Skip to main content
Municipal GuideWisconsinAllouez · Village

Allouez, Wisconsin Building Permit Guide

To get a building permit in Allouez, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

The Village of Allouez issues its own building, electrical, plumbing and HVAC permits through an online iWorQ portal, with inspections by its contracted firm, McMahon Associates.

Authority: Village of Allouez Community DevelopmentCode: Wisconsin UDC and Commercial Building Code; Allouez Chapter 225 feesPhone: 920-448-2800
Village Hall
1900 Libal StreetMonday–Thursday 7–4:30, Friday 7–11
Apply
iWorQ online portalBuilding, electrical, plumbing, HVAC
Review
Budget 7–14 daysInspections: 3–7 days to schedule
New home
$5,910 construction feeFee schedule dated Aug. 18, 2026

In the Village of Allouez, Community Development at Village Hall (1900 Libal Street, Green Bay; 920-448-2800) issues building, electrical, plumbing and HVAC permits through the village’s iWorQ portal, and the village holds its own state delegation for new one- and two-family homes. McMahon Associates carries out most inspections under contract. The village asks applicants to budget 7 to 14 days for review and 3 to 7 days to get an inspection, and its Chapter 225 fee schedule (dated August 18, 2026) sets a $5,910 construction fee for a new house.

What requires a building permit in Allouez?

The village’s own summary is that most construction projects require a building permit. Its fee schedule shows what it permits: new one- and two-family homes, additions, remodels, structural changes, foundation repair, accessory buildings of 200 square feet or more and other permanent structures, decks and porches, razing, and separate electrical, plumbing and HVAC permits, including water heater and HVAC unit replacements and solar panels.

Building or trade permit

  • New homes, additions, remodels and structural changes
  • Accessory buildings 200 sq ft and larger
  • Decks and porches
  • Electrical work, including solar panels
  • Plumbing work and water heater replacement
  • HVAC work and unit replacement
  • Razing a building
  • Commercial construction and grease traps

Zoning or public works permit

  • Sheds under 200 sq ft, fences, gazebos and pools
  • Driveway curb cuts and new street access
  • Sewer, storm and water laterals
  • Street excavation
  • Erosion control and stormwater
  • Permanent and temporary signs
  • Mobile storage units and construction dumpsters
  • Work near the Fox and East Rivers or in the floodplain

What the village decides and what the state holds

Allouez sets the local layer: zoning under Chapter 475, the Shoreland-Wetland Zoning Ordinance in Chapter 468, floodplain rules in Chapter 453, historic preservation, sign rules and the fees in Chapter 225. Its shed sheet, for example, keeps an accessory structure no higher than 15 feet, behind the front plane of the house and anchored to the ground, and it may never be used as living space. Building standards are the state’s: the Uniform Dwelling Code for one- and two-family homes and the Commercial Building Code for everything else, with state plan approval for larger commercial projects.

Allouez building department: who handles permitting

The Community Development department handles building and zoning permits, and the village is on the state’s list of municipalities with their own delegation for new one- and two-family dwellings. Trevor Fuller, Director of Planning and Community Development, answers zoning questions. Building-code questions, including sheds over 200 square feet, go to McMahon Associates’ inspection team, which the village contracts for most of its inspections; fences and sheds under 200 square feet go to the village’s Neighborhood Compliance Inspector.

Short on time to read all of this?

Get a free quote →
Allouez permitting contacts
OfficeContact
Village Hall, Community Development1900 Libal Street, Green Bay, WI 54301; 920-448-2800; Monday to Thursday 7:00 a.m. to 4:30 p.m., Friday 7:00 to 11:00 a.m.
Inspections (McMahon Associates, under contract)inspections@mcmgrp.com; 920-751-4200 ext. 260
Fences and sheds under 200 sq ftNeighborhood Compliance Inspector, 920-448-2800 ext. 121
Closing a permitinspections@villageofallouezwi.gov or 920-448-2800
Laterals, street access, excavation, stormwaterPublic Works Department, Village Hall
Floodplain maps and elevation certificatesBrown County Planning and Land Services, Zoning Division, 305 E. Walnut St., Room 320, Green Bay; 920-448-6480

Allouez had 13,838 residents in the 2025 Census estimate. The village, not Brown County, issues building permits for every address inside it, while the county’s zoning division keeps the flood maps and elevation certificates the village points residents to.

Allouez permit types

Building, HVAC, electrical and plumbing applications are filed online through the village’s iWorQ portal. Before applying, the village asks for detailed plans, the scope of work and supporting documents such as structural or electrical plans, and the state license numbers of every trade professional working on the job.

Residential permits

A new one- or two-family home goes through plan review and a construction permit valid for 24 months; an early-start permit for footings and foundations is available. Additions, remodels, structural changes, foundation repairs and accessory buildings of 200 square feet or more take a residential modification permit valid for 12 months, which includes two inspections but not the trades. Decks and porches have their own permit with footing, framing and final inspections. The village posts information sheets on the R1 and R2 districts, fences, driveways, parking, pools, decks and sheds.

Rules on the village’s January 2026 project sheets
ProjectKey rules
FencePermit for any fence 30 inches or higher, with a site plan; 3 feet maximum in the front yard and 6 feet on side and rear lines; clear sight triangles 30 feet back at street corners and 15 feet at driveways; never over the property line
DeckDrawing of size, location and materials; footing, foundation, framing and final inspections; behind the front plane of the house, 4 feet from a side line and 2 feet from the rear line; a front stoop may not exceed 25 square feet
Pool, hot tub or pond deeper than 18 inches48-inch fence with a lockable gate; permanent pools 10 feet and above-ground pools 4 feet from side and rear lines; a hot tub with an ASTM F1346 cover needs no fence
R1-75 lot7,500 sq ft and 75 feet of frontage; 30-foot front setback, side yards 6 feet each and 14 in total, rear yard 20 percent of the lot depth (15 to 30 feet); 2.5 stories or 35 feet; accessory buildings up to 1,200 sq ft (900 in R1-50)

Not sure this scope needs a permit?

Get a free quote →

Those sheets list a $50 permit fee for decks and pools, which matches the zoning review fee in Chapter 225; the schedule also charges a $480 deck or porch building permit that includes the three inspections.

Commercial permits

Commercial projects pay a plan review fee when review is required, and construction, electrical and plumbing permits at $500 plus 25 cents per square foot. A commercial building, a new home and some other projects need a certificate of occupancy, issued only after the final inspections pass and the permit is closed. Commercial erosion control and post-construction stormwater permits come from Public Works under Chapter 385.

What comes before the building permit

  • Zoning approval. Each building permit carries a zoning review fee; rezonings, conditional uses and other procedures follow Table 11-1 of Section 475-1101, with an application fee plus noticing and publication costs per meeting.
  • Shoreland. Work within 300 feet of the Fox River or the East River, or on the landward side of the 100-year floodplain, needs a permit under Chapter 468, for buildings, decks and patios as well as shoreline vegetation removal and filling or grading.
  • Floodplain. A floodplain land use permit under Chapter 453.
  • Historic property. A Certificate of Appropriateness before exterior changes to a locally designated landmark.
  • Laterals and driveways. Public Works permits for sewer, storm and water laterals, a new street access or a street excavation; no curb may be cut before the driveway permit.

Allouez permit fees

Fees are in Chapter 225 of the village code; the schedule on the Codes and Policies page is dated August 18, 2026, and its building and zoning amounts match the May 2025 version. Starting work before the permit is issued doubles the fee.

Rather talk it over?

Call 1-855-478-4290 →
Allouez building fees (Chapter 225, Aug. 18, 2026)
PermitFee
New 1–2 family dwelling: plan review$170
New dwelling: construction (10 listed inspections plus 2 re-inspections included)$5,910
New dwelling: state seal / administrative fee$50 / $100
New dwelling: erosion control permit / final yard grade deposit$100 / $2,000 per parcel
Early start (footings and foundations)$960
Certificate of occupancy / temporary occupancy deposit$50 / $1,000 per unit
Residential modification building permit (two inspections) / plan review$330 / $80
Residential electrical, plumbing or HVAC permit (one inspection)$170 each
Water heater or HVAC unit replacement$50 per unit
Deck or porch (three inspections)$480
Residential raze permit$330
Extra inspection or re-inspection / failure to call for inspection$170 / $50
Commercial plan review / early start$330 / $960
Commercial construction, electrical or plumbing$500 plus $0.25 per sq ft each
Commercial HVAC$250 per unit
Zoning review: new dwelling or addition / accessory, fence, deck, pool$100 / $50
Zoning review: new commercial / change of use$200 / $75
Curb cut, home or duplex / other buildings$50 / $100
Lateral connection, residential / non-residential$100 / $200 per lateral
Floodplain land use permit, home or duplex / other$50 / $75
Commercial erosion control / post-construction stormwater$250 / $1,000, plus inspection fees

Worked example. The 225.02 items for a new house add up to $6,380: plan review $170, construction $5,910, state seal $50, administrative fee $100, erosion control $100 and the certificate of occupancy $50. The zoning review adds $100, for $6,480, and the $2,000 final yard grade deposit is collected as well. Lateral connections and the plumbing fixture fee in Section 225.09 (up to six fixtures for $40, then $5 each) are listed separately.

The building page quotes a permanent sign fee of $75 plus 50 cents per square foot and no fee for a temporary sign, while the adopted Chapter 225 schedule lists $100 for a sign and $30 for a 30-day temporary sign; the schedule is the adopted figure.

Trade permits and who may pull them

Electrical, plumbing and HVAC permits are separate iWorQ applications, each including one inspection on residential work; on a new house the construction fee already covers the electric service, underground plumbing, rough electrical, rough plumbing and rough HVAC inspections. The village asks for the trade license numbers on the permit.

Rather not deal with the building department?

Get a free quote →
  • Plumbing. Section 225.09 sets plumbing permit fees by fixture for homes and duplexes and by floor area over 10,000 square feet for other buildings; private water wells are not allowed.
  • Builders. A contractor on a new one- or two-family home needs the state Dwelling Contractor certification and a Dwelling Contractor Qualifier; an owner-occupant is exempt.
  • Electricians and plumbers. State licenses from DSPS.
  • HVAC. State registration; the village’s pages show no local HVAC license.
  • Solar. A photovoltaic plan review is $80 on top of the electrical permit.

How to apply for an Allouez permit

1. Check zoning

Read the district sheet and ask the Director of Planning about setbacks or approvals.

2. Prepare the file

Plans, scope of work and every contractor’s license number.

3. Apply in iWorQ

File the building application, then the electrical, plumbing and HVAC permits.

4. Add public works permits

Laterals, street access, excavation and erosion control as needed.

5. Wait for approval

Allow 7 to 14 days for review; the village says when the permit is ready.

6. Post and build

Post the permit for remodels, additions and new buildings, and book inspections.

7. Close the permit

After the final, close it with the village to get any certificate of occupancy.

Review, corrections and what causes delay

The building department checks each application against the building codes, zoning and safety rules and notifies the applicant when the permit is approved. The village’s planning window is 7 to 14 days for review and 3 to 7 days to schedule an inspection. Projects that need a rezoning, conditional use, sign exception or historic preservation review wait for the meetings the code requires (sign exceptions go to the Plan Commission and the Village Board), and each meeting adds noticing and publication costs.

Inspections in Allouez

Book inspections with McMahon Associates by email or phone. A new house fee covers the footing, foundation, electric service, underground plumbing, rough-in, rough electrical, rough plumbing, rough HVAC, energy and final inspections and two extra or re-inspections; each further inspection is $170, and failing to call for a required inspection costs $50.

After the final inspection passes, close the permit with the village by email or at 920-448-2800; a certificate of occupancy for a new home or commercial building is issued only once the permit is closed. Residential permits are valid for 12 months (24 months for a new home), and a renewal is $170 for each inspection still required.

Want this handled start to finish?

Get a free quote →

Wisconsin building code

Allouez enforces the state codes through its own delegation and contracted inspectors, and its local rules sit in the village code chapters on zoning, shoreland-wetland zoning, floodplain, erosion control and stormwater, signs and fees. FEMA’s Community Status Book lists Allouez as participating in the National Flood Insurance Program, community 550612, with a current map dated May 9, 2023, and in class 6 of the Community Rating System, a 20 percent flood insurance discount; the village credits its flood mitigation work for that rating.

Wisconsin's Uniform Dwelling Code covers one- and two-family homes. Its Commercial Building Code covers public buildings, workplaces and buildings of three or more units. Local ordinances must conform to both. Wisconsin rules

Allouez permit search and official resources

Permit applications are filed in the village’s iWorQ portal, and the village publishes its annual new housing fee report and housing affordability report under Act 243. For permit records, ask Community Development at 920-448-2800.

Inspections are where schedules slip.

Get a free quote →

Allouez building permit FAQs

How much is a building permit for a new house in Allouez?

The construction fee is $5,910, and with plan review, seal, administrative, erosion control and occupancy fees the 225.02 items total $6,380, plus a $100 zoning review.

Do I need a permit for a shed?

Yes. Sheds under 200 square feet take a $50 zoning permit; larger ones need a building permit.

How long does review take?

The village asks applicants to budget 7 to 14 days, and 3 to 7 days to schedule an inspection.

Who does the inspections?

McMahon Associates, under contract with the village; email inspections@mcmgrp.com or call 920-751-4200 ext. 260.

How long is a permit valid?

Twelve months, or 24 months for a new one- or two-family home.

Do I need a permit to widen my driveway?

A curb cut needs a $50 permit for a home, and a new street access needs a Public Works permit; driveways are limited to 30 feet wide at the curb.

Can I apply online?

Yes. Building, electrical, plumbing and HVAC applications are all in the iWorQ portal.

Simplify Allouez permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Wisconsin. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Allouez sooner?

Let Alliance prepare, file, and track your Allouez permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Allouez permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.