Inside the City of Susanville, the city’s Building Division at City Hall, 66 North Lassen Street (530-252-5118), issues building permits and the electrical, plumbing and mechanical permits that go with them, reviews plans and inspects the work; Dow Davis is the Building Official. Applicants file at the Building and Planning counter. Under the fee schedule set by Resolution No. 24-6362, plan review is 65% of the building permit fee, each trade carries a $54 application fee, and the minimum permit fee is $64.
What requires a building permit in Susanville?
The city requires a building permit to erect, enlarge, alter, repair, move, improve, convert or demolish a building or structure, and that includes plumbing, mechanical and electrical changes. Its FAQ gives examples: new homes, room additions, decks and patios, garage conversions, retaining walls, window replacement, fire and wood stove replacements, new roofs and siding, and new or changed signs. Work caught without a required permit is charged a double penalty.
Permit required
- New homes, additions and garage conversions
- Decks, patios and retaining walls
- Re-roofing, siding and window replacement
- Wood stove and fireplace replacement
- Electrical, plumbing and mechanical work
- Demolition of all or part of a building
- New signs and changes to existing signs
No permit
- One-story detached sheds and playhouses up to 120 square feet
- Fences not over 6 feet high
- Retaining walls up to 4 feet, measured from the bottom of the footing, unless holding a surcharge
- Sidewalks and driveways not over 30 inches above grade and not part of an accessible route
- Painting, papering, tiling, carpeting, cabinets and countertops
- Above-ground prefabricated pools under 24 inches deep and 5,000 gallons at a house
- Swings and play equipment, and wall-supported awnings projecting up to 54 inches
Removing or moving a wall during a remodel does not need a demolition permit, but it does need a building permit.
What Susanville decides and what the state holds
The city sets design values for its climate under Ordinance No. 99-860: a ground snow load of 86 pounds per square foot west of Roop Street and in the Maurino Manor Subdivision and 58 east of Roop Street, a 110 mph wind speed with Exposure B and C, climate zone 16, seismic design category D and a 20-inch frost depth. It also sets its fees, zoning and frontage-improvement rules and owns the city water and natural gas systems. Contractor licensing is a state matter.
Susanville building department: who handles permitting
The Building Division processes and issues permits for new development and renovation, reviews plans for compliance with state and city codes, and inspects the work. The Planning Division in the same building reviews land use, zoning and design. Everything outside the city limits in Lassen County is permitted by the county’s Planning and Building Services Department at 707 Nevada Street, Suite 5.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Building Division, City Hall, 66 North Lassen Street, Susanville, CA 96130 |
| Building Official | Dow Davis, 530-252-5116 |
| Permit counter | 530-252-5118; fax 530-257-4725 |
| Hours | Monday to Friday, 8:30 a.m. to 4:30 p.m. |
| Planning Division | 530-252-5117 (zoning verification from the City Planner) |
| Public Works | Right-of-way encroachment permits and the city water and natural gas systems, 66 N Lassen Street; utility billing 530-252-5111 |
| Outside the city | Lassen County Planning and Building Services |
Susanville permit types
One building permit application covers building, electrical, mechanical and plumbing work; the form asks whether the structure is a manufactured home or commercial, and records zoning, flood plain and occupancy. The Building Division also publishes a new construction submittal checklist, a generator installation sheet, an EV charging permit checklist, a subcontractor list and a smoke and carbon monoxide alarm self-verification form.
Residential permits
- New homes and additions need four complete, legible plan sets plus an assessor’s floor plan and an 11 by 14 set, with structural and energy calculations, truss calculations and, where needed, wall bracing design. Where the ground snow load exceeds 50 pounds per square foot, a licensed professional must prepare the construction documents.
- Fire sprinklers in one- and two-family homes and manufactured homes follow the city’s residential sprinkler standard: installers hold a C-16 license, or C-36 and C-16 for combined systems, with a limited owner-builder exception for 13D systems.
- Demolition needs the asbestos declaration required by state law, and pre-1978 buildings must be tested for lead-based paint, with abatement above set areas.
Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
Commercial work and any change of occupancy need plans prepared by a California design professional showing existing conditions and the changes needed for full code compliance, including occupancy, construction type, exits, accessibility and plumbing fixture counts; a change that moves a building into a higher risk category must meet the seismic requirements for a new structure in that category. A change of occupancy needs the Building Official’s approval and cannot proceed until the building meets current code for the new use. Where the use changes but the hazard level stays the same and nothing has to be added, the FAQ asks for two sets of life safety plans instead; where a tenant improvement is needed, the commercial plan check route list sets the number of sets. Fire Department plan check and application fees of $87 each apply where the fire department reviews the work.
Not sure this scope needs a permit?
Get a free quote →For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Planning approval: land use and zoning must be approved before building plans are submitted; architectural design and site plan review, administrative permits and conditional use permits are priced in the planning fee table below.
- Frontage improvements: additions or improvements over $50,000 within three years trigger curb, gutter, sidewalk and driveway installation under Section 12.20.010, with a Public Works right-of-way encroachment permit and deposit before the building permit is issued.
- Floodplain: work in a mapped flood area needs the city’s floodplain permit, and the building permit application records the flood plain status.
- Historic buildings: the Planning Division keeps a historic building review application, and placement on the historic building site registry is $126.
Susanville building permit fees
Building Division fees are set by Resolution No. 24-6362, posted as the Building Division fee schedule for 2024 and 2025. Building permit fees themselves depend on the work, and the city says construction costs vary with the type of work; plan review is 65% of the building permit fee unless the schedule says otherwise, and outsourced structural review can add more.
| Item | Fee |
|---|---|
| Minimum permit fee | $64 |
| Minimum permit fee, electrical, mechanical or plumbing | $129 |
| Application fee, per trade (building, electrical, mechanical, plumbing) | $54 |
| Plan review | 65% of the building permit fee |
| Demolition permit | $149 plus $54 application fee and SB 1473 fee |
| Plan revisions | $52 plus $79 an hour after the first half hour |
| Expedited plan review | $193 |
| Re-inspection | $87 |
| Temporary certificate of occupancy | $111 for the first 30 days |
| Sign permit / copy change only | $203 plus $50 application fee / $59 |
| Reissue an expired permit | $203 minimum plus $54 application fee |
| Fire Department plan check / application | $87 / $87 |
| Site improvement plan review | $1,000 deposit, hourly fees plus 15% |
| SB 1473 green building fee | $1 per $25,000 of valuation or portion |
Rather talk it over?
Call 1-855-478-4290 →Worked example: demolishing a small detached building valued under $25,000 costs the $149 demolition fee, the $54 application fee and $1 for SB 1473, a total of $204 before any seismic fee or separate trade disconnects.
| Item | Fee |
|---|---|
| Administrative permit | $217 |
| Architectural design and site plan review, under / over 1,000 sq ft | $113 / $1,343 |
| Residential conditional use permit, proposed (fences, signs, gray water systems) | $522 |
| Conditional use permit, minor / moderate / major | $1,494 / $1,760 / $2,314 |
| Variance, proposed development | $783 |
| Home occupation permit | $105 |
| Floodplain permit | $239 |
| Lot line adjustment or lot merger | $706 |
| Tentative parcel map (four or fewer lots) | $1,526 |
New homes also pay parkland dedication fees, which vary by type of construction, and the state seismic fee applies to new construction or changes to a building’s lateral load system. Projects in the Skyline Terrace area and on parts of Riverside Drive carry additional fees, so ask the counter for those before you budget. A lit sign also needs an electrical permit on top of the sign permit fee.
Trade permits and who may pull them in Susanville
The Building Division issues electrical, mechanical and plumbing permits on the same application as the building permit, each with its own $54 application fee and a $129 minimum when issued alone. Generator installations follow the city’s generator requirements sheet, and EV chargers its EV checklist.
Rather not deal with the building department?
Get a free quote →Contractors need the correct state CSLB license, and the city’s business license application lists contractors as a business type, with the $4 state SB 1186 fee added to every license; the form also lists a fire inspection ($82) and a home occupation permit ($90) where they apply, and extra fees for businesses in the uptown HUSA area. Homeowners can act as owner-builders under state law; for fire sprinklers, the city’s handout allows owner-builders to install only 13D systems that meet the state owner-builder rules. The application asks for the project value and the floor area of the building, garage and other space, which set the fees.
How to apply for a Susanville building permit
Confirm the use and setbacks with the Planning Division and get any design review or use permit approved first.
If improvements will pass $50,000 within three years, arrange the curb, gutter and sidewalk work and encroachment permit with Public Works.
Use the plan check submittal form: four legible sets no larger than 24 by 36 inches, wet-signed on every page, with architect or engineer seals where required.
Bring the building permit application and plans to the Building and Planning counter at 66 North Lassen Street.
Pay the plan review, permit and trade application fees the counter calculates, and collect the issued permit.
Ask the permit counter at 530-252-5118 how to request inspections for your permit.
Review, corrections and what causes delay
The city says plan sets missing site, architectural or structural plans, or structural and energy calculations, are treated as incomplete and handed back for resubmittal. Illegible plans are not accepted. Every plan set needs a site plan showing the assessor’s parcel number, project and owner names with contact details, full lot dimensions with bearings and distances, a north arrow, any Planning Division or use permit conditions and the driveway; the preferred scales are 1/4 inch per foot for architectural and structural sheets and 1 inch to 20 feet for site plans. Revisions cost $52 plus $79 an hour after the first half hour, and expedited plan review is available for $193. The city publishes no standard review time.
Susanville building inspections
Building inspectors check new development and renovation work against the approved plans at each stage; the city does not publish a separate inspection request line, so ask the permit counter at 530-252-5118 how to book them when the permit is issued. A failed inspection that needs a return visit costs $87. A temporary certificate of occupancy is $111 for the first 30-day period, and an expired permit can be reissued for a minimum of $203 plus the application fee.
For one- and two-family homes the city provides a smoke detector and carbon monoxide alarm self-verification form. Residential fire sprinkler systems are inspected under the city’s sprinkler standard, and every demolition applicant completes the asbestos declaration with the application.
Want this handled start to finish?
Get a free quote →California building code in Susanville
Susanville applies the California Building Standards Code with its own Title 15 (Buildings and Construction) in the municipal code. The Building Division page still lists the 2019 California Building Code and the plan check form the 2022 editions; applications filed since January 1, 2026 fall under the 2025 code, so ask the Building Official which Title 15 amendments apply. FEMA’s Community Status Book lists the City of Susanville (community 060093) as participating in the National Flood Insurance Program, with flood maps effective September 3, 2010.
California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Susanville permit search and official resources
Requests for copies of permits, plans and inspection records go through the city’s online public records portal, linked from the Building Division and Public Works pages, or ask the Building Division at 530-252-5118.
- Susanville Building Division
- Building permit FAQs
- Building Division fee schedule, Resolution 24-6362
- Building permit application
- Plan check submittal requirements
- New construction submittal checklist
- Residential fire sprinkler standard
- Demolition permit handout
- Planning Division
- Planning Division fees, Resolution 25-6446
- Business license application
- FEMA Community Status Book, California
Inspections are where schedules slip.
Get a free quote →Susanville building permit FAQs
Where do I apply for a building permit in Susanville?
At the Building and Planning counter in City Hall, 66 North Lassen Street, open Monday to Friday from 8:30 a.m. to 4:30 p.m.
Do I need a permit for a fence?
Not for a fence of 6 feet or less; taller fences need a permit.
Do I need a permit for a shed?
Not for a one-story detached shed or playhouse of 120 square feet or less.
How much is plan check?
65% of the building permit fee, plus a $54 application fee for each trade on the permit.
What snow load do I design for?
86 pounds per square foot ground snow load west of Roop Street and in Maurino Manor, and 58 east of Roop Street; above 50 a licensed professional must prepare the plans.
Will my remodel trigger sidewalk work?
If additions or improvements exceed $50,000 within three years, the city requires curbs, gutters, sidewalks and driveways along the frontage, with a Public Works encroachment permit first.
Does Susanville issue permits outside the city?
No. Lassen County Planning and Building Services permits everything outside the city limits.
Simplify Susanville permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Susanville sooner?
Let Alliance prepare, file, and track your Susanville permits while your crew stays on the job.
More California permitting guides
Lassen County
Read guide →Shasta County
Read guide →Lake County
Read guide →Sutter County Building Permit Guide
Read guide →Tehachapi Building Permit Guide
Read guide →Tehama County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Susanville permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.