Johnstown, Colorado Building Permit Guide

The Town of Johnstown issues building and electrical permits through its eTRAKiT portal and contracts SAFEbuilt for plan review, most inspections and its Chief Building Official.

Authority: Town of Johnstown Building DepartmentCode: 2024 International Codes; 2023 NECPhone: 970-578-9608
Apply
eTRAKiTPermits, contractor licences and inspection requests
Use tax
3.5% on construction materialsCollected when the permit is issued
Inspection cut-off
4:00 pm the business day beforeBookable up to 7 days ahead

Building permits inside Johnstown come from the Town’s Building Department at 201 Centennial Drive (permit desk 970-578-9608; Town Hall 970-587-4664), and applications are made online in eTRAKiT. Plan review and most inspections are done for the Town by SAFEbuilt, which also supplies the Chief Building Official. Fees come from the Town’s 2026 Fee Schedule, adopted January 5, 2026, and a 3.5% use tax on construction materials is collected with the permit. Small residential permits are turned around in up to 7 or 14 business days.

What requires a building permit in Johnstown?

The Building Department publishes two lists, one of work that needs a permit and one of work that does not.

Permit required

  • Any new structure or addition
  • Finishing or converting a basement or garage space
  • Adding or removing walls or doors
  • A deck, covered or enclosed porch, pergola or stairs
  • Replacing windows, window frames or door frames
  • Roofing or siding over 100 sq ft
  • A new or replacement water heater, furnace or air conditioner
  • A new or replacement in-ground pool, hot tub or fireplace
  • Solar panels
  • Plumbing work and electrical work
  • Retaining walls over 4 ft from the bottom of the footing
  • Commercial signs, commercial fences, tenant finishes and changes of use
  • Demolition of all or part of a structure

Permit not required

  • A freestanding shed of 120 sq ft or smaller
  • Residential fencing, landscaping and sprinkler systems
  • A new concrete patio, driveway or walk, kept at least 3 ft from property lines for drainage
  • Painting, carpet and flooring
  • Cabinets, shelves and countertops
  • Gutters and storm windows
  • A light fixture, bathroom fan or ceiling fan swapped with no wiring changes
  • A faucet, disposal, tub, sink or toilet replaced in the same spot with no pipe changes
  • An interior door replaced without its frame

The Town’s separate Roofing page defines a roofing permit as replacing more than 200 sq ft of a residential roof covering, so a job between 100 and 200 sq ft is worth an email to the permit technician first. Sheds and patios still have to respect setbacks and easements, typically 5 ft from side and rear lot lines.

Who handles Johnstown building permits?

The Johnstown Building Department administers the Town’s adopted codes. Its Building Permit Technician processes applications and payments and sends out invoices, permit documents and certificates through eTRAKiT. The Town contracts SAFEbuilt for plan reviews and permit inspections and to act as Chief Building Official; that role is held by Jonathan Gesick of SAFEbuilt.

Short on time to read all of this?

Get a free quote →
Johnstown Building Department contacts
DetailInformation
Building Department201 Centennial Drive, Johnstown, CO 80534
Permit processing970-578-9608; BuildingPermits@JohnstownCO.gov
Code, plan review and inspection questions (SAFEbuilt)970-305-3161
Town Hall450 S. Parish Avenue; 970-587-4664; Monday to Friday, 8 am to 5 pm
ApplicationseTRAKiT self-service portal

Town permits apply inside the town limits. Johnstown reaches into both Weld and Larimer counties, and addresses on the Larimer side pay Larimer County use tax with the permit; land outside the limits is permitted by the county it lies in.

Johnstown permit types and eTRAKiT filing

eTRAKiT handles permit applications, contractor licences, invoices, inspection scheduling and inspection results. A resident doing the work personally enters their own details in the contractor section. Permits for new commercial construction cannot be started online and go through the permit technician. Contractors are limited to 5 application submittals a day.

The Town groups its fees and requirements by permit class:

  • Residential New and Commercial New: a building from the ground up.
  • New Apartment: a new multi-family building.
  • Residential or Commercial Alterations/Additions.
  • Residential “Review Not Required”: air conditioning, like-for-like window or door replacement, furnace, roofing, siding, water heater, and water or sewer line upgrades. These pay only the permit fee and use tax.

Contractor licence. Every contractor doing permit-required work in town needs a Johnstown licence, which is also what lets them apply in eTRAKiT. It costs $100 and lasts 365 days. Apply under “Apply for NEW Contractor License/AEC” with a Certificate of Good Standing from the Colorado Secretary of State and an insurance certificate naming the Town of Johnstown, 450 S Parish Ave, as holder. Payment is by credit card and review can take up to 7 days.

All new construction other than a single-family home on a platted lot must finish its approvals and agreements with the Planning and Development Department before a building permit application is submitted.

Johnstown permit fees and use tax

Fees are set by Town Council resolution. The current schedule is the 2026 Fee Schedule, Exhibit A, adopted January 5, 2026; building fees are in its Chapter 18.

Johnstown building permit fee table (2026 Fee Schedule, Sec. 18-121)
Total valuationBase feeAdded for value above the band floor
$1 to $500$23.50Nothing
$500 to $2,000$23.50$3.05 per $100 or fraction
$2,000 to $25,000$69.25$14 per $1,000 or fraction
$25,000 to $50,000$391.25$10.10 per $1,000 or fraction
$50,000 to $100,000$643.75$7 per $1,000 or fraction
$100,000 to $500,000$993.75$5.60 per $1,000 or fraction
$500,000 to $1,000,000$3,233.75$4.75 per $1,000 or fraction
Over $1,000,000$5,608.75$3.65 per $1,000 or fraction

Not sure this scope needs a permit?

Get a free quote →

A $40,000 basement finish, for example, has a permit fee of $391.25 plus 15 × $10.10, which is $542.75. Fees are doubled if construction begins before the permit is issued.

Johnstown plan review, electrical and inspection fees (2026)
ItemFee
Plan review, non-residential65% of the permit fee
Plan review, residential30% of the permit fee
Residential new home or new stock plan review$500
Residential new stock home, basement or alteration$50
Residential addition, detached garage or shed$100
Residential miscellaneous, deck or arbor$20
Plan resubmittal$50
Electrical, residential living space$77 up to 1,000 sq ft; $116 up to 1,500 sq ft; $155 up to 2,000 sq ft; then $6 per 100 sq ft
Electrical, commercial, solar and non-living residential space$77 up to $2,000 of value; then $6 per $1,000
Electric meter, temporary or permanent$38 each
Building re-inspection, after-hours inspection$47 per hour
Electrical re-inspection$50 per hour
Backflow preventer inspection; water or sewer re-inspection$50 each
Temporary Certificate of Occupancy (expires after 6 months)$600
Use tax3.5% on construction materials

Rather talk it over?

Call 1-855-478-4290 →

The schedule lists both a 30% residential plan review rate and flat residential review fees by project type, so the invoice in eTRAKiT is what settles which applies to your job. Get the permit issued before buying materials: the 3.5% use tax is collected with the permit, and the permit receipt shows suppliers that only State sales tax is due. New homes and new commercial buildings also pay water and sewer tap fees, raw water development, a regional park fee and police, public facilities and transportation impact fees, with library and parks impact fees added for homes. Fire and school district fees are paid directly to those districts before the Certificate of Occupancy.

Electrical, plumbing, mechanical and gas in Johnstown

Johnstown issues its own electrical permits. Municipal Code Sec. 18-81, as amended by Ordinance 2025-280 on December 1, 2025, makes the 2023 National Electrical Code the Town’s edition and says a later edition adopted by the State Electrical Board replaces it one year after the State adopts it. The Board adopted the 2026 edition on May 27, 2026, so the 2023 edition remains the Town’s until that year has run; where the Town’s code and the State’s differ, Sec. 18-82 applies the more restrictive, and the Town’s Building Codes page adds that the most current version of the code shall be enforced. The other trades use the 2024 International Plumbing, Mechanical and Fuel Gas Codes. Plumbing work and electrical work are both on the permit-required list, and trade inspections (electrical rough and final, plumbing underground, rough and final, mechanical rough, gas test and final) are scheduled like any other SAFEbuilt inspection.

  • Water heaters and boilers: the application names a plumbing contractor licensed with the Town, or includes proof of ownership if a homeowner is installing it at their own residence, and gives the gallon or BTU size. One plumbing final inspection is required.
  • Gas piping: the owner supplies the gauge and holds the line at 10 psi; the reading must not move. Inspection comes before the piping is covered or an appliance is attached.
  • Drain, waste and vent piping: tested with a 10 ft head of water or 5 psi of air, held for 15 minutes before the inspector arrives.
  • Solar: electrical rough, permanent meter and electrical final inspections, with a structural engineer’s letter for roof-mounted panels.

The Town itself, not SAFEbuilt, inspects water and sewer services, backflow preventers and grease interceptors.

Application documents and review times

All documents are submitted electronically as PDFs. Every residential permit needs the owner’s name and phone number, the owner’s address if different from the job address, and the unit or lot number where there is one. Project pages add the following.

Rather not deal with the building department?

Get a free quote →

Up to 14 business days

  • Addition, basement finish or deck: a drawing of the proposed work
  • Residential solar: full specifications of the photovoltaic system, a site plan showing where it goes, the signed contract with the solar contractor and, for a roof mount, a structural engineer’s letter

Up to 7 business days

  • Roofing: the roof covering material (Class 4 impact shingles are required), the underlayment (ice and water shield barrier is required) and the number of squares
  • Water heater: the plumbing contractor or proof of ownership, and the unit size

The applicant is emailed when the fees are ready to pay. For new buildings, every foundation must be engineered by a Colorado licensed engineer from a soils analysis of the specific site; detached accessory buildings may use a foundation approved by the building official. A parcel touched by the FEMA 100-year floodplain must include a Floodplain Development Permit application with the building permit packet, even if the building footprint is outside the floodplain, and the building permit waits for the Floodplain Administrator’s approval.

How to apply: 6 steps for Johnstown

1. Check the two lists

See whether the job is on the Town’s permit-required list, and ask Planning about setbacks and easements.

2. Finish planning approvals

Anything other than a single-family home on a platted lot needs its Planning and Development approvals and agreements completed first.

3. License the contractor in eTRAKiT

Pay the $100 licence fee and upload the good standing and insurance certificates; owners doing their own work list themselves as contractor.

4. Submit the application

Upload the PDFs the project page asks for; new commercial construction is started with the permit technician.

5. Pay the invoice before buying materials

The invoice carries the permit fee, plan review fee and 3.5% use tax; keep the receipt for your suppliers.

6. Schedule inspections in eTRAKiT

Pick each inspection under the permit’s Inspections tab by 4:00 p.m. on the business day before.

Johnstown inspections and closeout

Since March 1, 2026, every SAFEbuilt inspection for Johnstown has to be requested in eTRAKiT: log in, open the permit from the dashboard, go to the Inspections tab and click Schedule. Some of the Town’s older project pages still give a SAFEbuilt phone number for inspection requests; the Inspections page is the current rule.

Want this handled start to finish?

Get a free quote →
  • Request by 4:00 p.m. on the business day before the inspection. You can book up to 7 days ahead and cancel until 7:00 a.m. on the day.
  • No inspections on weekends or holidays. If a date cannot be picked, it is full.
  • The permit and approved documents must be printed and on site, with every inspection area accessible: snow cleared, a ladder at the crawlspace, the home unlocked and address numbers visible. Otherwise the inspection fails and a $50 re-inspection fee is charged.
  • Results appear in eTRAKiT within 24 hours.
  • Town inspections (water and sewer service, Public Works final, Planning final, demolition final, right-of-way final, backflow and grease interceptor) are requested on the Town Inspection Request Form by 4 p.m. the business day before; water and sewer inspections need 24 to 48 hours’ notice.

Before the first inspection. A soils engineer inspects the open excavation and gives the building inspector a soils report. Property pins must be found, and strings pulled between them if the structure is within 6 ft of a property line. No concrete is poured before footing or wall forms are approved. At the frame inspection the house is weather-tight, the roofing is on and the plumbing, heating and rough electrical are already approved. The final comes after finish grading and the electrical final, and a Certificate of Occupancy follows; none is issued for accessory structures such as garages.

Local Johnstown details that matter

Design criteria from January 1, 2026. Ground snow load 30 psf, design wind speed 115 mph, seismic design category B and a 30-inch frost line. Ice barrier underlayment is required.

Impact-rated roofs. A re-roof application has to show Class 4 impact shingles and an ice and water shield underlayment, and a secured ladder is required at the roof final.

Location-based fees. Depending on the address, a permit can also carry Regional Sewer, West Water Tank, 402 Tier 1 or Tier 2, or High Plains Boulevard fees. The Building Department will check an address if you email it.

Water meters. A new meter is requested on the Town’s new meter installation form once all the necessary inspections have passed.

Other codes. The Town lists the Colorado Wildfire Resiliency Code and the Colorado Model Electric and Solar Ready Code alongside its 2024 International Codes.

Colorado building code

Colorado has no statewide building code for private buildings: each city and county decides whether a code applies and which edition, while the state sets electrical and plumbing rules, a minimum energy code on any update, and a wildfire code for the mapped wildland-urban interface. Building codes in Colorado

Inspections are where schedules slip.

Get a free quote →

Official Johnstown permitting resources

Johnstown building permit FAQs

Who issues building permits in Johnstown?

The Town of Johnstown Building Department, through eTRAKiT. SAFEbuilt reviews the plans and carries out most inspections under contract to the Town.

How much is a building permit in Johnstown?

It follows the valuation table in the 2026 Fee Schedule: a $40,000 basement finish is $542.75, plus plan review and 3.5% use tax on materials. Non-residential plan review is 65% of the permit fee.

Do I need a permit for a shed or fence in Johnstown?

Not for a freestanding shed of 120 sq ft or smaller, or for residential fencing. Commercial fences need a permit.

How long does a residential permit take?

Up to 7 business days for roofing and water heater permits and up to 14 business days for decks, additions, basement finishes and solar.

How do I schedule an inspection?

In eTRAKiT, by 4:00 p.m. on the business day before, up to 7 days ahead.

Do contractors need a Johnstown licence?

Yes. It costs $100 a year and is applied for in eTRAKiT.

Does Johnstown issue electrical permits?

Yes. A home up to 1,000 sq ft of living space pays $77, rising to $155 at 2,000 sq ft, plus $38 for each meter.

What happens if I start without a permit?

The fee schedule doubles the fees when construction begins before the permit is issued.

Simplify Johnstown permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Colorado. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Johnstown sooner?

Let Alliance prepare, file, and track your Johnstown permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Johnstown permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.