Randolph County has adopted no building code, building permit or zoning for unincorporated land; its County Engineer handles subdivisions, flood-zone permits and driveway pipes.

Authority: No county building permit; County Engineer for flood, subdivision and logging permitsCounty code: None adopted by the CommissionPhone: 256-357-2311
County building permit
NoneThe Commission has adopted no building codes or permit requirements
County Engineer
256-357-2311108 Woodland Ave. West, Wedowee
Zoning
None outside the townsApplies outside municipal limits and police jurisdictions
Septic
Randolph County Health DepartmentEnvironmental health: 334-863-8981

The Randolph County Commission says in its Zoning & Permitting memorandum that it has not adopted any building codes or permit requirements, and that no zoning applies to unincorporated land outside municipal limits and police jurisdictions. Three things still go through the County Engineer (256-357-2311): dividing land into subdivision lots, building in a flood-prone area, and harvesting timber. Septic certifications come from the Randolph County Health Department (334-863-8981). Inside Roanoke, Wadley, Wedowee and Woodland, the town’s own rules apply.

What approvals does Randolph County require?

The county memorandum is short and direct about what applies on unincorporated land.

Required through the county

  • Permit to Develop in a Special Flood Hazard Area, for homes or businesses in a flood-prone area
  • Subdivision approval, for dividing land into subdivision lots
  • Logging permit, for harvesting timber
  • Driveway pipe evaluation by the Highway Department before a pipe goes in on a county road
  • Septic tank certification from the Health Department

Not required by the county

  • A county building permit
  • County plan review or building inspections
  • Zoning approval, outside municipal limits and police jurisdictions

The Commission asks anyone who builds a new home or installs a new structure to tell the Revenue Commissioner’s Appraisal Office (256-357-4343, ext. 402), so that tax exemptions are in place and unreported buildings are not back-taxed.

Who issues building permits in Randolph County?

Nobody at county level. The 4 incorporated places each handle their own territory, and they publish different amounts.

Short on time to read all of this?

Get a free quote →
Building permits in Randolph County by place
PlaceWho issues building permitsContact
RoanokeCity of Roanoke; building permit applications are obtained at City Hall, and business locations are approved by the Zoning Administrator. The zoning ordinance, which covers all land inside the corporate limits, is enforced by the Building Inspector, who issues a zoning permit once the application and plans have been reviewedCity Hall, 809 Main Street, 334-863-4129; 8:00 a.m. to 5:00 p.m., Monday to Friday
WadleyTown of Wadley; a Zoning Permit from the Enforcement Officer (the Building Inspector) is required before constructionTown Hall, 265 Highland Circle, (256) 395-2261; 7:30 AM to 4:00 PM
WoodlandThe town publishes a $50 mobile home placement permit and a contractor licence rule, and nothing else on building permits; ask Town HallTown Hall, 120 County Road 64, 256-449-2222
Wedowee (county seat)The Town publishes no permit procedure. The Division G hazard mitigation plan lists a zoning ordinance in Wedowee and no code enforcementTown Hall, (256) 357-2122
Unincorporated Randolph CountyNo building permit. County Engineer for flood, subdivision and logging permits108 Woodland Ave. West, Wedowee, 256-357-2311

Chris Gann is the County Engineer. The Commission Office is at 12 East Broad Street Southeast, Wedowee (256-357-4980).

Randolph County permits and forms

The Highway Department page carries the county’s permit documents:

Not sure this scope needs a permit?

Get a free quote →
  • Application for Permit to Develop in a Special Flood Hazard Area. Filed with the Floodplain Administrator at the County Engineer’s office, with a location map, plans detailing the building site and the flood hazard parameters. It covers residential, non-residential and accessory structures, fill, manufactured home installation and substantial improvements.
  • Flood Damage Prevention Ordinance.
  • Private Subdivision Regulations and the county’s subdivision specifications.
  • Logging Permit and overload permit.
  • Driveway Pipe Policy, approved by the Commission on February 24, 2025.

Business licences for the county are issued by the Probate Judge’s office (256-357-4933).

Fees in Randolph County

With no county building permit there is no county building permit fee, plan review fee or inspection fee. The flood hazard application form and the Driveway Pipe Policy state no fee; under the pipe policy the owner buys the pipe.

In the towns, Woodland charges $50 for a permit to place a mobile home. Roanoke and Wadley do not post their permit fees online; Roanoke’s zoning ordinance says only that a lapsed permit needs a new application and all fees again. Roanoke City Hall answers on 334-863-4129 and Wadley Town Hall on (256) 395-2261.

Trades, septic and utilities in Randolph County

The county issues no electrical, plumbing, mechanical or gas permits. Its memorandum points out that residential home builders must still be licensed by the Alabama Home Builders Licensure Board and follow the Alabama Residential Building Code, and it urges owners to check their contractor’s licence.

Septic tank certifications are issued by the Randolph County Health Department, 320 Main Street, Roanoke. The environmental health line is 334-863-8981.

Woodland requires every business and contractor to buy a town licence before working inside the town limits.

Rather talk it over?

Call 1-855-478-4290 →

Documents to prepare

Flood-prone site (county)

  • Application for Permit to Develop in a Special Flood Hazard Area
  • Location map of the site
  • Plans that detail the building site
  • Special flood hazard area parameters
  • Parcel number, applicant and contractor details
  • A final Elevation Certificate once construction is complete

Wadley zoning permit

  • A map or plat drawn to scale
  • Shape and dimensions of the lot
  • Size and location of existing and proposed buildings
  • Existing and intended use of each building
  • Setback and side lines of buildings on adjoining lots
  • Zoning district boundaries that apply to the lot

How to proceed in Randolph County: 5 steps

1. Decide whether a town applies

Land inside Roanoke, Wadley, Wedowee or Woodland, or in a police jurisdiction, follows that municipality’s requirements.

2. Call the County Engineer early

Ring 256-357-2311 about flood-prone land, dividing a parcel or cutting timber. The office works Monday to Thursday, 6 a.m. to 4:30 p.m.

3. Ask for a driveway pipe evaluation

Mark the location; the Highway Department sizes the pipe and checks sight distance, then you buy the pipe and tell the department when it is on site.

4. Get the septic certification

Contact the Health Department’s environmental health office on 334-863-8981.

5. Report the new structure

Tell the Revenue Commissioner’s Appraisal Office on 256-357-4343, ext. 402.

Rather not deal with the Randolph County building department?

Get a free quote →

Inspections in Randolph County

The county carries out no building inspections. For a flood hazard permit, the Engineer’s office reviews the site, records the base flood elevation and the structure’s elevation, and requires a final Elevation Certificate when construction is finished.

In Wadley, the Enforcement Officer may enter a permitted site to inspect it and must make the final inspection within 3 regular business days of being told the building is ready; a building may not be occupied until the Certificate of Occupancy is issued.

Randolph County-specific points

Driveway pipes: metal or concrete only, installed in runs of 20 to 40 feet and no longer. The policy allows no more than 2 tri-axle loads of backfill, with less than a small dump truck load of crushed stone. Where the drive ties into the pavement edge, the owner must grade the slope so water runs to the ditch, not into the road.

Wadley: repairs that do not change the character of a structure and cost no more than $1,000, painting and wallpapering are exempt from the zoning permit. Clearing trees and undergrowth from a site does not need one either.

Woodland mobile homes: Ordinance No. 2026-08-10-1 requires a home of at least 800 sq ft that is less than 5 years old when first placed, on a lot of not less than 1 acre.

Roanoke: the City adopted a new zoning ordinance, dated February 5, 2024, and posts it with its zoning map. Under it a building permit can lapse if the work is not finished within 12 months of issue, and a permit that has been expired for more than 180 days is renewed only in extenuating circumstances.

Commission meetings: second and fourth Mondays of each month at 3 p.m., in the Courthouse Annex in Wedowee.

Want this handled start to finish?

Get a free quote →

Alabama building code

From 1 January 2027, under Act 2024-443, a residential home builder must build to the applicable residential code (the Alabama Residential Building Code, or the local code where one applies) even where no building department inspects the work. Since 1 October 2024 the Alabama Home Builders Licensure Board adopts the residential code, and the Licensing Board for General Contractors the commercial energy code. Alabama’s codes and the 2027 change

Official Randolph County resources

Inspections are where schedules slip.

Get a free quote →

Randolph County building permit FAQs

Do I need a building permit in Randolph County, Alabama?

Not from the county. The Commission states that it has not adopted any building codes or permit requirements. Land inside a town, or in a flood-prone area, is different.

Is there zoning in Randolph County?

No zoning restrictions apply to unincorporated land outside municipal limits and police jurisdictions. Roanoke and Wadley have their own zoning ordinances.

Who do I call about building in a flood zone?

The County Engineer, who is the Floodplain Administrator, at 108 Woodland Ave. West in Wedowee, 256-357-2311. A Permit to Develop in a Special Flood Hazard Area is required.

Where do I get a septic permit in Randolph County?

From the Randolph County Health Department in Roanoke. Its environmental health number is 334-863-8981.

Who issues building permits in Roanoke, Alabama?

The City of Roanoke. Applications for building permits are obtained at City Hall, 809 Main Street, 334-863-4129.

Does Wadley require a permit?

Yes. Wadley’s zoning ordinance requires a Zoning Permit from the Enforcement Officer before construction, renovation or development, apart from small repairs up to $1,000, painting and wallpapering.

Simplify Randolph County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Alabama. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Randolph County sooner?

Let Alliance prepare, file, and track your Randolph County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Randolph County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.