 the Town requires an erosion and sedimentation control bond with zoning review for additions, in-ground pools and new buildings; the check is held until the project is complete.
How do I book an inspection?
Call 860-665-8580 at least 24 hours ahead, and have the owner or an adult representative over 21 on site.
Who approves septic systems in Newington?
The Central Connecticut Health District in Rocky Hill, which also covers Berlin, Rocky Hill and Wethersfield.
Newington permit search and official resources
The Online Permit Center has a public Search for a Permit option alongside the application link, and an account lets you follow your own applications. For older permits and certificates of occupancy, ask the Building Department at Town Hall or use its online contact form.
Inspections are where schedules slip.
Get a free quote →- Newington Building Department
- Newington Online Permit Center (apply and search permits)
- Newington permit application requirements
- Newington building permit fee schedule (from July 1, 2025)
- Newington permit fees and value charge schedule
- Newington permit forms
- Newington inspection requirements
- Newington zoning applications and fees
- Newington Town Planner
- Newington Fire Marshal’s Office
- Central Connecticut Health District: septic and wells
- Office of the State Building Inspector
- Connecticut Department of Consumer Protection: licenses and registrations
Simplify Newington permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Connecticut. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Newington sooner?
Let Alliance prepare, file, and track your Newington permits while your crew stays on the job.
More Connecticut permitting guides
Hartford County
Read guide →Avon
Read guide →Berlin
Read guide →Newtown Building Permit Guide
Read guide →North Branford Building Permit Guide
Read guide →North Haven Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Newington permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.