Inside the City of Superior, permits are issued by the Building Inspection Division of the Public Works Department, Suite 230, 1316 North 14th Street (715-395-7288), led by Chief Building Inspector Patrick Rohde. Applications, payments and inspection requests run through the city’s Self Service Portal, every contractor must be registered with the city, and a complete file is reviewed within 10 business days. A new one- or two-family home is one combination permit: $1,000 plus $0.50 per square foot of finished area and $0.25 per square foot of unfinished space.
What requires a building permit in Superior?
The Building Inspection Division lists the work that needs a permit in its FAQ and on its permit pages. The list is broad: if it is built, moved, demolished, re-roofed or wired, plan on a permit.
Permit required
- New houses and other buildings, including sheds
- Improvements and alterations to a home or business
- Moving or demolishing a building
- Roofing or re-roofing, siding, and window and door replacement
- Electrical, plumbing and heating installations or changes
- Wood stoves and fireplaces, gas inserts included
- All accessory buildings and residential fences, decks and pergolas
- Any excavation, work in the right of way or other land-disturbing activity
- Signs
Listed as exempt
- Plastic or composite sheds under 40 square feet, by the adopted fee schedule
- The accessory structure page lists sheds of 64 square feet or more as needing permits, so ask about anything between 40 and 64 square feet before building
A deck that carries a roof is treated as a porch and permitted as an addition, and a detached garage must meet the general construction standards of the Uniform Dwelling Code under Superior Code Section 34-132. Work done before the permit is issued and posted is work without a permit, which can raise the fee and bring a citation under Sections 34-13, 34-83 and 34-88.
What Superior decides and what the state holds
The city adopts the state commercial building code, Uniform Dwelling Code, plumbing code and electrical code and enforces them itself under its DSPS delegation. It adds what the state leaves to cities: contractor registration, its own fee schedule, zoning (Chapter 122), stormwater and land-disturbance permits under its storm sewer permit, and the Special Area Management Plan for wetlands.
Superior building department: who handles permitting
The Building Inspection Division reviews plans, issues permits and inspects residential construction, HVAC, electrical and plumbing, and it runs code compliance. DSPS’s delegated-agent list, current as of September 24, 2026, shows the City of Superior as delegated for the Uniform Dwelling Code. Commercial electrical permits and inspections are handled by REM Inspections under contract with the city, and larger commercial plan reviews can go to Redline Plan Review.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Building Inspection Division | Public Works, 1316 North 14th Street, Suite 230, Superior, WI 54880; 715-395-7288 (the division contact block also lists 715-395-7289); fax 715-395-7346; TTY 715-395-7521; BuildingSafety@superiorwi.gov |
| Hours | Monday to Friday, 8 a.m. to 4:30 p.m.; inspectors usually in the office 8 to 8:30 a.m. and 4 to 4:30 p.m. |
| Chief Building Inspector | Patrick Rohde |
| Planning Department (zoning, rezoning, special use) | 1316 North 14th Street; 715-395-7335; planning@superiorwi.gov |
| Commercial electrical | REM Inspections (electric@reminspecting.com), under city contract |
The Town of Superior and the Village of Superior are separate municipalities with their own DSPS delegations; they do not file through the city.
Superior permit types
Every application is filed in the Self Service Portal, which also handles invoices and inspection requests. Plans must be submitted digitally as well as on paper, by upload, on a CD or by email to BuildingSafety@superiorwi.gov. The city’s permit types are building, electrical, mechanical, plumbing, land disturbing and right-of-way, stormwater management, razing and sign permits.
Residential permits
- New homes. One combination permit covers building, electrical, mechanical, plumbing with laterals, excavation, driveway access, grading and erosion control, post-construction stormwater, zoning and SAMP sign-off, the state seal and plan review. Before applying, complete the makeup and combustion air, erosion control, energy compliance, wall bracing and water calculation worksheets and the memorandum of understanding posted with the new-construction checklist.
- Additions. A combination permit at $300 plus $0.50 per square foot.
- Alterations. A building permit, with separate HVAC, plumbing or electrical permits and their own plans when those systems change.
- Accessory structures. Decks, detached garages, larger sheds, pergolas and fences each have a checklist and worksheets; a site plan is required for zoning.
- Roofing, siding, windows, modular and manufactured homes, razing. Each has its own portal application.
Who may apply matters. Owner-occupants, owners who intend to occupy, and city-registered contractors may apply for general building permits on houses and duplexes; only owner-occupants and registered contractors may apply for the other residential permit types, and gas piping and electrical service equipment must be installed by a city-registered contractor of that trade.
Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
Since the city’s August 12, 2026 notice, the division reviews structural and HVAC plans for new buildings and alterations under 50,000 cubic feet and small additions (up to 2,500 square feet, one floor, an 18-foot roof span and 12-foot walls), plus most commercial plumbing plans, including systems of 16 or more fixtures in public buildings. Larger buildings and all fire suppression and alarm plans go to Redline Plan Review, electrical plans to REM Inspecting, and an applicant may choose DSPS for any review; petitions for variance still go to DSPS. Every commercial project, whoever reviews it, gets its permit from the city.
Not sure this scope needs a permit?
Get a free quote →For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning and Planning. Rezonings, special use permits, buffer appeals, certified survey maps, street vacations and variances go through the Planning Department to the Plan Commission or Zoning Board of Appeals; staff also review site plans. The zoning ordinance, last updated in 2002, is being rewritten to match Comprehensive Plan 2040.
- Wetlands. Wetlands are widespread in Superior. Eligible degraded wetlands can be filled under the city’s SAMP II general permits, administered by the Building Inspection Division with final approval from the U.S. Army Corps of Engineers and the Wisconsin DNR; only 140 of the 1,097.5 eligible acres may be permitted over the program’s ten-year life.
- Land disturbance and stormwater. A permit is needed before any grading, excavation, filling, trenching, driveway or new hard surface; a stormwater management permit is needed when a project disturbs an acre or more or adds 20,000 square feet of impervious surface.
Superior permit costs and fees
Fees come from the city’s posted Building Inspection Fee Schedule, headed “Adopted”; the city posts it as its 2025 updated schedule, and no adoption date is printed on it. The portal issues an invoice once the application is approved, and the permit issues after payment.
| Item | Fee |
|---|---|
| New one- or two-family home (combination permit) | $1,000 plus $0.50 per sq ft finished and $0.25 per sq ft unfinished |
| Addition (combination permit) | $300 plus $0.50 per sq ft |
| Early footing and foundation approval | $2,000 |
| Roof, siding, or windows and doors (same openings) | $30 each; any two or more $50 |
| Structural alterations | $100 plus $10 per $1,000 of value |
| Accessory structures (garages, decks, porches, sheds, pergolas) | $0.25 per sq ft of footprint, minimum $30 |
| Fence / moving a building | $30 / $100 |
| Residential plumbing, HVAC or electrical item | $60 (electrical circuits $60 to $150) |
| Package permits: water heater, furnace, boiler, fireplace | $75 |
| Kitchen or bathroom remodel, basement waterproofing, mobile home | $180 (three inspection trips) |
| Driveway access / excavation / razing | $65 / $40 / $40 |
| Erosion control and grading; post-construction stormwater | $100 each up to one acre, plus $50 per extra half acre |
| Commercial new construction, total for all trades | Group 1 multi-family $0.70, Group 2 $1.00, Group 3 $0.40 per sq ft |
| Commercial alterations | $60 per trade plus $10 per $1,000 of value |
| Signs / appeals filing fee | $0.25 per sq ft, minimum $25 / $100 |
| Re-inspection; trips beyond eight on a new home | $60 each |
| No permit: first offense / second within 12 months | Double / triple fees |
Rather talk it over?
Call 1-855-478-4290 →Worked example from the schedule: a house with 1,600 square feet of finished living space and 1,100 square feet of garage and unfinished basement is $1,000 + (1,600 × $0.50) + (1,100 × $0.25) = $1,000 + $800 + $275 = $2,075, and that one permit already includes the trades, driveway access, erosion control and state seal. Starting a new house or addition early doubles the fee; the schedule counts from permit issuance, or from ten business days after the application if no review action has been taken, whichever comes first.
Commercial shells and interior build-outs are charged at 50% of their group’s rate. Industrial plants that need quarterly electrical inspections outside new construction are billed $100 an hour instead of permit fees.
Trade permits and who may pull them
All building, electrical, HVAC and plumbing contractors and subcontractors must be registered with the city through the Self Service Portal before working in Superior, and the city accepts bonds written by the bonding companies themselves.
- Residential electrical. Permitted and inspected by the Building Inspection Division; service equipment must be installed by a city-registered electrical contractor.
- Commercial electrical. REM Inspections handles commercial electrical plan review, permit applications and inspections under city contract; the contractor must still be registered with the city.
- Plumbing. The division permits and inspects residential and commercial plumbing; lateral repairs and interior gas, water and sewer piping are $60 items.
- HVAC and gas. Each heating unit, duct system, air exchanger, fireplace or heat pump is a $60 item; gas piping work requires a registered contractor of that trade.
- Owners. An owner-occupant may apply for residential permits, but a new house built by a contractor also needs the state Dwelling Contractor and Qualifier credentials on file.
Rather not deal with the building department?
Get a free quote →How to apply for a Superior building permit
Contractors register with the city; owners confirm they qualify as owner-occupants for the permit type.
Ask Planning about the district and setbacks, and check the Douglas County GIS map and SAMP wetland mapping for the lot.
Use the checklist for your project type; new homes need the combustion air, erosion control, energy, bracing and water worksheets.
Upload the application and digital plans and supply paper plans as well.
The division invoices after approval; keep the payment confirmation email.
Display the permit so it can be seen from the street, then call for inspections.
Review, corrections and what causes delay
An incomplete application is placed on hold, and one left on hold for more than a month may be voided. Complete files are reviewed within 10 business days; the FAQ gives 3 to 5 working days for signs and minor projects and 5 to 7 for single-family homes, and a review may pull in Planning, Engineering, Fire or the county health department. Residential permits generally last six months, new homes and commercial new construction two years, and other commercial permits one year.
Inspections in Superior
The permit holder must call for inspections at 715-395-7288 rather than contacting an inspector directly; the inspections page asks for two business days’ notice, while the FAQ says 24 hours, and voicemail takes requests after hours. Commercial electrical inspections are booked through REM Inspecting. The rule of thumb is that each phase is inspected before the next one covers it.
The FAQ describes a typical sequence for new construction: footing and foundation with setbacks before concrete is poured, underground plumbing under test, floor joists and insulation, framing, exterior lath before a stucco scratch coat, drywall before taping, and a final, with electrical, plumbing and mechanical inspections at each rough stage. The new-home combination fee includes eight inspection trips; each extra trip, and each re-inspection, is $60.
Wisconsin building code in Superior
Superior adopts the state commercial code (SPS 361 to 366), the Uniform Dwelling Code (SPS 320 to 325), the plumbing code (SPS 381 to 385) and the electrical code (SPS 316) and enforces them through its own inspectors and its commercial contractors. FEMA’s Community Status Book lists Superior (community 550116) as participating in the National Flood Insurance Program, and new flood maps take effect on December 10, 2026; check a lot near Lake Superior, the bay or the rivers against the new maps before designing.
Wisconsin's Uniform Dwelling Code covers one- and two-family homes. Its Commercial Building Code covers public buildings, workplaces and buildings of three or more units. Local ordinances must conform to both. Wisconsin rules
Want this handled start to finish?
Get a free quote →Superior permit search and official resources
The Self Service Portal’s search shows permits, inspections and code compliance cases for any city address from June 2021 onward. For older permits or a fuller property file, submit a public records request through the city’s Just FOIA portal.
- Building Inspection Division
- Self Service Portal (applications, payments, inspections, record search)
- Required building permits
- Building inspection fee schedule (adopted)
- Permitting process overview
- Residential permits
- Residential new construction checklists
- Residential accessory structures
- Commercial permits
- Commercial plan review update, August 2026
- Commercial electrical (REM Inspections)
- Contractor registration
- Inspection scheduling
- Building inspection FAQs
- Codes adopted by the city
- Permit and inspection records
- Public records requests (Just FOIA)
- Planning Department applications
- Zoning code update
- Special Area Management Plan (wetlands)
- Stormwater and land-disturbance permits
- DSPS Uniform Dwelling Code delegated agents
- FEMA Community Status Book, Wisconsin
Inspections are where schedules slip.
Get a free quote →Superior building permit FAQs
How much does a permit for a new house cost in Superior?
$1,000 plus $0.50 per square foot of finished area and $0.25 per square foot of unfinished area, covering all trades and the state seal; 1,600 finished and 1,100 unfinished square feet comes to $2,075.
Do I need a permit to re-roof?
Yes. A roof permit is $30, or $50 when combined with siding or window work.
Do contractors have to register with the city?
Yes. Building, electrical, HVAC and plumbing contractors and subcontractors all register through the portal.
How long does review take?
Up to 10 business days once the application is complete.
Who handles commercial electrical permits?
REM Inspections, under contract with the city; residential electrical stays with the Building Inspection Division.
Do I need a permit for a fence or shed?
Yes for residential fences ($30) and sheds, except plastic or composite sheds under 40 square feet.
Is the Village or Town of Superior covered by the city?
No. Both are separate municipalities with their own DSPS-delegated building programs.
Are new flood maps coming?
Yes. FEMA’s new maps for Superior take effect on December 10, 2026.
Simplify Superior permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Wisconsin. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Superior sooner?
Let Alliance prepare, file, and track your Superior permits while your crew stays on the job.
More Wisconsin permitting guides
Douglas County
Read guide →Bayfield County
Read guide →Washburn County
Read guide →Taylor County Building Permit Guide
Read guide →Trempealeau County Building Permit Guide
Read guide →Vernon County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Superior permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.