Riverside, California Building Permit Guide

Riverside’s Building & Safety Division works from the One Stop Shop on City Hall’s third floor, takes applications in the Public Permit Portal and publishes tiered plan check turnaround times.

Authority: Building & Safety DivisionPortal: Public Permit PortalPhone: (951) 826-5697
Building & Safety
(951) 826-5697Mon–Fri 9:00 am – 4:00 pm; Wed from 10:00 am
One Stop Shop
951-826-5800City Hall, 3rd Floor
Inspection line
(951) 826-5361Before 5:00 pm for the next business day
Permit issuance fee
$41.00Schedule of July 1, 2026

Building permits in the City of Riverside are issued by the Building & Safety Division of the Community & Economic Development Department at City Hall, 3900 Main St., 3rd Floor, Riverside, CA 92522. The One Stop Shop on that floor puts planning, building, fire, utilities, business license and public works staff on one floor.

This guide covers Riverside’s Building & Safety Division, its July 1, 2026 fees, plan check times, inspections and the Planning and Public Works permits that go with a building permit.

What requires a building permit in Riverside?

Planning Division clearance is required for most building permit applications before they go to Building & Safety. Some permits are issued the same day over the counter, such as simple water heater change-outs, residential service meter upgrades, reroofs, re-stucco and simple patio covers. Work in streets, alleys and easements needs a Public Works construction permit or street opening permit.

California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments

Short on time to read all of this?

Get a free quote →

Who handles permitting in Riverside?

Riverside permit contacts
OfficeHandlesContact
Building & Safety DivisionBuilding permits and inspections; City Hall, 3900 Main St., 3rd Floor, Riverside, CA 92522; counter Monday - Friday 9:00 am – 4:00 pm, Wednesday 10:00 am – 4:00 pm(951) 826-5697
One Stop ShopPlanning, building, fire, utilities, business license and public works staff on the third floor951-826-5800
Planning DivisionClearance before most building permit applications826-5371
Public WorksConstruction and street opening permits for streets, alleys and easementsPublic Works permitting page

Riverside permit costs and fees

Building and Safety fee schedule dated July 1, 2026:

  • Permit issuance $41.00; building plan check and building inspection $87.00 per hour; reinspection $98.00.
  • Residential tear-off and re-roof up to 1000 SF: $61.50 plan check and $61.50 permit, plus $12.50 for each additional 500 SF.
  • Expedited solar energy system up to 38 KW: $100.50.
  • A 10% General Plan Maintenance surcharge and a 4% Technology surcharge are added to all plan check and permit fees.
  • Expedited after-hours plan review: $160/hour for a Senior Plan Check Engineer and $131/hour for a Senior Plans Examiner.

Not sure this scope needs a permit?

Get a free quote →

How to get a building permit in Riverside

1. Get Planning clearance

Required for most building permit applications; Planning Division 826-5371.

2. Apply in the Public Permit Portal

Applications, electronic plans and fee payments go through the portal, run on the POSSE Land Management System; projects already in Project-Dox electronic review continue there.

3. Allow for review

Bulletin #137 (issued 3/27/26): a completeness check of 1–3 business days, then 5, 10 or 20 working days for Tier 0, Tier 1 or Tier 2 first submissions.

4. Use a faster route if eligible

Residential solar PV under 10kWDC is reviewed within 3 working days under the Express Solar Permitting Program. Under the Self-Certification Pilot Program, California-licensed architects and engineers certify eligible plans and the permit is issued within 5 business days of a complete application.

5. Get Public Works permits

A street opening permit can usually be obtained within 7 to 10 business days of submittal; Public Works permits are valid for one year.

For ADUs, Dwell Riverside offers permit-ready plans of 746, 800, 1,020 and 1,200 sq. ft., each in Craftsman, Ranch and Spanish styles.

Rather talk it over?

Call 1-855-478-4290 →

A building permit carries a validity period and can expire if work does not start or stalls between inspections; confirm the expiry with Riverside on phased or delayed work. Permit validity in California

Inspections in Riverside

Inspections can be requested on the Automated Inspection Request Line, (951) 826-5361, with the permit number and the 3-digit inspection code; in most cases requests received before 5:00 pm are scheduled for the following business day. To arrange an approximate time, call between 7:30 am and 8:00 am on the morning of the inspection. Area inspectors keep office hours at City Hall from 7:30 - 8:00 am and 4:00 - 4:30 pm.

RMC 7.35.010 limits construction to Monday – Friday 7:00 am to 7:00 pm and Saturdays 8:00 am – 5:00 pm, with no work on Sundays or federal holidays.

Local design criteria in Riverside

Riverside’s local design criteria classify most of the city as wind exposure category C and use 2 inches per hour for roof drainage design.

Official Riverside permitting resources

These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.

Rather not deal with the building department?

Get a free quote →

Want this handled start to finish?

Get a free quote →

Frequently asked questions

How do I request a building inspection in Riverside?

Call the Automated Inspection Request Line at (951) 826-5361 with the permit number and 3-digit inspection code; requests received before 5:00 pm are usually scheduled for the next business day.

How long is plan check in Riverside?

Under Bulletin #137, first submissions take 5, 10 or 20 working days for Tier 0, Tier 1 and Tier 2 projects, after a completeness check of 1–3 business days.

Does Riverside have ready-made ADU plans?

Yes. Dwell Riverside offers permit-ready ADU plans of 746, 800, 1,020 and 1,200 sq. ft., each in Craftsman, Ranch and Spanish styles.

Simplify Riverside permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Inspections are where schedules slip.

Get a free quote →
  • Confirm the city’s planning, building, fire and public works reviews the project needs
  • Prepare the application and plans for the city’s portal or counter and track each review cycle
  • Schedule inspections and gather the clearances needed to close the permit

Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Riverside sooner?

Let Alliance prepare, file, and track your Riverside permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Riverside permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.