Inside the City of Manitowoc, permits come from the Building Inspection Department (Division of Life Safety) at City Hall, 900 Quay Street, (920) 686-6940, led by Inspection Supervisor Scott Keil. DSPS lists the city as a delegated agent for the Uniform Dwelling Code, and the city is also a delegated municipality for commercial plan review through E-Plan Exam. Permits are requested and tracked in MyGov, and the Common Council’s fee schedule (version October 28, 2025) prices a new house at $0.17 per square foot plus plan review, occupancy and the state seal.
What requires a building permit in Manitowoc?
New construction, additions, alterations, repairs, demolition and any electrical, HVAC or plumbing work need a permit before work starts, and one project may need several permits and a plan review. Its Permit Requirements sheet for one- and two-family homes (version October 2026) spells out the common cases.
Permit required
- New houses, additions, garages and sheds over 120 square feet
- Decks, porches, ramps and steps, new or replaced
- New, replaced or moved doors, windows and skylights
- Fences, new or replaced, and pools of every kind, including inflatable pools and outdoor spas
- Roofing or siding jobs covering more than 25% of the surface
- Furnaces, boilers, fireplaces and central air (HVAC and electrical permits)
- Structural changes, gutting, new or removed walls and changes to exits or stairs
- Finished basements; bathroom and kitchen remodels with new cabinets, fixtures, fans or appliances
- Water heaters, sump pumps, new circuits and service upgrades
- Placing a manufactured home built on or after April 1, 2007, demolition, and moving a building over a city street
No permit
- Sheds of 120 square feet or less (setbacks and four corner hold-downs still apply)
- Replacing only the decking boards on a deck
- Replacing 25% or less of the roofing or siding
- Size-for-size roofing, siding, door or window work on a detached garage
A shed over 120 square feet is limited to 720 square feet in wood or metal framing and 1,200 square feet in masonry, and needs a 4-inch slab with a thickened edge.
What Manitowoc decides and what the state holds
The construction standards are state codes: the city’s application binds every project to the Uniform Dwelling Code, the Commercial Building Code, the Wisconsin Plumbing Code and the National Electrical Code. The city sets its own fees, runs zoning under Chapter 15 (with floodplain zoning in Section 15.490), keeps local building, plumbing and electrical chapters (16, 17 and 18), registers contractors, and requires rental units to be registered under Ordinance 16.140. Short-term rentals are licensed by the Manitowoc County Health Department, not the city.
Manitowoc building department: who handles permitting
The department has its own building, electrical, plumbing and housing inspectors, and also handles zoning, signs, fences, floodplain and variances. The DSPS list of UDC delegated agents (current as of September 24, 2026) shows the City of Manitowoc with its own delegation, so new one- and two-family homes are permitted and inspected by city staff. Land outside the city limits lies in surrounding towns such as Manitowoc and Manitowoc Rapids, which hold their own UDC delegations on the same list.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Building Inspection Department, Division of Life Safety, City Hall, 900 Quay Street, Manitowoc, WI 54220 |
| Phone | (920) 686-6940 |
| Hours | Monday to Thursday 7:30 a.m. to 5:00 p.m.; Friday 7:30 to 11:30 a.m.; drop box on the west side |
| Department head | Scott Keil, Inspection Supervisor |
| Online | MyGov portal for applications, invoices, plan corrections and inspection requests |
| Commercial plan review | E-Plan Exam (general line 414-296-2144), or the city for small projects |
| Streets, driveways, erosion control | Engineering Department, (920) 686-6910 |
| Addresses for new homes | Community Development, (920) 686-6930 |
Manitowoc permit types
Every contractor and tradesperson working in the city creates a MyGov user account and completes a Manitowoc contractor registration at no charge, online or on a paper form. The MyGov name must match the person named on the Wisconsin credential, because that name prints on the permit, and the registration lapses when the state credential on file expires. The city posts separate forms for building, deck, demolition, electrical, fence and wall, fire suppression, HVAC, manufactured home, moving, plumbing, pool, sign and tower or antenna permits.
Residential permits
The building permit application (version January 2026) asks whether the applicant is a contractor or the owner, the contractor’s Dwelling Contractor and Qualifier numbers for one- and two-family work, and the labor and material cost without the mechanical, electrical and plumbing work, which each need their own permit. An owner of a one- or two-family home signs the state Cautionary Statement. Each project type has a checklist on the form; an addition, for example, needs a site plan, footing and foundation plan, a cross section and a floor plan with framing.
A new one- or two-family house starts with an address from Community Development and the DSPS online permit form, which the city says 2015 Wisconsin Act 211 requires for every new dwelling. The packet then goes to Building Inspection: one copy of the DSPS form, two sets of construction plans, two sets of energy calculations, and two sets of plot and erosion plans prepared by a surveyor.
Building or remodeling a home here? Alliance handles home building permits, so the crew isn't waiting on the counter.
Commercial permits
The city partners with E-Plan Exam and is recognized by DSPS as a delegated municipality for commercial plan review, so building, HVAC, plumbing, fire alarm and sprinkler plans that would usually go to the state under SPS 361–366 and 380–387 can be sent to E-Plan Exam instead. E-Plan Exam contacts the applicant about its fees and guarantees a 15-day turnaround from a complete, paid submission. New buildings under 5,000 square feet and alterations under 10,000 square feet may be reviewed by the city itself. Either way, one hard copy of the approved plans and the approval letter goes to Building Inspection with the permit application.
Not sure this scope needs a permit?
Get a free quote →For tenant improvements and new commercial builds, Alliance handles commercial permit filing through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning. Building Inspection checks land use, setbacks, signs and fences against Chapter 15 and issues zoning verification letters.
- Variances. The Zoning Board of Appeals meets as needed on the third Tuesday at 5:00 p.m. at City Hall. File by the last Tuesday of the month before, with the $300 processing and publication fee, and show all three hardship tests.
- Site plan and design. New development and redevelopment may need site plan, landscaping and downtown design approvals before a permit issues.
- Erosion control and stormwater. The Engineering Department issues these permits under Chapters 28 and 29; a project disturbing 2,000 square feet or more, moving 200 cubic yards of soil, laying 300 feet or more of pipe or cable, or working on slopes over 12% needs one.
- Floodplain. Staff make floodplain determinations under Section 15.490.
- Utilities, sidewalks and driveways. Manitowoc Public Utilities sets up electric and water service; Engineering issues sidewalk, driveway and right-of-way permits online.
Manitowoc permit costs and fees
The Common Council adopts the fee schedule; the posted copy is version October 28, 2025. The schedule says fees are due at application, while the fee page says the amount is set after review, so use the MyGov fee estimator and expect an invoice. Area fees use exterior dimensions and include the garage and every finished floor; valuation fees count all construction except HVAC, electrical and plumbing, rounded up to the next thousand.
Rather talk it over?
Call 1-855-478-4290 →| Work | Fee |
|---|---|
| New one- or two-family dwelling or addition | $0.17 per sq ft, $50 minimum |
| Plan review: new house / addition / alteration | $100 / $75 / $25 |
| Occupancy permit | $75 per dwelling unit; $125 per commercial unit |
| Wisconsin permit seal (state charge) | $5 |
| Residential, multifamily or commercial alteration; other building alterations | $10 per $1,000 of value, $50 minimum |
| Multifamily or commercial new building or addition | $0.25 per sq ft, $50 minimum; plan review $300, waived if state approved |
| Detached garages and sheds | $0.25 per sq ft, $50 minimum, plus $25 plan review |
| Decks, porches, ramps; pools and spas; signs | $50 each plus $25 plan review |
| Fences | $25 plan review |
| Re-roofing or residing | $10 per $1,000 of value; $50 minimum, $500 maximum per building |
| Demolition | $50 per building plus $0.05 per sq ft, $500 maximum |
| Early start for footings and foundation | $50 garage or shed; $100 house; $200 multifamily or commercial |
| Moving a building over a public way | $75 under 500 sq ft; $175 for 500 sq ft or more |
| Electrical or plumbing permit | $35 up to $500 of work, rising by bands to $200 at $10,000, then $20 per extra $1,000 |
| HVAC heating unit | $50 up to 150,000 BTU, $15 per extra 50,000 BTU, $850 maximum |
| Air conditioning | $50 up to 3 tons, $15 per extra ton, $850 maximum |
| Duct systems / commercial exhaust hood | $1.40 per 100 sq ft, $30 minimum / $100 per unit |
| Reinspection; special inspection; no final called | $75; $125; $50 |
| Zoning variance | $300 |
Worked example from the schedule: a new single-family house measuring 2,400 square feet including the garage and finished floors costs 2,400 × $0.17 = $408, plus $100 plan review, $75 occupancy and the $5 state seal, or $588 before the separate electrical, HVAC and plumbing permits. Starting work before the permit doubles the total fee, except in emergencies. Erosion control permits from Engineering carry a $75 base fee for the first acre, and a right-of-way excavation permit is $100.
Trade permits and who may pull them
Electrical, HVAC and plumbing permits are separate from the building permit and are filed by the contractor who does the work, who must be registered with the city. The department’s own sheet sets out who may apply:
- Building: a certified Dwelling Contractor with a Dwelling Contractor Qualifier, unless the work is on an existing one- or two-family home occupied by its owner, who may then pull the permit and do the work.
- Electrical: a licensed electrician, unless the work is on an existing single-family home occupied by its owner. Work on the main service must be done by a licensed electrical contractor in every case, and the city’s electrical inspector checks the service before Manitowoc Public Utilities connects it.
- HVAC: an HVAC contractor holding the state credential (DSPS registers HVAC businesses), or the owner-occupant of an existing one- or two-family home.
- Plumbing: a licensed plumber, unless the work is on an existing single-family home occupied by its owner. Sewer and water laterals are inspected before they are covered.
- Fire suppression, signs and towers each have their own permit form.
Rather not deal with the building department?
Get a free quote →How to apply for a Manitowoc building permit
Use the Permit Requirements sheet and the project handouts, or call (920) 686-6940.
Create a MyGov account and complete the free Manitowoc contractor registration; homeowners create an account to apply and track their permit.
Confirm setbacks, file any variance, and get erosion control, stormwater or site plan approvals the project needs.
Fill in the building permit application with the project checklist; for a new house add the DSPS online form, plans, energy calculations and surveyed plot and erosion plans.
Submit in MyGov or at City Hall, then pay the invoice online; commercial projects attach the E-Plan Exam or state approval.
Each electrical, HVAC and plumbing contractor applies separately before starting.
Review, corrections and what causes delay
Incomplete new-home packets are returned without review. Plan review comments arrive by e-mail to the MyGov login address and are answered in the portal, so a shared company address keeps corrections from being missed. A contractor whose state credential has expired loses the local registration until proof of renewal is filed, which holds up any permit naming that contractor.
Inspections in Manitowoc
Required inspections are printed on the issued permit. Request them at least 24 business hours ahead by phone, e-mail or MyGov; they are booked first come, first served, and no work may be covered until it passes.
- Building: footing (before the pour), foundation (before backfill), slab on grade, rough-in after framing, insulation, final, and final occupancy before anyone moves in.
- Electrical: service, underground work, rough-in, above-ceiling and final.
- HVAC: rough-in of venting, ducts and gas piping, above-ceiling and final.
- Plumbing: underground, rough-in, sewer and water laterals, and final.
If no final inspection is requested and the permit expires, the project is archived as incomplete and the work is treated as unapproved. New homes and additions receive an occupancy permit at $75 per unit; rental units must then be registered with the city within 30 days of being occupied.
Wisconsin building code in Manitowoc
Manitowoc enforces the state codes through its own delegation and the local chapters on its code resources page. FEMA’s Community Status Book lists the city (community 550240) as participating in the National Flood Insurance Program, with a current flood map dated February 23, 2023, and Building Inspection staff make floodplain determinations under Section 15.490 of the zoning code.
Want this handled start to finish?
Get a free quote →Wisconsin's Uniform Dwelling Code covers one- and two-family homes. Its Commercial Building Code covers public buildings, workplaces and buildings of three or more units. Local ordinances must conform to both. Wisconsin rules
Manitowoc permit search and official resources
To see what has been permitted at an address, use the Address Lookup in the MyGov public portal, which lists all permit and request activity at a location. Copies of older permit files or plans go through the city’s open records request portal, or call Building Inspection at (920) 686-6940.
- Building Inspection Department
- Permits, forms and contractor registration
- Permit fee schedule (version 10/28/2025)
- MyGov permit fee estimator
- MyGov public portal and address lookup
- Building permit application (January 2026)
- Permit requirements for one- and two-family homes
- New home construction steps
- Plan review and E-Plan Exam
- Inspections and scheduling
- Fence and wall handout
- Accessory structure handout
- Deck, ramp and stair handout
- Variance process and Zoning Board of Appeals
- Floodplain
- Erosion control permits (Engineering)
- Right-of-way permits
- Rental registration, Ordinance 16.140
- DSPS UDC delegated agents list
- FEMA Community Status Book, Wisconsin
Inspections are where schedules slip.
Get a free quote →Manitowoc building permit FAQs
Do I need a permit for a shed in Manitowoc?
Not for a shed of 120 square feet or less, which still has to meet setbacks and be anchored with four hold-downs; a larger shed needs a building permit at $0.25 per square foot plus $25 plan review.
How much is a permit for a new house?
$0.17 per square foot of gross area including the garage, plus $100 plan review, $75 occupancy and the $5 state seal; a 2,400-square-foot house comes to $588 before trade permits.
Does a fence need a permit?
Yes, every new or replacement fence or wall. Within the required front yard a fence may be 4 feet high, and within side and rear yards 6 feet.
Can I do my own electrical or plumbing work?
Only on an existing single-family home you own and live in, and never on the main electrical service, which needs a licensed electrical contractor.
Do contractors have to register with the city?
Yes. Every contractor and tradesperson completes a free Manitowoc registration in MyGov, which lapses when their state credential expires.
Who reviews commercial plans?
E-Plan Exam, for the city as a DSPS-delegated municipality, with a guaranteed 15-day turnaround; small projects may be reviewed by the city.
How do I schedule an inspection?
Call (920) 686-6940, e-mail the department or request it in MyGov at least 24 business hours ahead.
Do I need a permit to re-roof?
Yes, if more than 25% of the roof is replaced; the fee is $10 per $1,000 of value, between $50 and $500 per building.
Simplify Manitowoc permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Wisconsin. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Manitowoc sooner?
Let Alliance prepare, file, and track your Manitowoc permits while your crew stays on the job.
More Wisconsin permitting guides
Manitowoc County
Read guide →Sheboygan County
Read guide →Kewaunee County
Read guide →Marathon County Building Permit Guide
Read guide →Marinette Building Permit Guide
Read guide →Marinette County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Manitowoc permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.