Marquette County issues building permits as well as zoning permits. The Planning and Zoning Department at 77 West Park Street, Room 104, Montello (608-297-3036), led by Zoning Administrator Jean Potter, runs zoning, shoreland, floodplain and septic permitting, and the county’s Building and Mechanical Code is enforced by its contracted inspector, General Engineering Company, in every municipality except the Town of Springfield, the Villages of Endeavor, Neshkoro and Oxford and the City of Montello. A new house pays $0.33 per square foot (minimum $847) under the UDC fee schedule in force from July 1, 2025 to December 31, 2026, plus a $175 county zoning permit.
What requires a permit in Marquette County?
The county’s rule of thumb is that a new home, a deck or patio, or an addition always needs both a building permit and a zoning permit, while most accessory buildings in the zoned towns need only the zoning permit. Which ordinances apply depends on the town and on how close the land is to water.
County zoning and land use
- A zoning permit for any structure of 100 square feet or more, including pre-built sheds and shipping containers used as storage, in the 12 county-zoned towns
- Shoreland zoning throughout the county within 1,000 feet of a navigable lake or 300 feet of a navigable stream, including in Shields and Springfield
- Floodplain rules in all areas on FEMA flood maps
- A sanitary permit to install, repair, alter or reconnect any septic system where there is no municipal sewer, issued before the zoning permit
- Conditional uses, campgrounds, year-round camping, wireless towers and tourist rooming house licenses
County building code
- New one- and two-family homes and manufactured homes
- Additions, remodels and alterations of $5,000 or more, and decks
- Residential electrical work, including service upgrades and temporary service
- Residential plumbing and HVAC, solar PV and fire sprinkler or alarm systems
- Camping units, and commercial electrical work
Zoned towns also limit a house to at least 400 square feet of year-round living area and 20 feet wide, allow one dwelling per parcel, and let campers stay on a parcel seasonally only if they are removed from December 1 to April 15. Some towns require additional local permits of their own.
What the county decides and what the state holds
The county writes its zoning administration and comprehensive zoning chapters (61 and 62), shoreland and floodplain protection (63 and 64), subdivision (69), the Building and Mechanical Code (71), the private sewage chapter (74) and a fee chapter (99). Its building code applies the state’s Uniform Dwelling Code; new-home energy compliance is shown with a 2009 IECC ResCheck and a heat loss calculation. Commercial buildings follow the state Commercial Building Code, and plans that need state approval must be approved before the permit application.
Marquette County building department: who handles permitting
The DSPS list of UDC delegated agents (current as of September 24, 2026) shows Marquette County itself as a delegated agent, with General Engineering as its inspection agency, and twelve municipalities marked “See County of Marquette”. General Engineering’s inspector keeps office hours in the Courthouse on Monday, Wednesday and Friday from 8 to 9 a.m.
Short on time to read all of this?
Get a free quote →| Place | UDC permits and inspections |
|---|---|
| Towns of Buffalo (1,446), Packwaukee (1,497), Montello (1,174), Douglas (824), Harris (769), Mecan (769), Westfield (806), Neshkoro (566), Newton (546), Moundville (545) and Crystal Lake (469); Village of Westfield (1,317) | Marquette County (General Engineering) |
| Towns of Oxford (960) and Shields (588) | The county says its building code applies; the DSPS list gives each town its own row, without a county reference, and the Town of Oxford’s own page says the town contracts with General Engineering for building permits, so ask the town clerk |
| Town of Springfield (832) | Own delegation; General Engineering named on the DSPS list |
| City of Montello (1,447) | The city’s own delegation |
| Villages of Oxford (536), Endeavor (426) and Neshkoro (410) | Their own delegations |
| Office | Contact |
|---|---|
| Planning and Zoning Department | 77 West Park Street, Room 104, Montello, WI 53949; 608-297-3036; permits@marquettecountywi.gov |
| Zoning Administrator | Jean Potter |
| Building inspection (contract) | General Engineering Company, 916 Silver Lake Drive, Portage; inspection line (608) 745-4070; Courthouse hours Mon, Wed, Fri 8–9 a.m. |
| County Highway Department (driveways on county roads) | PO Box 398, Montello, WI 53949 |
Marquette County permit types
Zoning applications (zoning permit, conditional use, campground, annual camping, wireless tower and rural address) are on the county’s forms page, each with an online payment option, or can be filled in at the zoning office. Building permits can be applied for online through General Engineering Company’s website or on paper.
Residential permits
New homes use the state UDC application; everything else (decks, additions, electrical services, remodels and alterations) uses the county’s General Building Permit Application. Each needs the owner’s details, every contractor with license numbers and expiry dates, and the signed cautionary statement. A new home or addition also needs an erosion control plan showing the tracking pad, energy code information, two sets of plans (one if filed as a PDF) with rooms labeled and window and door sizes, a wall cross section and brace wall worksheets where they apply. A deck permit needs footing size, post spacing, beam and joist sizes and spans, and the deck’s height above grade.
Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Not sure this scope needs a permit?
Get a free quote →Commercial permits
The General Building Permit Application also covers new commercial buildings and commercial additions or alterations, with electrical, plumbing, HVAC, construction and erosion control boxes. It asks whether a State of Wisconsin plan approval is needed, and the approved plans must be filed with the application. A commercial zoning permit is $150, and commercial electrical work is priced at $0.09 per square foot with a $220 minimum.
For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Sanitary permit first. Where a septic system is needed, the sanitary permit must be issued before the zoning permit.
- Zoning permit. The county checks the use and the setbacks: 63 feet from a town road, 75 from a county road and 110 from a state road (to the centerline), 75 feet from the high-water mark and from wetlands, and district side yards from 10 to 50 feet.
- Board of Adjustment. Variances, special exceptions and appeals ($300 each) are heard on the last Thursday of the month at 1:00 p.m.; applications received by month’s end are heard the next month, and a lone application can wait one more month. Tell your town board about the request.
- Rezoning or land division. Rezonings are $300; certified survey maps are $25 plus $10 a lot.
- Driveways. A county highway driveway permit is $100; a state highway needs a WisDOT connection permit.
Marquette County permit costs and fees
The Planning and Zoning Department publishes three schedules: 2026 zoning fees and 2026 sanitary fees (both dated July 1, 2025) and UDC building fees in force from July 1, 2025 to December 31, 2026.
| Work | Fee |
|---|---|
| New 1–2 family home (garage, decks and basement included; mechanicals included) | $0.33 per sq ft, $847 minimum |
| Plan review, new home / occupancy certificate | $94 per unit / $94 per unit |
| Erosion control, new home / addition | $165 / $110 |
| State seal | $40 |
| Early start (footings and foundation) | $275 |
| Manufactured or HUD home | $424 plus $0.33 per sq ft of basement, attached garage and decks |
| Additions / remodels and alterations of $5,000 or more | $0.33 per sq ft, $220 / $165 minimum, plus mechanicals; $55 plan review |
| Decks | $0.66 per sq ft, $193 minimum |
| Residential electrical (incl. service upgrade) | $171 |
| Residential plumbing / HVAC, with inspection | $116 each ($55 if no inspection is needed) |
| Residential solar PV | $374 up to 15 kW, plus $16.50 per kW above |
| Fire sprinkler or alarm systems | $0.04 per sq ft, $275 minimum |
| Camping unit | $303 plus $30 state insignia |
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee |
|---|---|
| Zoning permit: new single-family / addition / accessory / commercial | $175 / $100 / $75 / $150 |
| Shoreland administrative review permit | $100 |
| Rezoning; variance, appeal or special exception | $300 each |
| Rural address sign | $75 |
| Sanitary permit: conventional / mound, at-grade or in-ground pressurized / holding tank | $375 / $475 / $450 |
| Septic plan review: conventional / mound or at-grade | $125 / $250 |
| Replacement treatment tank only / privy / reconnection | $300 / $200 / $200 |
| Sanitary permit transfer or second-year renewal | $100 |
Worked example from the schedules: a new house with 3,000 square feet including its garage, deck and basement pays 3,000 × $0.33 = $990 for the building permit, plus $94 plan review, $165 erosion control, $94 occupancy and the $40 state seal ($1,383), and a $175 county zoning permit in a county-zoned town. On a conventional septic system add $375 for the sanitary permit and $125 for plan review; recording a holding tank or aerobic system agreement costs another $30 at the Register of Deeds.
Trade permits and who may pull them
In the municipalities under the county code, electrical, plumbing and HVAC permits are issued with the building permit by the county’s contracted inspector. On a new home the mechanicals are included in the $0.33 square-foot fee; on additions, remodels and other work each trade is added at its own fee. The General Building Permit Application asks for the construction contractor, the Dwelling Contractor Qualifier (an owner, officer or employee of the Dwelling Contractor), the HVAC contractor, the electrical contractor and master electrician, and the plumbing contractor.
Rather not deal with the Marquette County building department?
Get a free quote →- Credentials: Wisconsin issues the Dwelling Contractor certification and Qualifier for one- and two-family work (owner-occupants are exempt), licenses electricians and plumbers through DSPS, and registers HVAC businesses.
- Septic systems: all work must be done by a licensed plumber, soil tests for the design by a state-certified soil tester, and the owner signs a maintenance agreement for the new system. The county posts lists of plumbers, soil testers and pumpers.
- Commercial electrical: $0.09 per square foot (minimum $220), with separate fees by system rating that start at $495 for systems up to 25 kW.
How to apply for permits in Marquette County
Call 608-297-3036 or use the county GIS map to confirm the zoning district, whether the town is county-zoned and whether shoreland or floodplain rules apply.
Hire a certified soil tester and licensed plumber and obtain the sanitary permit, which comes before the zoning permit.
File the zoning permit application, in person in Montello or with online payment.
Use General Engineering’s online application or the paper forms, with plans, erosion control and energy documents.
From the County Highway Department for a county road, the town for a town road, or WisDOT for a state highway.
Call General Engineering at (608) 745-4070.
Review, corrections and what causes delay
The order matters: no zoning permit is issued until the sanitary permit is, and the building permit follows the zoning permit, so start with the septic design. Variances and special exceptions wait for the monthly Board of Adjustment hearing after published notice, and a hearing with only one application can be pushed back a month. A new-home file is complete only with the cautionary statement, erosion control plan, ResCheck and heat loss calculation, and both sets of plans.
Inspections in Marquette County
General Engineering Company inspects work under county building permits; call its office at (608) 745-4070 to schedule, or speak with the inspector during the Courthouse hours on Monday, Wednesday and Friday mornings. A new home receives an occupancy certificate ($94 per unit) after the final inspection. Septic installations are inspected under the county sanitary permit, and the county posts the form inspectors use to report on existing systems.
Zoning compliance is checked by the zoning office against the permit and the setbacks; the county asks owners to contact it before any construction or land use project so that every needed permit is identified first.
Wisconsin building code in Marquette County
Marquette County enforces the state Uniform Dwelling Code through its own delegation and Chapter 71, with General Engineering Company as its inspection agency. FEMA’s Community Status Book lists Marquette County (community 550601) as participating in the National Flood Insurance Program, with a current flood map dated December 18, 2012, and the county floodplain ordinance applies wherever those maps show flood hazard areas.
Want this handled start to finish?
Get a free quote →Wisconsin's Uniform Dwelling Code covers one- and two-family homes. Its Commercial Building Code covers public buildings, workplaces and buildings of three or more units. Local ordinances must conform to both. Wisconsin rules
Marquette County permit search and official resources
Zoning districts and parcel information are on the county’s Land Information GIS map. For copies of past zoning, sanitary or building permits on a parcel, contact the Planning and Zoning office at 608-297-3036 or permits@marquettecountywi.gov; building permits in Montello, Endeavor, Neshkoro, the Village of Oxford and Springfield are issued by those municipalities.
- Planning and Zoning Department
- Building requirements, setbacks and jurisdiction
- Residential dwelling permitting (General Engineering)
- Zoning permit applications and forms
- General building permit application
- UDC fee schedule (7/2025–12/2026)
- 2026 zoning fee schedule
- 2026 sanitary fee schedule
- Sanitation and septic systems
- Zoning and land use ordinances
- Chapter 63 Shoreland Protection
- Variances and special exceptions
- Planning and zoning FAQ
- Highway Department permits and fees
- DSPS UDC delegated agents list
- WisDOT state highway connection permits
- FEMA Community Status Book, Wisconsin
Inspections are where schedules slip.
Get a free quote →Marquette County permit FAQs
Does Marquette County issue building permits?
Yes. Its Building and Mechanical Code applies everywhere except the Town of Springfield, the Villages of Endeavor, Neshkoro and Oxford and the City of Montello, with General Engineering Company as inspector.
Do I need a zoning permit for a shed?
Yes, for any shed or accessory structure of 100 square feet or more in a county-zoned town; the fee is $75.
How much is a building permit for a new house?
$0.33 per square foot including garage, decks and basement, with an $847 minimum, plus $94 plan review, $165 erosion control, $94 occupancy and a $40 seal.
Which towns have no county zoning?
Shields and Springfield, although county shoreland zoning still applies near lakes and streams there.
How much is a septic permit?
$375 for a conventional system and $475 for a mound, at-grade or in-ground pressurized system, plus plan review of $125 or $250.
How far from the water must I build?
At least 75 feet from the ordinary high-water mark of navigable waters, and from wetlands in county-zoned towns.
When does the Board of Adjustment meet?
On the last Thursday of the month at 1:00 p.m.; applications received by the end of a month are heard the following month.
What is the smallest house allowed?
In the zoned towns, 400 square feet of year-round living area and at least 20 feet wide.
Simplify Marquette County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Wisconsin. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Marquette County sooner?
Let Alliance prepare, file, and track your Marquette County permits while your crew stays on the job.
More Wisconsin permitting guides
Adams County
Read guide →Columbia County
Read guide →Marinette County
Read guide →Marshfield Building Permit Guide
Read guide →Menasha Building Permit Guide
Read guide →Menomonee Falls Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Marquette County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.