Inside Los Gatos, the town’s Building Division at 110 East Main Street (408-354-6876) reviews plans and issues building, electrical, plumbing and mechanical permits. Applications start as pre-applications in the Accela Citizen Access portal, and simple residential jobs such as water heaters and panel upgrades can be permitted online. Under the FY 2026-2027 fee schedule, plan review is 65% of the building permit fee and is charged when the application is filed.
What requires a building permit in Los Gatos?
The town’s rule is that a building permit is needed for any erection, installation, extension, repair or material alteration of a building. Its permit-application page adds that all mechanical, electrical and plumbing work needs a trade permit, from furnace and new AC installations to new circuits, service upgrades, water heaters, re-pipes and water or sewer line replacement.
Permit needed (examples)
- New homes, additions and remodels, including non-structural kitchen and bath remodels
- Decks, porches, stairs and guardrails above the exemption limits
- Pools and spas, and pool demolition
- Retaining walls over 4 feet, generators, EV chargers and solar
- Window replacement and re-roofing, which in an HOA or historic district also need HOA and Planning approval
- Furnace and AC changes, water heaters, panel upgrades and re-pipes
No building permit (town handout)
- One-story detached accessory structures up to 120 sq ft
- Fences up to 7 feet, within the town fence ordinance
- Retaining walls up to 4 feet, measured from the bottom of the footing, with no surcharge
- Sidewalks and driveways (an Engineering encroachment permit may be needed)
- Painting, tile, carpet, cabinets and countertops
- Detached decks up to 200 sq ft and 30 inches above grade that do not serve the required exit door
Fence height is also limited by the Town Code fence ordinance: 6 feet plus 1 foot of lattice (7 feet total) in most of town, 6 feet in the hillside area, and 3 feet in a front or street-side yard, driveway view area or corner sight triangle. Barbed, razor, electric and transparent fences are prohibited, hillside lots of an acre or more need wildlife-friendly perimeter fencing, and exceptions up to 8 feet require a Community Development Director approval and fee.
What Los Gatos decides and what the state holds
The Town Council adopted local amendments to the 2025 codes on December 2, 2025 in Ordinance 2380, effective January 1, 2026 once approved by state agencies. They include reach codes requiring an AC-to-heat-pump switch when an existing home’s air conditioner is replaced and electric-ready pre-wiring when gas or propane equipment is installed in a remodel or addition of an existing single-family home. The ordinance also requires a Class A roof on every new structure, on roof repairs and alterations, and wherever more than half a roof is replaced in a year. The town adopted its own Fire Hazard Severity Zones map by Ordinance 2374 on June 17, 2025.
Short on time to read all of this?
Get a free quote →Los Gatos building department: who handles permitting
The Building Division in Community Development reviews plans for new construction, additions and remodels, and inspects all permitted work, including electrical, plumbing and mechanical installations, for property in the town’s jurisdiction. The Chief Building Official is Robert Gray; appointments with the Building Official are offered from 1 to 4 p.m., and inspectors meet by appointment only.
| Detail | Information |
|---|---|
| Office | Building Division, 110 E. Main Street, Los Gatos, CA 95030 |
| Phone and email | 408-354-6876, Building@losgatosca.gov |
| Counter | Monday to Friday, 8 a.m. to 1 p.m. (phones 7:30 a.m. to 4 p.m.) |
| Inspection request line | 408-354-6877 (24-hour voicemail); inspectors take calls 7:30 to 8 a.m. |
| Fax | 408-354-7593 |
| Portal | Accela Citizen Access (Online Permits System) |
Los Gatos permit types
Every application needs the Building Division Permit Application, with a separate mechanical, electrical and plumbing application for combination or trade permits. Submittals and resubmittals are made through the portal; the division does not accept plan sets sent by FedEx, UPS or other couriers.
Residential permits
- Online permits. Owners and contractors can create five residential permits themselves in the Online Permits System: panel upgrades up to 200 amps, copper re-pipes, water heater replacements of the same type and location, water line repair or replacement, and furnace and AC replacement in the same location. Inspections for these can be booked there too.
- Solar. Residential rooftop solar is permitted through SolarAPP+, which then hands off to the town’s Residential SolarAPP+ permit page.
- Plan-check projects. The town publishes submittal requirements for new homes, additions and remodels, pools, decks and stairs, generators, EV chargers, retaining walls and an express check for non-structural kitchen and bath remodels.
- Drawings for some trade jobs. Relocating a furnace or water heater, or switching to tankless, needs a drawing; rooftop AC units need Planning and HOA approval.
Building or remodeling a home here? Alliance handles residential permit filing, so the crew isn't waiting on the counter.
Commercial permits
Commercial shell buildings and tenant improvements have their own submittal requirements. Office tenant improvements use a lower valuation modifier (1.16) in the fee schedule, and commercial demolition costs $583.
For tenant improvements and new commercial builds, Alliance handles commercial permit expediting through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Planning. Projects needing zoning or architectural approval, and HOA or historic-district window and roof jobs, must clear the Planning Division first.
- Fire sprinklers. Under Ordinance 2380, new buildings with a residential (Group R) fire area must be sprinklered, with an exception for ADUs up to 1,200 sq ft where the main house has no sprinklers and other conditions are met; additions that push an existing home’s fire area over 3,600 sq ft also trigger sprinklers unless the addition is 500 sq ft or less and meets water supply rules.
- Sewer. Sewer line replacement may also need a West Valley Sanitation District permit.
- Right-of-way. Driveways and sidewalks may need an Engineering encroachment permit.
Los Gatos permit costs and fees
Fees come from the Development Services section of the town’s FY 2026-2027 Comprehensive Fee Schedule. For new construction and additions, valuation uses ICC building valuation data with a regional modifier of 2.32 (3.246 for hillside homes), raised each year by the ENR building cost index; for remodels the Building Official sets the valuation. The permit fee then comes from the valuation table below.
| Valuation | Permit fee |
|---|---|
| $1–$500 | $41 |
| $501–$2,000 | $41 plus $5.36 per $100 over $501 |
| $2,001–$25,000 | $122 plus $24.63 per $1,000 over $2,001 |
| $25,001–$50,000 | $688 plus $17.76 per $1,000 over $25,001 |
| $50,001–$100,000 | $1,131 plus $12.33 per $1,000 over $50,001 |
| $100,001–$500,000 | $1,749 plus $9.84 per $1,000 over $100,001 |
| $500,001–$1,000,000 | $5,688 plus $8.35 per $1,000 over $500,001 |
| Over $1,000,000 | $9,866 plus $5.54 per $1,000 over $1,000,001 |
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee |
|---|---|
| Plan review | 65% of the building permit fee, at filing |
| Title 24 energy and accessibility surcharge | 15% of the building permit fee when plan review applies |
| Issuing a building, electrical, mechanical or plumbing permit | $68 each |
| Trade plan review | 25% of the trade permit fee |
| Demolition | $333 residential, $583 commercial |
| Re-inspection | $199 an hour |
| Express plan review | $199 an hour, 1-hour minimum |
| Permit or plan check extension | $98 |
| Stormwater (NPDES) inspection, permits that may cause runoff | $88 |
| Temporary certificate of occupancy | $1,373 |
| Capital improvement / underground utility / park taxes | $0.18 / $0.18 / $0.04 per sq ft of added floor area |
Worked example from the schedule: a $200,000 addition falls in the $100,001–$500,000 band, so the permit fee is $1,749 plus 100 × $9.84, or $2,733. Plan review at 65% adds $1,776.45 and the 15% Title 24 surcharge $409.95, before the $68 issuing fee, trade permits, state fees and the per-square-foot taxes.
The schedule also prices common items for valuation: $147 per sq ft for a garage conversion to living space, $3.54 per sq ft for re-roofs, $26 per sq ft for a wood deck and $134 per sq ft for retaining walls. Refunds of 80% of permit fees are possible within one year if no work or inspection has taken place; plan check fees are refundable at 80% only before review begins.
Trade permits and who may pull them
Electrical, mechanical and plumbing permits are issued by the Building Division, each with a $68 issuing fee plus unit fees from the schedule, such as $40 for a water heater and $144 for re-piping a house, and plan review at 25% of the trade fee where plans are needed. Five common residential trade jobs can be permitted online by owners or contractors.
- Business license. Contractors must hold a current Town of Los Gatos business license to obtain permits.
- Heat pumps. Under the town’s reach code, replacing an existing home’s air conditioner triggers the AC-to-heat-pump requirement, so plan the equipment before applying.
- Fire. The Building Division’s list of partner agencies points to the Santa Clara County Fire Department for fire matters.
Rather not deal with the building department?
Get a free quote →How to apply for a Los Gatos building permit
Use the town’s Permit Decision Tool, and check with Planning, your HOA or the historic rules where they apply.
Create an Accela Citizen Access account with your email, or log in through Manage My Records.
Upload the application forms, plans and documents listed in the Plan Check Submittal Requirements; staff check the file is complete.
Once complete, the file becomes a full application and you pay online by card, by mailed check or at the counter between 8 a.m. and 1 p.m.
Receive comments and marked-up plans and upload resubmittals in the portal; staff encourage working through issues by email.
Once the review is approved the permit is issued, and inspections are then booked in the portal or by phone.
Review, corrections and what causes delay
Review does not begin until the pre-application is complete, so a missing item from the submittal list delays the start. Changes to approved plans must be submitted by your design professional and approved before the work is altered, and extra plan review for revisions is billed at $190 an hour with a one-hour minimum. Express or initial plan review is available at $199 an hour with a one-hour minimum, and outside consultants used for plan checking are billed at actual cost. A permit or plan check that has not expired can be extended for $98.
Inspections in Los Gatos
Inspections run Monday to Friday from 8 a.m. to 3 p.m., excluding holidays. Requests can be made around the clock but must be in by noon for the next business day. Book online in the Online Permits System (search your permit number, such as B18-0001, and choose Schedule or Request an Inspection), by voicemail at (408) 354-6877, or by fax at (408) 354-7593.
- Voicemail details. Leave the inspection type, requested date with a.m. or p.m. preference, permit number, street address and a contact name and phone; incomplete requests are not scheduled. The inspector calls the afternoon before to confirm.
- Time windows. Mornings usually run 8 a.m. to noon and afternoons noon to 3 p.m., but the windows are estimates only; do not call inspectors directly to schedule.
- Re-inspections are charged at $199 an hour, and inspections outside normal hours at $240 an hour with a four-hour minimum.
- Construction hours are Monday to Friday 8 a.m. to 6 p.m. and Saturday 9 a.m. to 4 p.m., with no construction on Sundays or town holidays.
California building code in Los Gatos
Los Gatos enforces the 2025 California codes as amended by Ordinance 2380, including its reach codes, sprinkler rules and Class A roofing rule; the Building FAQ still describes the 2022 codes, so rely on the Current Adopted Codes page. FEMA’s Community Status Book lists the Town of Los Gatos (community 060343) as participating in the National Flood Insurance Program, with a current flood map dated February 19, 2014.
Want this handled start to finish?
Get a free quote →California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Los Gatos building permit FAQs
Who issues building permits in Los Gatos?
The Town of Los Gatos Building Division at 110 East Main Street (408-354-6876) for property in the town’s jurisdiction.
Can I get a permit online?
Yes for five residential jobs: panel upgrades up to 200 amps, copper re-pipes, like-for-like water heaters, water lines, and furnace and AC replacements in the same place. Everything else starts as a pre-application in Accela.
How much does a building permit cost in Los Gatos?
It follows the valuation table. A $200,000 addition has a $2,733 permit fee, plus $1,776.45 plan review and a $409.95 Title 24 surcharge, then issuing fees and taxes.
How tall can my fence be without a permit?
A fence up to 7 feet needs no building permit, but the fence ordinance caps most fences at 6 feet plus 1 foot of lattice, 6 feet on hillsides and 3 feet in required front or street-side yards and view areas.
Do I have to install a heat pump?
Under the town’s reach code, replacing an existing single-family home’s air conditioner triggers the AC-to-heat-pump requirement.
When must I book an inspection?
By noon for the next business day, online, by voicemail at (408) 354-6877 or by fax.
Can I drop off plans by courier?
No. The Building Division does not accept submittals or resubmittals by FedEx, UPS or other couriers; use the portal.
Los Gatos permit search and official resources
Pending and issued building permits from 1994 on can be viewed online without registering. Older permit history is kept on Laserfiche and microfiche at the Building Division counter, open 8 a.m. to 1 p.m. on weekdays. The town also posts monthly issued-permit reports.
Inspections are where schedules slip.
Get a free quote →- Los Gatos Building Division
- Online Permits System (Accela)
- Permit applications
- Plan check submittal requirements
- Work exempt from permits and fence ordinance
- Inspection request information
- FY 2026-2027 development permit fees
- Current adopted codes and reach codes
- Ordinance 2380, 2025 building codes
- Local Responsibility Fire Hazard Severity Zones
- Monthly issued permits
- Building staff directory
- 2025 California Title 24 building standards
- FEMA Community Status Book, California
Simplify Los Gatos permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Los Gatos sooner?
Let Alliance prepare, file, and track your Los Gatos permits while your crew stays on the job.
More California permitting guides
Santa Clara County
Read guide →Milpitas
Read guide →Morgan Hill
Read guide →Lynwood Building Permit Guide
Read guide →Madera Building Permit Guide
Read guide →Madera County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Los Gatos permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.