Inside the City of Waupun, which lies in both Dodge and Fond du Lac counties, permits come from the city’s Building Inspection / Zoning office at City Hall, 201 East Main Street (920-229-6360), run under contract by Grand Valley Inspection Services. A new one- or two-family home is priced at $500 plus $0.28 per square foot, with a $1,000 minimum, for the building, plumbing, electrical and HVAC permits together, and the city adds a $45 administrative fee to every building permit.
What requires a building permit in Waupun?
Waupun answers the question through its fee schedule and its building inspector FAQ: every item priced there needs a permit, and the FAQ adds the common small jobs that owners ask about. The property owner is responsible for getting the permit.
Building permit
- New homes, additions, remodels, garages and accessory buildings
- Re-roofing a house, garage or business; re-siding or replacing windows on a house
- Decks, permanent swimming pools and prefabricated sheds
- Fences, once any one section is longer than 20 feet
- Signs and chicken coops with runs
- Electrical services, laterals, furnace or air conditioner replacement and plumbing remodels
- Demolition and moving buildings, and agricultural buildings
Zoning review as well
- New homes, additions and garages (a zoning fee is part of the permit)
- Pools, fences, signs, decks and sheds
- Commercial, industrial and multi-family work, which also needs Plan Commission site plan approval
- Home occupations, licensed every year by the zoning administrator
Building on, altering, regrading or filling land should be checked with the building department first, because a permit may be needed even where no structure is involved. Starting construction without a permit doubles the fee.
What Waupun decides and what the state holds
Waupun is a DSPS-delegated municipality for the Uniform Dwelling Code, so new one- and two-family homes are permitted and inspected by the city’s contracted inspector. The city writes its own zoning code (Chapter 16, with the sign code in Section 16.11), fence rules, fees and stormwater rules. Commercial buildings over 50,000 cubic feet need DSPS plan approval, and the state dwelling and commercial codes set the construction standards.
Waupun building department: who handles permitting
Waupun contracts out its building inspection. The city’s page names Grand Valley Inspection Services as the firm that provides its building and zoning inspector, and the same office answers setback, address and zoning questions. DSPS’s delegated-agent list, current as of September 24, 2026, shows the City of Waupun as delegated for the Uniform Dwelling Code across both counties, with the City Clerk as its municipal contact.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Building Inspection / Zoning | City Hall, 201 East Main Street, Waupun, WI 53963; 920-229-6360; inspector@cityofwaupunwi.gov |
| Office hours | Monday and Wednesday, 10 a.m. to 12:30 p.m.; other times by appointment |
| City Clerk (licenses, records) | 920-324-7915; City Hall open weekdays 7:30 a.m. to 4:30 p.m. for records |
| Public Works (erosion control, stormwater) | 920-324-7918 |
| Population (2025 estimate) | 11,150: 7,593 in Dodge County and 3,557 in Fond du Lac County |
The Town of Waupun in Fond du Lac County is a different government with its own DSPS delegation, and neither county issues building permits inside the city; certified survey maps for city lots are recorded at the Dodge or Fond du Lac County Register of Deeds, depending on the side of the line.
Waupun permit types
The city’s Licenses & Permits page links the building, HVAC, electrical, plumbing, fire protection and street opening/right-of-way applications to its iWorQ online portal, and the Building Permits page still posts the paper Wisconsin Uniform Building Permit Application, which covers construction, HVAC, electrical, plumbing and erosion control on one form.
Residential permits
- New one- and two-family homes. Two sets of building plans, two plats of survey or plot plans showing elevations and distances to the lot lines, two copies of the heat-loss calculations and two copies of the erosion control plan (which can be drawn on the survey).
- Additions, remodels, accessory buildings, fences and pools. One set of plans, one plot plan showing existing buildings, the new work, setbacks and erosion control, and the completed application.
- Bonds. A new home carries a $1,000 bond, as does an addition over 500 square feet, refunded after occupancy if every inspection was called, the occupancy permit was issued before move-in and all orders were corrected on time; re-inspection charges come out of it.
- Early start. Footings and foundations only, for $100 or $0.03 per square foot, whichever is more.
Building or remodeling a home here? Alliance handles residential permit filing, so the crew isn't waiting on the counter.
Commercial permits
Multi-family, assisted living, nursing home, commercial and industrial projects need Plan Commission site plan approval, state-approved building plans with a description of the building, two copies of the property survey showing every building to scale with erosion control marked on one, and the application. The fee schedule says plans for buildings under 50,000 cubic feet are reviewed at DSPS fee rates, while plan approval over 50,000 cubic feet must come from DSPS.
For tenant improvements and new commercial builds, Alliance handles commercial permit expediting through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Site plan review. Required on commercial, industrial and multi-family parcels for new buildings, additions, parking lot changes and changes of land use; $100 department review plus any consultant or engineering cost.
- Plan Commission. Zoning changes, conditional uses, site plans and certified survey maps go to the Plan Commission, which meets the third Wednesday of the month at 4:45 p.m.; file forms and fees 3 weeks ahead.
- Zoning Board of Appeals. Variances and interpretations are heard the first Monday of the month at 4:30 p.m., with applications due 3 weeks before.
- Erosion control and stormwater. Public Works permits and inspects construction site erosion control and post-construction stormwater practices and posts a stormwater permit application and maintenance agreement.
- Street openings. Work in a street or sidewalk needs an excavation permit ($50 application, $10,000 bond).
Waupun permit costs and fees
The building fee schedule posted by the inspection office is dated effective July 30, 2019, and the city adds a $45 administrative fee to every building permit. The minimum fee is $50, plan review is included for homes, additions and garages, and fees double when work starts without a permit.
| Item | Fee |
|---|---|
| New one- or two-family home (building, plumbing, electric and HVAC) | $500 base plus $0.28 per sq ft, minimum $1,000 |
| New home extras: UDC seal / erosion control / occupancy / zoning | $40 / $50 / $50 / $100 |
| Residential addition: building | $0.16 per sq ft, minimum $300 |
| Addition or garage trades: plumbing, electric, HVAC | $0.04 per sq ft each, minimum $80 |
| Garage or accessory building (new or addition) | $0.14 per sq ft, minimum $100 |
| Residential remodels | $6 per $1,000 of construction cost |
| Electrical service / laterals / furnace or AC replacement | $80 / $60 / $50 |
| Plumbing remodel | $50 or $8 per fixture |
| Decks | $100 to $150 (2 or 3 inspections at $50) |
| Pools, sheds, fences, chicken coops | $50 each, plus $50 zoning review where listed |
| Signs | $50 plus $0.50 per sq ft of each face |
| Commercial and multi-family: building | $100 plus $0.20 per sq ft, minimum $500 |
| Commercial trades | Plumbing, electric, HVAC $60 plus $0.06 per sq ft (minimum $80), or $8 per plumbing fixture / $1.25 per electrical opening if greater; sprinklers $60 plus $0.04 per sq ft or $1 per head |
| Commercial bond / occupancy / plan review / zoning | $1,500 under 10,000 sq ft or $3,000 over / $100 / $100 or $200 / $200 |
| Demolition: dwelling / accessory / commercial | $100 / $50 / $300 |
| Administrative fee on every building permit | $45 |
Rather talk it over?
Call 1-855-478-4290 →Worked example from the schedule: a new 2,000-square-foot house is $500 + 2,000 × $0.28 = $1,060, which is above the $1,000 minimum. Adding the $45 administrative fee, the $40 UDC seal and the $50 erosion control, $50 occupancy and $100 zoning charges listed for new homes gives $1,345, plus a $1,000 bond that comes back after occupancy. A $12,000 re-roof is $72 (12 × $6) plus $45, or $117.
Zoning and land division fees come from the city’s annual fee schedule, revised January 1, 2026: conditional use $150, variance $150, zoning code amendment $150, certified survey map $100 plus $15 per lot, preliminary plat $250 plus $15 per lot and final plat $150 plus $5 per lot.
Trade permits and who may pull them
For a new home the plumbing, electrical and HVAC permits are included in the single new-dwelling fee; for additions, garages and commercial work each trade is priced separately. The application lists the dwelling contractor, the Dwelling Contractor Qualifier and the HVAC, electrical and plumbing contractors with their license or certification numbers.
- Electrical. An owner may do electrical work on renovations and additions to a home they own and live in, but not on a new house; new homes and commercial work need a state-licensed electrician.
- Plumbing. The same owner-occupant rule applies to interior plumbing for renovations and additions. Exterior plumbing must be done by a licensed master plumber, master plumber-restricted or utility contractor, and new homes and commercial buildings need a licensed master plumber.
- HVAC. Furnace or air conditioner replacement is a $50 permit; new commercial HVAC is $60 plus $0.06 per square foot.
- Fire protection. Sprinkler permits are $60 plus $0.04 per square foot or $1 per head, whichever is more, and are filed in the city’s online portal.
- Contractor-built homes. The state Dwelling Contractor certification and Qualifier go on the permit; an owner-occupant building their own home is exempt.
Rather not deal with the building department?
Get a free quote →How to apply for a Waupun building permit
Setbacks depend on the zoning district; ask the building inspector’s office, and go to the Plan Commission or Zoning Board of Appeals first if the project needs a conditional use, site plan or variance.
Two sets of plans, surveys, heat-loss sheets and erosion control plans for a new home; one set and a plot plan for smaller work.
Use the iWorQ portal linked from the Licenses & Permits page, or the paper Wisconsin Uniform Building Permit Application.
Add the $45 administrative fee and, for a new home or large addition, the escrow bond.
Notify the building department for every required inspection so the bond can be returned.
Move in only after the occupancy permit is issued.
Review, corrections and what causes delay
The inspector is in the office only on Monday and Wednesday mornings, so call or email ahead to book a meeting at another time. Commercial files cannot be permitted until the Plan Commission has approved the site plan and the state has approved the building plans. A permit lasts one year, or two years for one- and two-family housing, so plan the work to finish inside that window.
Inspections and occupancy in Waupun
The building department must be notified for all required inspections; missed inspections, an occupancy without a permit or uncorrected orders forfeit the escrow bond, and re-inspections needed because work was not ready are deducted from it. Inspections are arranged with the inspector at 920-229-6360 or inspector@cityofwaupunwi.gov.
A new home or addition needs an occupancy permit ($50; $100 for commercial buildings) before anyone moves in, and an addition is inspected at footing, foundation, floor, framing, insulation and final stages, which the fee table lists for the building portion. Decks take two or three inspections, and the fence FAQ reminds owners to call Digger’s Hotline (811) before setting posts.
Wisconsin building code in Waupun
Waupun enforces the state dwelling and commercial codes through its contracted inspector and adds its zoning, sign, fence and stormwater rules. FEMA’s Community Status Book lists Waupun (community 550108) as participating in the National Flood Insurance Program, with flood maps effective May 19, 2014 and a Community Rating System class 8 that gives policyholders a 10% discount. Flood maps, elevation certificates for work in a special flood hazard area and the floodplain ordinance are available from the building inspection department and at the Waupun Public Library.
Want this handled start to finish?
Get a free quote →Wisconsin's Uniform Dwelling Code covers one- and two-family homes. Its Commercial Building Code covers public buildings, workplaces and buildings of three or more units. Local ordinances must conform to both. Wisconsin rules
Waupun permit search and official resources
Permit and inspection records are public records held by the city. Ask the City Clerk’s office by phone, by mail or through the city’s online records request form; copies are $0.25 a page, charges over $5 are paid in advance, and search time is billed only when it exceeds $50.
- Building Inspection / Zoning
- Building permits: what to submit
- Building permit fee schedule, effective July 30, 2019
- Wisconsin Uniform Building Permit Application
- Licenses and permits, with online permit applications
- Building inspector and zoning FAQs
- City annual fee schedule, revised January 1, 2026
- Site plan approval process
- Plan Commission
- Zoning Board of Appeals
- Stormwater management
- Stormwater permit forms
- Floodplain hazard information
- Open records requests
- DSPS Uniform Dwelling Code delegated agents
- FEMA Community Status Book, Wisconsin
Inspections are where schedules slip.
Get a free quote →Waupun building permit FAQs
Who do I call about a building permit in Waupun?
The city’s contracted building and zoning inspector at 920-229-6360, in the office Monday and Wednesday from 10 a.m. to 12:30 p.m.
Do I need a permit to re-roof or replace windows?
Yes. Re-roofing, re-siding and window replacement each cost $6 per $1,000 of construction cost, with a $50 minimum, plus the $45 administrative fee.
Do I need a permit for a fence?
Yes, once any one section is longer than 20 feet; the fee is $100 ($50 building, $50 zoning) plus $45. Side and rear fences may be 6 feet and front-yard fences 4 feet and 90% see-through.
Can I do my own electrical or plumbing work?
For renovations and additions to a home you own and live in, yes; not on a new house, and exterior plumbing needs a licensed plumber or utility contractor.
How much is a permit for a new house?
$500 plus $0.28 per square foot (minimum $1,000) for all four trades, plus $45 and the listed seal, erosion, occupancy and zoning fees and a $1,000 refundable bond.
How long is a permit good for?
One year from issue, or two years for one- and two-family housing.
Does Dodge or Fond du Lac County issue permits in the city?
No. The City of Waupun issues building and zoning permits throughout the city on both sides of the county line.
Simplify Waupun permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Wisconsin. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Waupun sooner?
Let Alliance prepare, file, and track your Waupun permits while your crew stays on the job.
More Wisconsin permitting guides
Dodge County
Read guide →Beaver Dam
Read guide →Fond du Lac County
Read guide →Wauwatosa Building Permit Guide
Read guide →West Allis Building Permit Guide
Read guide →West Bend Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Waupun permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.